This authorisation is for placing into service of CVL - electrification of the...
CAR-A EE4 works that have been recorded in SJR32 (CSM-RA) and SJR78
(NTSN). The footprint of the authorisation is from Overhead Line Structure (ELR:
CAR) CAR/11/704 (8 mile 35 chains) to the limit of Electrification at Overhead Line
Structure CAR/36/709 (23 mile 78 chains) (ELR: CAR). The footprint includes
Rhymney sidings; the southern sidings limits is structure CAR/36/207 (23 mile 53
chains); and the northern sidings limit is structure CAR/36/378 (23 mile 62 chains)
(ELR: CAR).
Page 1 of 3
The restrictions or limitations of use on the structural subsystem are those contained
on the UK declaration of verification TRAN01-KAW-ZZ-CVL-UPF-Z-MF-000185,
Version P02 and contained in technical file ApBo DeBo Technical File ACS/3167
CAR 4A Energy Technical File – Design and Production (EE4A) ACS3167R54,
Issue 02.
and
CAR-A EE3B-1 & EE3B-2 works that have been recorded in SJR31 (CSM-RA)
and SJR76 (NTSN). The footprint of the authorisation is from Overhead Line
Structure (ELR: CAR) CAR/02/313 (02 mile 49 chains) to the limit of Electrification at
Overhead Line Structure CRY/07/656 (02 mile 58 chains), on the Coryton Branch
line (ELR: CRY) and to the limit of electrification at Caerphilly Station in Bay Platform
at Overhead Line Structure CAR/11/390 (08 mile 21 chains) (ELR: CAR).
The restrictions or limitations of use on the structural subsystem are those contained
on the UK declaration of verification TRAN01-KAW-ZZ-CVL-UPF-Z-MF-000176,
Version P02 and contained in technical file ApBo DeBo Technical File ACS/3167
CAR 3B Energy Technical File – Design and Production (EE3B-1 & EE3B-2)
ACS3167R49, Issue 03.
The Energy subsystem authorised by this letter must be operated and maintained in
accordance with Regulation 20...