810022 is pencilled in to debut today, and can be searched on RTT

810022 (with modifications to improve door reliability) was in good form from a traction point of view on it's first day of operation in public service yesterday, accelerating in diesel mode northbound after Loughborough with run times between signals LR511 and NE4481 (min : sec) similar to other well performing sets:
30/06/26 810022 1D66 2:55 1F85 2:54
(on a check-out run last week on 3A26 on 25/06/26 2:53).

Contrasts with 810011 which was observed at Derby on Monday with the engine under vehicle 855011 silent and Loughborough acceleration times of 3:07 (1D66) and 3:06 (1F85).

With all engines providing traction the Class 810s are very noticeably around 9 sec slower accelerating northbound from Loughborough than well performing Meridians, and engine reliability still leaves a lot to be desired (study about to be published by the Railway Performance Society).
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,299
810022 (with modifications to improve door reliability) was in good form from a traction point of view on it's first day of operation in public service yesterday, accelerating in diesel mode northbound after Loughborough with run times between signals LR511 and NE4481 (min : sec) similar to other well performing sets:
30/06/26 810022 1D66 2:55 1F85 2:54
(on a check-out run last week on 3A26 on 25/06/26 2:53).

Contrasts with 810011 which was observed at Derby on Monday with the engine under vehicle 855011 silent and Loughborough acceleration times of 3:07 (1D66) and 3:06 (1F85).

With all engines providing traction the Class 810s are very noticeably around 9 sec slower accelerating northbound from Loughborough than well performing Meridians, and engine reliability still leaves a lot to be desired (study about to be published by the Railway Performance Society).
Is it confirmed it's had door modifications, that was only speculation on my part from observing the work underway at Merchant Park on the units.
 

WesternLancer

Veteran Member
Joined
12 Apr 2019
Messages
14,945
Not sure if images of these have previously been posted in the thread.
Aurora branded chocolates that I picked up one day earlier in the sprint at the Aurora new train EMR display stand at Sheffield station when passing through

There were also other EMR branded items (eg a small teddy bear with an EMR scarf) but I think this was the only 810 branded item - so probably good for the record to have these images in the thread.

It was good quality, tasty chocolate.
 

Attachments

  • IMG_6800.jpeg
    IMG_6800.jpeg
    3.4 MB · Views: 172
  • IMG_6799.jpeg
    IMG_6799.jpeg
    3.3 MB · Views: 168
  • IMG_6798.jpeg
    IMG_6798.jpeg
    3.1 MB · Views: 166
Last edited:

ajp999

Member
Joined
8 Aug 2022
Messages
97
Location
Nottingham
Appears that 810016 failed tonight on 1D90 1605 St Pancras to Nottingham and was terminated at Leicester following an extended station stop at Kettering.
 

60159

Member
Joined
26 Nov 2018
Messages
411
81016 back in service today. Worked Sheffield-St Pancras and 14.02 back
It was on the 13.35 Nottingham.
I copped it at West Hampstead Thameslink.
Not easy to get 810s in London as no number on the front. Difficult at St P and they go pretty quickly thro’ Kentish Town etc tho’ my eyesight not great.
Any tips?
 

50002Superb

Established Member
Joined
18 Aug 2021
Messages
2,074
Location
Nottingham
It was on the 13.35 Nottingham.
I copped it at West Hampstead Thameslink.
Not easy to get 810s in London as no number on the front. Difficult at St P and they go pretty quickly thro’ Kentish Town etc tho’ my eyesight not great.
Any tips?
The 810s have their number on the front?

It’s in silver just below the cab window.
 

Amos390

Member
Joined
22 Jan 2025
Messages
674
Location
Nottingham
Extremely small and only 3 digits, and can imagine very difficult at a fast speed
Yes, have seen a handful passing and they are difficult to read, they do also have a bit bigger of a number in the usual spot beneath the cab side window though, those are a bit easier to see.
 

NY SAARSS

On Moderation
Joined
22 Nov 2025
Messages
11
Location
Uranus
It was on the 13.35 Nottingham.
I copped it at West Hampstead Thameslink.
Not easy to get 810s in London as no number on the front. Difficult at St P and they go pretty quickly thro’ Kentish Town etc tho’ my eyesight not great.
Any tips?
do you use realtime trains ? mentioned on here almost weekly. try realtime trains.co.uk. put in a station name ie. West Hampstead thameslink. click submit. click the detailed box top right. you should see what is due for the next hour or so. Many train operating companies details are listed but not london overground. if there is a number of carriages listed on the right hand side of the page then click on that and then hopefully the train details will come up with the trains number on the page. Not always correct but a very useful tool to use. there is a small white box top right corner so if you are looking for a unit say 810022 enter number click and if the unit is working then it should tell you. there are differant versions of realtime trains i only use the free version so there are some adverts that do get in the way but if you get on with it then you could pay for extra services. give it a go many people on here use it so if you get stuck shout up and someone mostly TOM will post a very helpful comment to get you up and running.
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,299
Just been informed by a source from Hitachi that unit 810031 is now complete at Merchant Park, leaving just 032 and 033 to complete the production run.

There is also the test units and a couple of units with faults that need dealing with:-

001/003/004/005/007/008 and 009.

Also the elusive 810002.

I've also been told that Aycliffe will be taking on the crack repair work for the 8XX fleet and also the Scotrail 385s, so units should shortly start to return here for mods.
 

Amos390

Member
Joined
22 Jan 2025
Messages
674
Location
Nottingham
Just been informed by a source from Hitachi that unit 810031 is now complete at Merchant Park, leaving just 032 and 033 to complete the production run.

There is also the test units and a couple of units with faults that need dealing with:-

001/003/004/005/007/008 and 009.

Also the elusive 810002.

I've also been told that Aycliffe will be taking on the crack repair work for the 8XX fleet and also the Scotrail 385s, so units should shortly start to return here for mods.
Ooh that’s good news all round, nice that the 810s are neirly done off the line, and good that Newton Aycliffe have a bunch of jobs coming in the near and far future, I believe they also will have something to to with the HS2 trains as well?

However, there is also not so good news, 810022 failed just south of Clay Cross Jn earlier today on 1F50, blocking the MML north of Derby for a good half hour, before limping to Chesterfield, returning ECS to Derby and eventually after a bit returning to Etches.
 

BRcrosslane

Member
Joined
23 Jun 2024
Messages
60
Location
Sandbach
If it's a train fault then it would go against the fleet and be one on the total for the period. They need to get more in service and get the mileage run up to build service experience and help identify one off issues from build/maintenance and those endemic to the design. Given the experience with the the 80x fleets you would expect Hitachi to get the reliability sorted.
Should of stuck with the 125s, proven British reliability.
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,299
Ooh that’s good news all round, nice that the 810s are neirly done off the line, and good that Newton Aycliffe have a bunch of jobs coming in the near and far future, I believe they also will have something to to with the HS2 trains as well?

However, there is also not so good news, 810022 failed just south of Clay Cross Jn earlier today on 1F50, blocking the MML north of Derby for a good half hour, before limping to Chesterfield, returning ECS to Derby and eventually after a bit returning to Etches.
Yes off topic Aycliffe will assemble the shells for HS2 before they go by road to Derby who will fit out the shells.
 

Chris172

Member
Joined
3 Feb 2018
Messages
153
Wouldn't be surprised if Hitachi give EMR extra units as an apology. How late are they now?
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,299
Wouldn't be surprised if Hitachi give EMR extra units as an apology. How late are they now?
Discovered many times that will never happen.

The contract between the leasing company and Hitachi will have many penalty clauses in, one being delivery.

When delivery is late penalties will be imposed, and unseen to recall someone posting some accounts on here stating Hitachi have paid out many millions in penalty payments to date.

Even if they did give extra units, can the depot infrastructure cope with additional units?
 

Towers

Established Member
Joined
30 Aug 2021
Messages
2,964
Location
UK
Just been informed by a source from Hitachi that unit 810031 is now complete at Merchant Park, leaving just 032 and 033 to complete the production run.

I've also been told that Aycliffe will be taking on the crack repair work for the 8XX fleet and also the Scotrail 385s, so units should shortly start to return here for mods.
Which sets are going back for crack repairs - not the freshly built 810s, surely?!
 

D365

Veteran Member
Joined
29 Jun 2012
Messages
13,155
81016 back in service today. Worked Sheffield-St Pancras and 14.02 back
016 working the Sheffield route again today. Very comfortable air con by 810 standards.

For balance, 810016 on the 1250 Nottingham to London had water dripping from the air con in coach B!
Oops… that sounds a lot less comfortable. I was in coach C this morning.
 
Last edited:

londonmidland

Established Member
Joined
22 Dec 2009
Messages
2,346
Location
Leicester
810006 failed with the brakes stuck on this afternoon, after stepping up for a failed 222 - the 810 never managed to leave Derby.

Now, 810013 has terminated at Leicester, due to a fault on this train.
 

800001

Established Member
Joined
24 Oct 2015
Messages
7,299
Ah; is this in addition to the work being undertaken at Eastleigh or have they lost the contract?
Honestly not sure. Makes sense to move to Aycliffe saves leasing a building at Eastleigh.
 

fgwrich

Established Member
Joined
15 Apr 2009
Messages
10,608
Location
Hampshire
Ah; is this in addition to the work being undertaken at Eastleigh or have they lost the contract?
Not so much a contract lost at Eastleigh - Hitachi does the work in house and leases Bay 2 North & South and Bay 1 South from Arlington for it as part of Project Acer.

== Doublepost prevention - post automatically merged: ==

Honestly not sure. Makes sense to move to Aycliffe saves leasing a building at Eastleigh.
Also saves a long drag and conducting clearance work for the 385s.
 