Wow 2027 is soon, the units will probably start heading up soon then. Where will they be repainted does anyone know?
No idea on the repaints. In terms of timelines from the Scotrail press release:
With passenger services entering service before the end of 2027, there will be a phased approach to the trains being introduced, with the final train expected to be in operation before the end of 2028.
Six Class 222s will be used specifically for training and they will start to arrive in early 2027 giving staff around nine months to get used to the new way of working, before they go through the refurbishment programme.
The refurbishment and training can happen in parallel on different units reducing the need to get units quickly. Those that are released by EMR can head up or to refurbishment to reduce risk of slip.
Perhaps more important, given their declining reliability, is where will they be maintained?
At EMR they are worked hard with a high availability target, ad hoc covering for 810s and a similar unit requirement every day of the week. None of the Scotrail HSTs do more than 800 miles in a day, some of EMRs 222s do 1200 miles in a day. The Scotrail network has lower speeds on average. Provided a suitable availability target is given, the reliability is unlikely to be anywhere near as much as an issue.
As I didn't see the announcement thread originally, if anyone else is in the same boat it's here:
Alstom just revealed it has the 10 year refurbishment and maintenance contract for 222s for Scotrail (option to extend to March 2042) so move to Scotland now official
10-year Technical Support and Spares Supply Agreement (TSSSA) to support Class 222 fleetComprehensive fleet refresh and technology upgrades to enhance passenger experienceSupports ScotRail’s sustain