HS2 Reset: Evidence to Transport Committee - 9 July 2025 "Total overspend on high-speed rail could be as much as 100%"

mmh

Established Member
Joined
13 Aug 2016
Messages
4,245
Getting more frequent services because your local line isn't full of trains whipping past isn't a benefit?
Hint: the people who have to suffer the construction aren't in Milton Keynes.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

MatthewHutton

Member
Joined
17 Aug 2024
Messages
1,084
Location
Oxford
You were responding to
I responded to two points, firstly to say that a respectable share of customers weren’t going to London from larger places on the mainlines and secondly to say that HS2 didn’t go anywhere near Milton Keynes or Luton.

This sort of not caring about anyone outside the big cities is why people in small northern towns are protest voting for literal nazis like Restore. So if we want to stop that it would be helpful for people to have looked at a map before saying additional HS2 stations aren’t desirable.
 

Krokodil

Established Member
Joined
23 Jan 2023
Messages
6,524
Location
Wales
Except the line doesn’t go anywhere near Milton Keynes and Luton.
The "high speed metro" someone was proposing (every other gate post all the way to Edinburgh) would have done.

40% of Luton trips are to London and 60% of Milton Keynes ones are.

It’s hardly overwhelming and the non London ones are cheaper to provide.
They will be able to make do with all of the newly-vacant seats on the residual service then. No more through passengers to do battle with.
 

Krokodil

Established Member
Joined
23 Jan 2023
Messages
6,524
Location
Wales
This sort of not caring about anyone outside the big cities is why people in small northern towns are protest voting for literal nazis like Restore. So if we want to stop that it would be helpful for people to have looked at a map before saying additional HS2 stations aren’t desirable.
Aylesbury has a population of 90k. There's absolutely no justification for adding a stop on HS2 for them. No one serious is arguing for that.

If they want to argue (as I believe one MP did at the recent debate) that Aylesbury should be connected to EWR (something that was approved but the funding later pulled) then I'm all in favour.
 

NCT

Established Member
Joined
18 Apr 2025
Messages
2,095
Location
London
Not this again ...

The 100mph Chiltern Main Line is a fast conventional railway by any European standards.
 

Peter Sarf

Established Member
Joined
12 Oct 2010
Messages
9,570
Location
Croydon
Because the people who have to suffer the construction don’t get the benefits.

EDIT: It isn’t the only cost driver as the gold plating for speed definitely doesn’t help but it is a cost driver.
I know lets build lots of motorways instead and put in junctions every mile or so.

It is never going to be totally fair. The starting point for HS2 was to get the fastest (non-stop) trains off the WCML so existing smaller stations on the WCML can be better served. The route chosen for HS2 does not go through particularly large towns where a station would be justified AND the capacity of HS2 needed to be saved for the longer distance FAST services.
I responded to two points, firstly to say that a respectable share of customers weren’t going to London from larger places on the mainlines and secondly to say that HS2 didn’t go anywhere near Milton Keynes or Luton.
That is why there are no stations on HS2 between Old Oak Common and Birmingham Interchange.
This sort of not caring about anyone outside the big cities is why people in small northern towns are protest voting for literal nazis like Restore. So if we want to stop that it would be helpful for people to have looked at a map before saying additional HS2 stations aren’t desirable.
The only way to get round this would be to not bother building HS2 and let the people living along the WCML suffer a poorer and poorer service as demand for major cities continues to rise. I think the designers did look at a map to ensure their decision to omit intermediate stops was fine.
 

The Ham

Veteran Member
Joined
6 Jul 2012
Messages
12,021
Whilst there's no train stations in the Chilterns due to HS2 and they will have to deal with construction, they will benefit from HS2, it's just nuanced and not that easy to explain.

Firstly, whist a lot of HS2 travel is counted as "new" it's travel which would happen due to population growth.

Without HS2, that's likely to mean more traffic using the M40, which is likely to mean more times when it's congested and more times that people divert off the M40 though the local roads.

Even without population growth (and counter to popular belief, most growth is in the 65+ population with the working age population being fairly flat) you don't need significant numbers of people switching from road to rail to see improvements to road congestion.

Likewise, if Birmingham is the same commuting time as Aylesbury it means that the pressure for housing reduces outside of the existing urban areas.

If there was a station (or indeed multiple stations) on HS2 within the gap between Old Oak Common and Birmingham Interchange, that would then result in thousands of new homes being delivered near that new station. The impact from that would be far bigger than the impact from building HS2.

I'm sure that there's more, however, that should be enough to explain why there's advantages to being bypassed by HS2.
 

Mark J

Member
Joined
12 May 2018
Messages
650
Aylesbury has a population of 90k. There's absolutely no justification for adding a stop on HS2 for them. No one serious is arguing for that.

If they want to argue (as I believe one MP did at the recent debate) that Aylesbury should be connected to EWR (something that was approved but the funding later pulled) then I'm all in favour.
I certainly agree that Aylesbury should be connected to East West Rail.

It is stupid that this had the funding pulled.
 

FMerrymon

Member
Joined
11 Dec 2024
Messages
362
Location
Reading
I certainly agree that Aylesbury should be connected to East West Rail.

It is stupid that this had the funding pulled.

You can see it in this video, this stretch is all 4 track for a future Aylesbury Link.
.

It needs this section complete and hs2 running for the capacity to reach MK, so funding can't really be allocated until they get that sorted.
 

gravitystorm

Member
Joined
25 Nov 2021
Messages
102
Location
Motspur Park
The Green Signals podcast have covered the latest Transport Committee meeting, with about 20 minutes of discussion covering the first half of the committee meeting.


Richard Bowker is quite sceptical on a few points raised in the meeting, including whether using ATO with ETCS would have to be "invented" (rather than just adapted from the current use of ATO with ETCS on Thameslink), whether the initial opening intensity of 3 tph really leaves HS2 unable to do any testing for the original deliverables (e.g. for ATO or 360kph), and also questions whether Peter Hendy is correct that HS1 can be used for rolling stock testing, given that the plan to equip HS1 with ETCS is currently scheduled for the mid-late 2030s.

He also questions why, given that the "railway systems" installation is described as a "factory process", is it going to take at least 7 years from the end of civil engineering (currently targeting 2029) and the railway opening (earliest 2036). Is it Treasury cash flow restrictions? Or something else? I look forward to hearing more about the length of this part of the process because it also seems like a long time given it's the more certain and predictable part.
 

Technologist

Member
Joined
29 May 2018
Messages
467
The "high speed metro" someone was proposing (every other gate post all the way to Edinburgh) would have done.


They will be able to make do with all of the newly-vacant seats on the residual service then. No more through passengers to do battle with.

Here is what you are missing, the point of the metro is not to optimise the long distance journeys it is to massively interconnect the country whilst also providing adequate long distance connectivity.

This is the anticipated passenger flows on one line of the "Super Metro" network based on a gravity model, this assumes a high frequency service. The upper right half shows the existing typical journey time and the other number is the time on the super metro. The lower left half shows anticipated passenger flows between the city pairs.

The gravity model is probably optimistic but only 373 people a year go between Milton Keynes and Luton so any attempt to extrapolate a market where one does not exist is fruitless. Clearly two cities with 250k populations 8 minutes apart by train are like to have millions of journeys per year.

I also benchmarked where we do have a market using the existing numbers and some established factors (journey times ^-1.35, 1.4X due to increased frequency, 2.5x if the journey drops under an hour x4 if drops under 25 min). These give numbers of 1.5-3 times less than the gravity model suggests. So these numbers would be representative of what would happen if you built the super metro and then improved local transport to London esq levels.

Origin / DestinationLondonLutonM. KeynesNorthamp.LeicesterNottingh.SheffieldLeedsYorkMiddl.Newc.
London23m / 10m32m / 20m46m / 29m65m / 41m94m / 51m120m / 64m133m / 75m112m / 84m2h35 / 1h412h50 / 1h53
Luton18.5M65m / 8m60m / 16m55m / 28m1h35 / 38m2h05 / 51m2h25 / 62m2h40 / 71m3h40 / 1h283h25 / 1h41
Milton Keynes14.2M4.8M15m / 7m1h40 / 19m2h00 / 29m2h10 / 42m2h20 / 53m2h30 / 62m3h50 / 1h203h20 / 1h32
Northampton8.1M2.6M3.9M60m / 11m1h30 / 21m2h15 / 34m2h40 / 45m2h55 / 54m4h10 / 1h113h45 / 1h24
Leicester9.5M2.1M3.2M3.5M22m / 8m55m / 21m1h50 / 32m1h55 / 42m3h00 / 1h002h50 / 1h12
Nottingham9.2M1.8M2.5M2.4M5.1M50m / 11m1h25 / 23m1h45 / 32m3h10 / 50m2h45 / 1h03
Sheffield7.4M1.2M1.6M1.5M2.9M4.6M40m / 10m50m / 19m2h10 / 37m1h50 / 49m
Leeds11.8M1.5M1.9M1.7M3.4M4.9M8.2M22m / 8m1h25 / 26m1h20 / 38m
York4.2M550k680k610k1.1M1.4M2.1M4.5M55m / 15m55m / 27m
Middlesbrough2.1M410k490k380k750k980k1.5M2.9M1.8M60m / 12m
Newcastle6.5M850k950k810k1.4M1.8M2.4M4.6M3.1M3.8M
Total91.5M34.3M34.2M25.5M32.9M34.6M33.4M45.4M20.0M15.1M26.2M

The key point is this, the super metro line would likely cost a comparable amount to HS2 (depends on what baseline you used, given HS2's cost inflation there would be paths to doing it cheaper), but the economic consequences of having this level of interconnectivity would be massive, we are essentially turning large fractions of the country into single travel to work areas. We could justify having national level facilities located in Middlesbrough as it is less than 2 hours from London and less than 1 hour from Manchester.
 
Last edited:

SynthD

Established Member
Joined
4 Apr 2020
Messages
2,014
Location
UK
Here is what you are missing, the point of the metro is not to optimise the long distance journeys it is to massively interconnect the country whilst also providing adequate long distance connectivity.
Metro, long distance, rules of physics. Pick two. You have chosen the first two, HS2 picks the latter two.
 

Palmerston

Member
Joined
4 Oct 2024
Messages
204
Location
Hampshire
Here is what you are missing, the point of the metro is not to optimise the long distance journeys it is to massively interconnect the country whilst also providing adequate long distance connectivity.

Origin / DestinationLondonLutonM. KeynesNorthamp.LeicesterNottingh.SheffieldLeedsYorkMiddl.Newc.
Northampton8.1M2.6M3.9M60m / 11m1h30 / 21m2h15 / 34m2h40 / 45m2h55 / 54m4h10 / 1h113h45 / 1h24
While I think the super metro might be a bit far-fetched, I do think Northampton should be reconnected to Leicester and Nottingham etc, which is feasible, if not very simple. Especially once the southern end of the WCML has some spare capacity.
 

FMerrymon

Member
Joined
11 Dec 2024
Messages
362
Location
Reading
Metro, long distance, rules of physics. Pick two. You have chosen the first two, HS2 picks the latter two.

I'd say it picked all three, since the metro is what you'd run on the sections of wcml, mml and ecml being bypassed.
 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,587
Away from HSMetro for a second, I'm confused as to why they need to wait until 2029 or later (2029 is if the weather is ok for groundworks over the next few summers) to start laying the rails. Looking at the civils works in your area list on the HS2 site, they seem to almost all finish in 2026 or 2027 - is there another stage that needs to take place between civils finishing and laying the rails?
 

InTheEastMids

Established Member
Joined
31 Jan 2016
Messages
1,382
Away from HSMetro for a second, I'm confused as to why they need to wait until 2029 or later (2029 is if the weather is ok for groundworks over the next few summers) to start laying the rails. Looking at the civils works in your area list on the HS2 site, they seem to almost all finish in 2026 or 2027 - is there another stage that needs to take place between civils finishing and laying the rails?
I think it's that Mark Wild wants to derisk the delivery but minimising overlap between civils and rail systems.
This also probably reduces annual spend and that keeps HMT less unhappy, even though it is probably a worse VfM approach because you have time for more inflation and defer benefits by opening later
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,401
Location
Northampton
Away from HSMetro for a second, I'm confused as to why they need to wait until 2029 or later (2029 is if the weather is ok for groundworks over the next few summers) to start laying the rails. Looking at the civils works in your area list on the HS2 site, they seem to almost all finish in 2026 or 2027 - is there another stage that needs to take place between civils finishing and laying the rails?
Assuming that:
- HS2 list is complete for civils,
- civils includes things like drainage,
- installation of things like maintenance accesses can come after track laying.
Then the big thing that would come between civils and the track slab would likely be the tunnel systems. Fire, Ventilation, Evacuation etc.

The first cross-passage door in the Chiltern tunnel has only just been installed: https://www.ianvisits.co.uk/article...rst-tunnel-safety-door-being-installed-90142/, so there's a way to go yet.
 

Technologist

Member
Joined
29 May 2018
Messages
467
Metro, long distance, rules of physics. Pick two. You have chosen the first two, HS2 picks the latter two.

Go on what rules of physics does a high speed metro disobey?

1: Accelerations are the same as a tube train they just go on for longer, they are less vigorous than on buses and are about equivalent to climbing a wheelchair ramp. It's rate of onset of acceleration that matters more than absolute g force pulled.
2: The acceleration is well within the capability of a battery electric vehicle and current BEVs are fitted with drive trains that can deliver super car acceleration for about £30k
3: Line speed is the same as HS2, the batteries mean that current draw would be less peaky per train
4: We would be using eddy current brakes so we can stop the trains at ~2ms-2 in an emergency regardless of traction available

It seems that most the objections are based on ether some assumption that some passengers would not be able to handle the acceleration or that having an interior more like a Thameslink train would not be acceptable for long distance travellers. Neither of these are physics based and neither are really supportable.

I have colour coded the chart so you can visually see what the passenger make up is:

ColourDurationPercentage
Light Green8-25 minutes48%
Olive Green25-60 minutes31%
Yellow60-90 minutes15%
Red90-113 minutes5%

So what we can see is that a metro type interior is actually much more suitable for this sort of train, no need for reservations, people travelling a long way will just take seats when people get off at the next stop after they board. Half of people are on the train are there for less than 25 minutes.

Just out of interest the total number of passenger km on this service is 86 billion, which compares to 65 billion for the entire national rail service today. That is for 520km of twin track lines and 11 stations, even if this cost £150bn to build and the passenger numbers were halved it would be incredibly profitable. I should also add that while the gravity model is likely a little optimistic in practice we'd likely build or upgrade a fair number of other lines to a similar standard so we would see plenty of additional interchange passengers on the line which are not counted in these flows.

1780668650896.png
 
Last edited:

The Ham

Veteran Member
Joined
6 Jul 2012
Messages
12,021
Go on what rules of physics does a high speed metro disobey?

1: Accelerations are the same as a tube train they just go on for longer, they are less vigorous than on buses and are about equivalent to climbing a wheelchair ramp. It's rate of onset of acceleration that matters more than absolute g force pulled.
2: The acceleration is well within the capability of a battery electric vehicle and current BEVs are fitted with drive trains that can deliver super car acceleration for about £30k
3: Line speed is the same as HS2, the batteries mean that current draw would be less peaky per train
4: We would be using eddy current brakes so we can stop the trains at ~2ms-2 in an emergency regardless of traction available

It seems that most the objections are based on ether some assumption that some passengers would not be able to handle the acceleration or that having an interior more like a Thameslink train would not be acceptable for long distance travellers. Neither of these are physics based and neither are really supportable.

I have colour coded the chart so you can visually see what the passenger make up is:

ColourDurationPercentage
Light Green8-25 minutes48%
Olive Green25-60 minutes31%
Yellow60-90 minutes15%
Red90-113 minutes5%

So what we can see is that a metro type interior is actually much more suitable for this sort of train, no need for reservations, people travelling a long way will just take seats when people get off at the next stop after they board. Half of people are on the train are there for less than 25 minutes.

Just out of interest the total number of passenger km on this service is 86 billion, which compares to 65 billion for the entire national rail service today. That is for 520km of twin track lines and 11 stations, even if this cost £150bn to build and the passenger numbers were halved it would be incredibly profitable. I should also add that while the gravity model is likely a little optimistic in practice we'd likely build or upgrade a fair number of other lines to a similar standard so we would see plenty of additional interchange passengers on the line which are not counted in these flows.

View attachment 205431

"a little optimistic" is likely doing a LOT of heavy lifting there.

Take for instance Milton Keynes, the current rail departures for the year are 3,050,000, whist the table above suggests that just going to London would be around 7.1 million.

That's an uplift from around 10 rail departures per head of population to 23 rail departures per head of population.

Given the UK average is 10.5 (21 total rail trips) per head of population and London sees 26.5 and the next highest regions (South East and East) sees around 14, that's quite a large increase.

The reason London is so high is liken due to Overground and other heavy rail Metro services. Although it's worth noting that doesn't include London Underground, which roughly doubles the numbers.

== Doublepost prevention - post automatically merged: ==

I have my thoughts (and some could likely guess at what they are from what I've said), but would be interested in what others think of this assessment:

Letter: HS2 consultants are blindly leading the UK into a ditch https://share.google/E1dkXVzubaRDpaN6o

Your article on HS2’s consultancy spending (Report, May 26) invites a deeper question. The Katha Upanishad warns: “Like the blind led by the blind, fools go hither and thither.” Matthew said both shall fall into the ditch. Pieter Bruegel painted them. HS2 is Britain’s ditch. But were all truly blind, or did some keep their eyes wide open?

HS2’s original £37.5bn estimate was set before meaningful design. Today, the Y-shaped network is gone. What remains is a single line to Birmingham, costing up to £103bn with an uncertain opening date. The mistake was legal. Unlike the 2012 London Olympics — designated as an overriding national interest with a single permitting authority — HS2 was sent through ordinary parliamentary and legal processes. Tens of thousands of stakeholders gained enforceable rights to object. Each had a de facto veto.

This created an inescapable trap. Every concession added unmeasurable cost, making honest forecasting impossible. Into this vacuum stepped consultants and legal advisers. They sold collaborative processes, more governance, more cost controls and forecasting, more flexible contracts. None worked: HS2’s problem was legal and political, not managerial. No system reconciles a fixed budget with an open-ended obligation to satisfy thousands of objectors. Consultants sold solutions to problems they had no power to fix.

And contractors? In a project defined by uncertainty, the only certain outcome was their profitability. Undefined scope turns flexible contracts into open invitations.

We rightly should not silence stakeholders. But without legal reform, a constrained government cannot spend its way to solutions — only to more HS2s and profits for those selling the blindness. The parable ends in a ditch, and we are falling. The question is whether enough of us, seeing clearly, will stop walking.

Nuno Gil
Professor of New Infrastructure Development, Alliance Manchester Business School, Manchester, UK
 
Last edited:

InTheEastMids

Established Member
Joined
31 Jan 2016
Messages
1,382
Letter: HS2 consultants are blindly leading the UK into a ditch https://share.google/E1dkXVzubaRDpaN6o
I think I agree with the thrust of the letter - the £37.5Bn budget must've been set long before the design was mature/frozen enough to warrant the certainty that's been attached to it.

But frankly I would expect a slightly cooler-headed analysis from a university professor, this reads like a bit of a rant. The planning issues and political tinkering with scope have been well described before and I don't think any particularly novel perspective is offered. Then, it's some very lazy "blame the consultants" thinking.

"Consultants sold solutions to problems they had no power to fix." Quick! Somebody needs to call BBC TV Watchdog.

Heidi, a 51 year old woman from Swindon South is a vulnerable Government minister in charge of Multi-billion pound HS2 Ltd. She was mis-sold "consultancy" by a couple of burly men, who - when challenged by TV's Matt Allwright - covered their faces, assaulted the camera crew and sped away in a white Ford Transit. Do you know them? Have you seen them? Please call.

The serious point I'm making is that if consultants were doing this, it's actually reflecting that HS2 Ltd/DfT were not competent clients who understood which things consultants can and can't fix. They are not individuals requiring protection from rogue traders. The very cynical take on Client behaviour is, when realising that something might hit the fan, commissioning a consultant to either validate it or provide a convenient scapegoat in the future. I have sat in meetings where it is extremely apparent that this is what the Client wants.
 

FMerrymon

Member
Joined
11 Dec 2024
Messages
362
Location
Reading
I think I agree with the thrust of the letter - the £37.5Bn budget must've been set long before the design was mature/frozen enough to warrant the certainty that's been attached to it.

37.5bn wasn't ever the budget, though, its an early estimate in 2009 prices from 2011. The certainty attached this figure was from the media reporting of the time. The first budget was in 2013 (50.1bn in 2011 prices) with slightly more work done - thats around 85bn in today's prices. However, we know the hybrid bill process made a few changes and, even then, by 2020, its now said they didnt have a mature enough design - that was what Mark Wild pointed to for the increases in costs since 2020.


The serious point I'm making is that if consultants were doing this, it's actually reflecting that HS2 Ltd/DfT were not competent clients who understood which things consultants can and can't fix.

Agree, and I love the Heidi from Swindon South story :D. I didnt read the letter as blame the consultants overall though, more that there were systemic issues in delivery.
 

HSTEd

Veteran Member
Joined
14 Jul 2011
Messages
20,265
Even if battery electric trains struggle to deliver the performance @Technologist proposes, a track based linear synchronous motor (like those proposed for maglevs) certainly can deliver that performance.
 

Technologist

Member
Joined
29 May 2018
Messages
467
Even if battery electric trains struggle to deliver the performance @Technologist proposes, a track based linear synchronous motor (like those proposed for maglevs) certainly can deliver that performance.
I don't see what issues would prevent us having conventional wheeled trains with that level of performance, we are talking relatively tame acceleration compared to a BEV vehicle. We might struggle with battery life which might force us to initially have larger batteries and slightly overweight trains but given the general progress of the area that would be corrected at the first battery change.

I would assume that the intensity of use of the line would mean that we wouldn't have very many issues with traction as the line would be self cleaning in operation. From a safety perspective we would likely use eddy current brakes as the emergency system so we would have a means of slowing down without relying on traction.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,981
Location
Surrey
National Audit Office have released a report into the HS2 reset its a 56 page document so can only offer some observations but its largely a regurgitation of what we've already heard at Transport and Public Accounts committees.

https://www.nao.org.uk/wp-content/uploads/2026/06/high-speed-two-reset.pdf

The first recommendation is

DfT and HS2 Ltd expect to complete the reset in spring 2027, but it is essential that they ensure the programme is fully on a stable footing before the reset is complete. DfT and HS2 Ltd should review how realistic the timetable is in autumn 2026 to complete remaining work and, if necessary, revise the timetable to provide them with the additional time needed to complete the reset.
If HS2 haven't got a grip by Spring 2027 not sure they ever will

Then there is this on rolling stock

When deciding on the HS2 train fleet and how it will integrate with the wider rail network, DfT should ensure that it aligns with the future operation of the rail network as a whole and ensure sufficient seat capacity to maximise overall benefits.
Specifically reinforcing what Chris Gibb was promoting by saying
3.9 HS2 Ltd awarded a contract for trains in 2021. The cancellation of Phase 2 in 2023 means that trains will run on the existing railway north of Birmingham. However, the stations on the existing West Coast Main Line railway are smaller than the HS2 stations that were planned. Therefore, the platforms are too small to accommodate the HS2 trains running with two 200-metre units as was originally planned. If HS2 trains operate as a single 200-metre unit, they would carry fewer passengers than the trains which currently run on the West Coast Main Line. In addition, the new trains will not be able to go as fast as the current Pendolino trains on certain sections of the track. A reduction in the length of the trains, and in turn seat capacity, will impact on the programme’s benefits and the wider rail network.
3.10 HS2 Ltd and DfT are now looking at options for including longer trains in the fleet. They expect to make a final decision on the number and length of units needed by 2028, to coincide with wider DfT decisions on trains for the whole of the West Coast Main Line. They have assessed that agreeing any change in train length by 2028 would allow the supply chain to adjust and deliver trains when they are needed. In the meantime, they are reviewing how this and recent scope changes (for example, removal of automatic train operation), impact the current contract and the next steps they need to take as part of the commercial reset.

Not sure I had seen this reported before but

The reset programme began in January 2025, and HS2 Ltd expects to complete it in spring 2027. HS2 Ltd estimates it will spend £153 million on the reset (in nominal prices), having spent £101 million by the end of March 2026. HS2 Ltd uses additional resources to conduct the reset alongside continued delivery of the programme.
In the grander scheme of HS2 its a small amount but its still £153m that has to come from DfTs budget that cant be spent on something else.

In summary they've made eight recommendations and DfT don't have to agree to them but will usually provide a commentary once they've considered the report.
 