New info in TfL Board papers for next weeks Safety committee

The detail of what was found and been tweaked is probably in non-public part 2, but appears current status is

3.3 reintroduction into service sometime May to September 2026

3.4 Investigations progressed well, testing was February to May

3.5 current status appears to be engaging with ORR on plans for reintroduction


I read that as TfL ready to reintroduce the trains, but waiting for ORR approval sign off. Not sure how much midnight oil ORR burns to expedite this process or if it will take weeks/months

== Doublepost prevention - post automatically merged: ==

Per latest TfL Board papers, Commissioners Report

page 17. "..... phased reintroduction expected to begin by late summer"


Seems to be inconsistent with the above May to September, late summer rather suggests end August or during September
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Taunton

Veteran Member
Joined
1 Aug 2013
Messages
12,218
Seems to be inconsistent with the above May to September, late summer rather suggests end August or during September
I think we had the same sort of generalised dates last year, and the first train was got going on the last possible day, September 30th. I guess the same will apply this time.

We still seem to have the same incessant sequence of weekend closures which have much reduced any value of the system outside weekdays. The Tower Gateway to Shadwell branch still seems the most affected
 
Last edited:

Mattplans

Member
Joined
27 Sep 2024
Messages
695
Location
London, UK
The Tower Gateway to Shadwell branch still seems the most affected
Are they reversing at Poplar or diverting to Bank nowadays? I was at Bank on 26/12 and I'm pretty sure I saw a Beckton train departing from there.

* Oops, noticed you said Shadwell. I thought it was Beckton!
 

Taunton

Veteran Member
Joined
1 Aug 2013
Messages
12,218
Three more days of closure of the east end of the system this coming weekend, including a non-holiday weekend Friday, along with no replacement buses provided. Those were always quite well used for weekend closure, but now it's use the regular buses - except that those over time have been reduced to basic north-south routes, deliberately because east-west uses the DLR here. I presume just money being saved by not having replacement buses. There's an inconsequential last line on the closure notice that "Normal bus fares will apply".

And if they're out testing how good the new trains are at stopping in the wet, looks like they've chosen the wrong weekend again ...
 

TheManWho

Member
Joined
15 Jul 2010
Messages
170
Three more days of closure of the east end of the system this coming weekend, including a non-holiday weekend Friday, along with no replacement buses provided. Those were always quite well used for weekend closure, but now it's use the regular buses - except that those over time have been reduced to basic north-south routes, deliberately because east-west uses the DLR here. I presume just money being saved by not having replacement buses. There's an inconsequential last line on the closure notice that "Normal bus fares will apply".

And if they're out testing how good the new trains are at stopping in the wet, looks like they've chosen the wrong weekend again ...
Low adhesion can be replicated, even in dry weather, with a solution applied to the running rails
 

Recessio

Established Member
Joined
4 Aug 2019
Messages
1,489
Location
London
Low adhesion can be replicated, even in dry weather, with a solution applied to the running rails
I'm sure I remember reading a story on these forums of someone meany years ago, who as a young apprentice was tasked with applying washing up liquid to the New Guildford line on a quiet Sunday...
 

Pakenhamtrain

Established Member
Joined
26 Jan 2014
Messages
1,201
Location
Melbourne, Australia

Mojo

Forum Staff
Staff Member
Administrator
Joined
7 Aug 2005
Messages
21,168
Location
0035
Just seen one of the “new” trains at Canning Town, so looks like they’re undergoing testing during this weekend’s closure.
 

Taunton

Veteran Member
Joined
1 Aug 2013
Messages
12,218
Just seen one of the “new” trains at Canning Town, so looks like they’re undergoing testing during this weekend’s closure.
At the present time it seems some parts of the system may as well have retreated to 5-day week operation. Goodness knows what any "test plan" looks like or how long this is all going to be going on for. Has it been two, or three, years since the first ones were delivered?

None of this stops large posters at stations claiming 99.999999 service reliability.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,015
Location
West Wiltshire
Likely be an update by Tuesday evening when latest TfL Board Programmes and Investment Committee papers are published for 1st July meeting. Although staff might choose to tell the Board something vague and lacking detail regarding timescale for trains to enter service.

Board papers from few weeks/months ago show big unbudgeted costs for the delay, and reading between the lines, suggests TfL (rather than CAF) are having to absorb cost, which suggests D23s are meeting contractual spec and delivery. Even looks like TfL are paying CAF to store the trains in Spain as apparently all built. However the wording in public papers is fluffy and avoids actually saying that TfL got trains built to spec that didn't match their infrastructure and signal braking distances.

 

81A

Member
Joined
22 May 2026
Messages
259
Location
UK
I’d imagine passengers will be missing the aircon the next few days… What is holding up introduction now? If TFL are paying presumably a signalling/other infrastructure issue and not an issue with the B23s themselves?
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,015
Location
West Wiltshire
I’d imagine passengers will be missing the aircon the next few days… What is holding up introduction now? If TFL are paying presumably a signalling/other infrastructure issue and not an issue with the B23s themselves?

TfL seem to know reasons, but aren't making it public, as per this snippet from latest Board committee papers, section 8.1.3
This investigation remains ongoing with our supply chain and relevant regulators, but our initial findings indicate a combination of factors contributed to the incident. Further details are provided in the paper on Part 2 of the agenda.

The minutes of previous meeting also give some clues, which I read as problem was TfL didn't understand its infrastructure (presumably signalling and braking distance), the new trains met spec so TfL pays, but train spec wasn't matched to infrastructure, so either trains or parts of the infrastructure (or both) now needed modifying.
Good progress had also been made with managing costs of the programme in line with the authorities approved by the Committee. The costs of investigating and resolving the cause of the incident at Canning Town was currently being assessed and any request for an increase in Authority would be brought back to the Committee.
The Committee noted the paper and the exempt supplementary information on Part 2 of the agenda; and noted that the values for which Authorities have been given and set out in the paper included commitments that extended beyond the period of the 2026/27 Budget, which was subject to approval by the Board, and the 2026 TfL Business Plan. Provision would, therefore, need to be made for those commitments in future budgets and business plans

The Board papers now seem to say hoping to reintroduce new trains sometime between May and September. Clearly May didn't happen and now in last week of June. And anyway says hoping to which doesn't sound like definite in that timescale
 

Taunton

Veteran Member
Joined
1 Aug 2013
Messages
12,218
I said 18 months ago on this thread (post 501) that the DLR management and technical staff just don't know how to handle this. And that's still my opinion. Further, reading the above, they are just issuing wiffle-waffle to the TfL Board, who equally appear unable to challenge the blandness.

Quite how "good progress with managing the costs of the programme" can be said at a point where the programme ought to be finished and wound up just escapes me, and probably escapes anyone else who has managed a project as well. Any word in the minutes about all the weekend journeys for us locals who live along the DLR being lost?
 

81A

Member
Joined
22 May 2026
Messages
259
Location
UK
the new trains met spec so TfL pays, but train spec wasn't matched to infrastructure, so either trains or parts of the infrastructure (or both) now needed modifying.
Train spec not matched to infrastructure?! You really couldn't make things like this up. Definitely fair for TFL to pay in that case though...
 

Taunton

Veteran Member
Joined
1 Aug 2013
Messages
12,218
Train spec not matched to infrastructure?! You really couldn't make things like this up. Definitely fair for TFL to pay in that case though...
Although you might hope the builder would notice, they must have made multiple trips to the DLR to see it in detail, and are supposed to be professional in this sort of thing.

Thinking they would go to CAF to save a bit on price compared to their old hands at Bombardier/Siemens, who had done multiple previous DLR builds and knew what they were doing is ending up costing TfL (and those of use who live on the line) very dear indeed. I do wonder what the National Audit Office will say.
 

Recessio

Established Member
Joined
4 Aug 2019
Messages
1,489
Location
London
Although you might hope the builder would notice, they must have made multiple trips to the DLR to see it in detail, and are supposed to be professional in this sort of thing.

Thinking they would go to CAF to save a bit on price compared to their old hands at Bombardier/Siemens, who had done multiple previous DLR builds and knew what they were doing is ending up costing TfL (and those of use who live on the line) very dear indeed. I do wonder what the National Audit Office will say.
But if TfL are the ones who misspecified the spec - rather than CAF not meeting the spec - how is that CAF's fault and how would Siemens/Bombardier have done any better?
 

35B

Established Member
Joined
19 Dec 2011
Messages
5,362
But if TfL are the ones who misspecified the spec - rather than CAF not meeting the spec - how is that CAF's fault and how would Siemens/Bombardier have done any better?
Absolutely. The customer are ultimately responsible for specifying the requirements so have to bear responsibility of what they buy performs to spec but can’t be used because of a deficient spec
 

Wolfie

Established Member
Joined
17 Aug 2010
Messages
7,392
Alstom or Siemens would have likely faced similar issues.
Well, if they'd built to spec (and not doing so potentially involves a world of hurt but some on here seem to think that should be the case) anyway....
 

SynthD

Established Member
Joined
4 Apr 2020
Messages
2,014
Location
UK
They do. It’s the Royal Mint Street works, the east half was built during closures several years ago.

Some construction-targeted detail in this pdf, including that there is a courtyard over the tunnel to keep it lightweight.
“Although the main part of the project is concrete-

framed, steelwork has provided the most efficient

solution to form two transfer structures that support

the building. By working closely with Network Rail

and TfL we have managed to find an efficient method

of installing this structure, while minimising the

effect on transport infrastructure,” explains Midgard

Project Director Andrew Henderson.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,015
Location
West Wiltshire
The latest TfL Board Finance report is showing the damaging effect of additional line closures for testing the new trains.

Per page 4, DLR journeys are 8% lower than previous year.

As this is in a Board Finance document, it is obviously on TfLs radar, even if there is no comment or explanation why (the comment is combined with one saying Trams 8% up) which rather masks significance of DLR fall

 

DGP

Member
Joined
31 Mar 2024
Messages
121
Location
London
The latest TfL Board Finance report is showing the damaging effect of additional line closures for testing the new trains.

Per page 4, DLR journeys are 8% lower than previous year.

As this is in a Board Finance document, it is obviously on TfLs radar, even if there is no comment or explanation why (the comment is combined with one saying Trams 8% up) which rather masks significance of DLR fall

Replied but got my Maths wrong. Very wrong!
 
Last edited:

Zeremony

Member
Joined
28 May 2022
Messages
48
Location
London
Basically expecting people to pay twice for what’s normally one journey. DLR are very good at doing that
Having ridden on a lot of the rail replacement buses during DLR closures, they are all free.

My biggest gripe with them is them not running during Prince Regent to Beckton closures.
 

Redistou

Member
Joined
9 Feb 2026
Messages
8
Location
Hayes, Kent
Lewisham<>Bank and Lewisham <> both seem to have dropped down to less than 12 trains / hr. Poor travellers like me trying to Lewisham <> Stratford are being triple hit; Direct has been replaced by a change that often doesn't co-incide, the trains are fuller than before and changing half way through means a bun fight getting on to a new train mid-service. Ive mostly switched to cycling and last time I tried it took nearly an hour to complete the journey. (5:20 at stratford <> 6:10 at lewisham )
 