New info in TfL Board papers for next weeks Safety committee
The detail of what was found and been tweaked is probably in non-public part 2, but appears current status is
3.3 reintroduction into service sometime May to September 2026
3.4 Investigations progressed well, testing was February to May
3.5 current status appears to be engaging with ORR on plans for reintroduction
I read that as TfL ready to reintroduce the trains, but waiting for ORR approval sign off. Not sure how much midnight oil ORR burns to expedite this process or if it will take weeks/months
== Doublepost prevention - post automatically merged: ==
Per latest TfL Board papers, Commissioners Report
page 17. "..... phased reintroduction expected to begin by late summer"
Seems to be inconsistent with the above May to September, late summer rather suggests end August or during September
The detail of what was found and been tweaked is probably in non-public part 2, but appears current status is
3.3 reintroduction into service sometime May to September 2026
3.4 Investigations progressed well, testing was February to May
3.5 current status appears to be engaging with ORR on plans for reintroduction
I read that as TfL ready to reintroduce the trains, but waiting for ORR approval sign off. Not sure how much midnight oil ORR burns to expedite this process or if it will take weeks/months
== Doublepost prevention - post automatically merged: ==
Per latest TfL Board papers, Commissioners Report
page 17. "..... phased reintroduction expected to begin by late summer"
Seems to be inconsistent with the above May to September, late summer rather suggests end August or during September