So have any class 380 units actually entered serive on the Ayrshire Coast/Inverclyde line services yet!
Is that a statement or a question?
What is a serive?
The Class 380 units were due to enter limited
service during September
However, due to issues with the wheelsets, resulting in late delivery, this was pushed back to mid October
Then we had the "non-multi" issue, which has resulted in a software upgrade in the units already in Britain (but does not appear to have been applied to all the other units outwith Britain)
Later that same evening one unit had some damage, which suspended the fleet for a week
I was informed last week that it was hoped to get some additional tests carried out this weekend, in an attempt to clawback some lost time, as none had originally been planned for weekends
GBRf had also originally planned for two crews for testing purposes, but due to the suspension they reallocated their staff and when operations commenced they could only supply one
From next week they will only be supplying one, as ScotRail drivers take over for all other runs; GBRf will continue to provide one crew for testing of new units to Carstairs and Carlisle