Interesting - who've they got in mind to refurbish the units for? Given that they're quite long in the tooth now, and that both AGA & London Overground are replacing them wholesale with Aventras, they must be bound for somewhere if PRM works are to be undertaken now.Wabtec tendering for 27 Class 317 prm only
Which according to Wiki are ~5 years older than the 24x 317/6 (also AGA-operated)Crunching numbers, it seems that the 15 317/5s and 12 317/1s (the ex-GN ones) are the possible contenders.
A mix of 317/5 ,7,8 , angel ones I think , toilet supply by alti I’m hearing
All 317s are Angel’s......A mix of 317/5 ,7,8 , angel ones I think , toilet supply by alti I’m hearing
This lot perhaps? https://rail.ricardo.com/rolling-stockAngel not doing the design work , some firm beginning with r, rickardo lol I’ll ask him tomorrow
Angel not doing the design work , some firm beginning with r, rickardo lol I’ll ask him tomorrow
And 27 4 car sets is more than a few
Which is all down to DfT not funding the work through franchise agreements. They were warned years ago by the TOCs and ROSCOs of the risks associated with dithering and delaying.You'd struggle to get any sympathy from the Gvt on this and the company are well aware of it. The PRM deadline has been known about for quite some time and nothing has been done to bring these units in line with the requirements.
Which is all down to DfT not funding the work through franchise agreements. They were warned years ago by the TOCs and ROSCOs of the risks associated with dithering and delaying.
Only one organisation to blame - the DfT.
GA/NR not done platform extension work to accommodate 10 car 720s (see extract of franchise agreement below), and not included in latest NR Enhancements Delivery Plan. So looks like GA will need some PRM 317s so they can run 8 car services to Hertford East, otherwise will be 5 car 720s only post 31-12-19 if platform work not done by then
105.2 Pursuant to paragraph 105.1 such changes to the infrastructure shall include such infrastructure works at each of Hertford East, Wickford, Manningtree, Kings Lynn, Elsenham, Ware, St Margarets and Enfield Lock Stations as are necessary to enable any Passenger Services comprised of 10 rolling stock vehicles to call at such Stations by no later than 1 September 2018
506 on Ilford - Carlisle under own power317506 due to be dragged to Kilmarnock from Ilford on Monday, PRM work starting?
GA/NR not done platform extension work to accommodate 10 car 720s (see extract of franchise agreement below), and not included in latest NR Enhancements Delivery Plan. So looks like GA will need some PRM 317s so they can run 8 car services to Hertford East, otherwise will be 5 car 720s only post 31-12-19 if platform work not done by then
105.2 Pursuant to paragraph 105.1 such changes to the infrastructure shall include such infrastructure works at each of Hertford East, Wickford, Manningtree, Kings Lynn, Elsenham, Ware, St Margarets and Enfield Lock Stations as are necessary to enable any Passenger Services comprised of 10 rolling stock vehicles to call at such Stations by no later than 1 September 2018