How could the UK reduce the cost of large infrastructure projects?

Status
Not open for further replies.

FMerrymon

Member
Joined
11 Dec 2024
Messages
362
Location
Reading
Yes, but the point is it's hitting Brightline, not nearly bankrupting the country like HS2

The country is not being nearly bankrupted by hs2. The government invests in such projects because it expects an economic return, a return that a private company wouldnt be able to receive.

There should be more private money in the scheme though, theres a lot of money to be made in the redevelopments around Birmingham and OOC, and for housing along the corridors with released capacity from hs2.
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,667
Location
Northampton
The Americans have recently got a 235 mile high speed line at ZERO cost to the goverment! And being subsidised heavily each year by the company's investors... the nationalisation fans are rather deluded.

Wikipedia gives it's maximum operating speed as 125mph (the bare minimum for HSR), but only between Orlando and Cocoa, a distance of about 60 miles. The remaining distance to Miami is on previously existing CSX tracks and operates at 80-110mph.

Brightline takes 3.5hrs to cover 235miles, LNER takes 2.66 hrs to cover the 260miles from London to Newcastle. I'm sorry but Brightline is worse for hype than HS2.
 

CMS1

Member
Joined
15 Feb 2025
Messages
245
Location
uk
I'm not saying Brightline is HS2, I'm responding to the thread question of how infrastracture can be delivered cheaper.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,965
I'm not saying Brightline is HS2, I'm responding to the thread question of how infrastracture can be delivered cheaper.

If you’d driven down the Martin B Andersen Beachline Expressway (528) from Orlando International to Cocoa Beach, you’d see why it was relatively cheap. Things are a lot cheaper to build when you can just buy the land without any issues, snd there’s almost nothing in the way.
 

sad1e

Member
Joined
26 Aug 2024
Messages
1,050
Location
London
Things are a lot cheaper to build when you can just buy the land without any issues, snd there’s almost nothing in the way.
Land purchase and development has really been a major issue for HS2 , each structure being built has had to be submitted separately to the appropriate country council.

Some councils such as Buckinghamshire have not exactly been very helpful with the Planning permission applications , constantly trying to push back works and denying permission for small parts of the railway which then require complete resubmission if declined.

HS2 as a whole should really have been put forward as an act of parliament order , any Victorian entrepreneur and his dog was able to build a railway with an act of parliament and not have to faff about with planning permissions for each individual structure. So why should HS2?
 

MatthewHutton

Member
Joined
17 Aug 2024
Messages
1,084
Location
Oxford
HS2 as a whole should really have been put forward as an act of parliament order , any Victorian entrepreneur and his dog was able to build a railway with an act of parliament and not have to faff about with planning permissions for each individual structure. So why should HS2?
Because it wasn’t politically viable to get that through parliament.

== Doublepost prevention - post automatically merged: ==

An example was the struggle to build the A34 road improvements. The building of the Newbury Bypass struggled throughout the 1990s to get done.
The first one was the A46/A4 at Bath I believe.
The stonehenge tunnel saga is another example.
Even by 1995 it was realised that a ~2.5 mile bored tunnel was necessary to do the job, but the Government has spent 30 years trying to shrink the tunnel or convert it to cut and cover (fundamentally destroying a major point of the tunnel!) and consequently nothing has been achieved.
This is another example of lack of imagination. Either you do a long tunnel, perhaps even 5 miles and come out the other side of Winterbourne Stoke - or you make it one way via Larkhill - or you just plant some Yew trees on the surface next to the road so you can’t see it.
The Americans have recently got a 235 mile high speed line at ZERO cost to the goverment! And being subsidised heavily each year by the company's investors... the nationalisation fans are rather deluded.
Brightline is basically just a European quality railway. It’s impressive for the United States. But it’s not that good. And it may well go out of business unfortunately.
 
Last edited:

HSTEd

Veteran Member
Joined
14 Jul 2011
Messages
20,380
If they go bankrupt it will be the investors who bear the loss not society. It does seem likely they will need subsidy before long, which is fair enough, but doesn't change the fact most of it was done at no cost to the public purse.
The investors will lose their investment but no more, that is the reality of limited liability.
The investor liability will be a small fraction of the total losses of Brightline. The rest will be eaten up by society, because thats what happens when people go bankrupt. Contractors unpaid, staff unpaid etc etc etc etc

The debts don't just vanish because you press a magic button marked "bankruptcy". Society at large just ends up paying for them.

And as noted, various items of brightline infrastructure were paid for by government.

If brightline continues to exist, it will likely need the approximately $500m/yr subsidy to be made up by the state, forever.
It will likely never be profitable because this inexpensive infrastructure is woefully inadequate to the task.

The effective subsidy will rapidly climb into the stratosphere.

By European standards its not even a particularly high performance railway.

== Doublepost prevention - post automatically merged: ==

This is another example of lack of imagination. Either you do a long tunnel, perhaps even 5 miles and come out the other side of Winterbourne Stoke - or you make it one way via Larkhill - or you just plant some Yew trees on the surface next to the road so you can’t see it.
That doesn't fix the crippling overload of the road though.
And you will not get permission for surface construction of a dual carriageway through the area, for the same reason you will not get permission for a cut and cover tunnel.
 
Last edited:

MatthewHutton

Member
Joined
17 Aug 2024
Messages
1,084
Location
Oxford
Theres definitely a problem in general with over engineering you can see with roads, the new dualled A30 north of Redruth and A303 at Sparkford could have been dualled by slapping another lane down, but instead a brand new road with massive lay-bys and ultra gentle corners was built instead. And I doubt it is any safer as it encourages grossly excessive speeds.

And those projects have costs that are 10x or more the M40 extension from the late 1980s.

The newish A1(m) south of darlington is probably another example.

== Doublepost prevention - post automatically merged: ==

That doesn't fix the crippling overload of the road though.
And you will not get permission for surface construction of a dual carriageway through the area, for the same reason you will not get permission for a cut and cover tunnel.
Long tunnel is probably best. The planning cost becomes like £0 because you just go under all the archeology. That’s worth something.
 
Last edited:

Uncle Buck

Member
Joined
30 Jun 2020
Messages
336
Location
Glasgow
Stop picking avoidable political fights.

HS2 tried to force surface route across the Chilterns, it eventually capitulated but only after years of delay with associated cost overruns.

Engineering problems are, in my experience, virtually always more solvable than socio-political ones.
Excellent point.

I’ve always said that HS2 should have followed the M1- partly because IMO this follows a more suitable route from the perspective of relieving other lines, but equally because it is through places that have already been “spoiled” by the motorway and because frankly that corridor is less scenic than the Chilterns.

There are some people who think that the way to tackle Nimbyism is by rubbing it in Nimbies’ faces, rather than by accepting that not wanting to have one’s hometown flattened is in fact a normal instinct.
 

Mr. SW

Member
Joined
13 Sep 2023
Messages
552
Location
Armchair
1) Hire a masterbuilder ie someone who has done it before
2) Get the right team into support them - ie people who have done it before and not a revolving cast of civil servants
3) Ask Why - why are you proposing to build what you are planning to build - is it the right solution to the problem
4) build with lego as he puts it - ie modular build using the same design over and over again
5) think slow: act fast - spend time planning and designing and then build rapidly - none of this stop start business or designing while building
6) learn from similar projects - no project is really unique it contains elements that have all been done before - learn from them
7) watch the downside - plan for risks, mitigate them
8) be prepared to say no and walk away - if the project cant be delivered to the proposed budget and timescale - say so - HS2 failed in part because people kept saying it could be delivered for an unrealistic budget and when it became apparent it couldnt, politicians lost confidence in it
9) make friends and keep them - HS2 had few friends and burnt through its political capital by not being honest and transparent on costs and timescale
Add:
Don't create enemies through poor design, policy, decision-making and explanation.
Hence don't create situations which can be used against the scheme.
This is what killed the West London Tram.
 

deltic

Established Member
Joined
8 Feb 2010
Messages
3,721
Pay everyone involved in the work half what they are currently getting.
Do the opposite, pay top dollar to attract the top talent, these are multi billion pound projects that need experienced people to deliver them..

== Doublepost prevention - post automatically merged: ==

Less corruption
Name a single example of corruption related to major infrastructure in the UK in recent years.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,965
HS2 as a whole should really have been put forward as an act of parliament order

It was !

High Speed Rail (London - West Midlands) Act 2017​

2017 CHAPTER 7​

An Act to make provision for a railway between Euston in London and a junction with the West Coast Main Line at Handsacre in Staffordshire, with a spur from Water Orton in Warwickshire to Curzon Street in Birmingham; and for connected purposes.



the new dualled A30 north of Redruth and A303 at Sparkford could have been dualled by slapping another lane down, but instead a brand new road with massive lay-bys and ultra gentle corners was built instead.

That’s called Highway standards, and it is safer*. The railway equivalent of what you’re proposing would be to build new railways with wooden sleepers, semaphore signalling, and a linespeed of 75mph.

*speed doesn’t kill. What kills is coming to a stop in a very short amount of time, or being accelerated to a high speed in a short amount of time. Removing short laybys, tight corners, side roads etc. all reduces the risks of the collisions that lead to these two eventualities.
 

MatthewHutton

Member
Joined
17 Aug 2024
Messages
1,084
Location
Oxford
That’s called Highway standards. The railway equivalent of what you’re proposing would be to build new railways with wooden sleepers, semaphore signalling, and a linespeed of 75moh.
That’s not really analogous when existing railways don’t have those features as they’ve been removed with general maintenance, but when there is no programme to upgrade existing trunk roads to the new road standard.

And on both sets of roads you are still limited to driving at 70mph++.

A better analogy is that we should go back and build new railway lines to the 1980s spec, which I support.

== Doublepost prevention - post automatically merged: ==

The act still required it to go through local planning permission - presumably because if it didn’t you wouldn’t have got the votes.

== Doublepost prevention - post automatically merged: ==

Name a single example of corruption related to major infrastructure in the UK in recent years
The Jubilee line extension had that corruption court case that collapsed - presumably they were guilty for the purposes of there being corruption in the project.
 
Last edited:

deltic

Established Member
Joined
8 Feb 2010
Messages
3,721
The act still required it to go through local planning permission - presumably because if it didn’t you wouldn’t have got the votes.
From what various politicans and senior HS2 people have said there was a lack of understanding of what powers the Act gave to HS2 Ltd. They were surprised (and so was I) that local planning permission was still required for so many aspects and that councils refused to rubber stamp HS2 proposals (which was not a surprise). HS2 was taken, in the vast majority of cases unsuccessfully, to judicial review by councils and other bodies over 50 times increasing costs and delays. HS2 had the votes in Parliament because it had support across all parties but its not clear government or MPs fully understood that the Act did not give HS2 Ltd carte blanche to get on and deliver the scheme.
 

MatthewHutton

Member
Joined
17 Aug 2024
Messages
1,084
Location
Oxford
From what various politicans and senior HS2 people have said there was a lack of understanding of what powers the Act gave to HS2 Ltd. They were surprised (and so was I) that local planning permission was still required for so many aspects and that councils refused to rubber stamp HS2 proposals (which was not a surprise). HS2 was taken, in the vast majority of cases unsuccessfully, to judicial review by councils and other bodies over 50 times increasing costs and delays. HS2 had the votes in Parliament because it had support across all parties but its not clear government or MPs fully understood that the Act did not give HS2 Ltd carte blanche to get on and deliver the scheme.
Presumably having to get local planning permission was a compromise for the rural conservative MPs along the route.
 

deltic

Established Member
Joined
8 Feb 2010
Messages
3,721
The Jubilee line extension had that corruption court case that collapsed - presumably they were guilty for the purposes of there being corruption in the project.
Was not aware of that case but even here the alledged wrong doing happened around 30 years ago and the court case was 20 years ago. As the case collapsed we have to assume innocence as no one was found quilty.

== Doublepost prevention - post automatically merged: ==

Presumably having to get local planning permission was a compromise for the rural conservative MPs along the route.
No - it was just the process - rural conservative MPs voted against the scheme anyway.
 

brad465

Veteran Member
Joined
11 Aug 2010
Messages
11,585
Location
Taunton or Kent
If HS2 had followed Motorway corridors (M40, M6, M42 and M1) like HS1 and LGV Nord do, the level of land acquisition would have been much less, while NIMBY resistance would have been much lower (hard to complain about a new railway being built where there's already an even larger and noisier road). Yes speeds wouldn't have been as high, but given this is mainly a capacity seller, they shouldn't have to be.

Some parts of some projects are inevitably "bespoke".

For example, the two most critical bits of the eastern leg of East West Rail are going to be rebuilding Bedford and rebuilding Cambridge. Although there are some previous rebuilds to learn from, such as London Bridge and Reading, rebuilding Bedford and rebuilding Cambridge are inevitably bespoke.
Okay, fewer bespoke parts.
 

Magdalia

Established Member
Joined
1 Jan 2022
Messages
7,435
Location
The Fens
Theres definitely a problem in general with over engineering you can see with roads, the new dualled A30 north of Redruth and A303 at Sparkford could have been dualled by slapping another lane down, but instead a brand new road with massive lay-bys and ultra gentle corners was built instead. And I doubt it is any safer as it encourages grossly excessive speeds.
I'm not a driver but I'm old enough to remember roads that were dualled by "just slapping another lane down". Long sections of the A1 were like this. They were very dangerous because they did not have grade separation at junctions.

Grade separation on roads is expensive, just as it is on railways. A good current example is the Black Cat-Caxton Gibbet project, where about half of the project cost is the grade separated junction at the Black Cat.
 

The exile

Established Member
Joined
31 Mar 2010
Messages
9,475
Location
Somerset
If HS2 had followed Motorway corridors (M40, M6, M42 and M1) like HS1 and LGV Nord do, the level of land acquisition would have been much less, while NIMBY resistance would have been much lower (hard to complain about a new railway being built where there's already an even larger and noisier road).
Much easier to do when the motorway is being built at roughly the same time rather than 50 - 60 years earlier.
 

CMS1

Member
Joined
15 Feb 2025
Messages
245
Location
uk
Much easier to do when the motorway is being built at roughly the same time rather than 50 - 60 years earlier.
Yet we still haven't learnt to coordinate infrastructure today! Look at the new A428 on Google Maps, very similar route to EWR and they could be putting in the EWR alignment alongside it now while they're at it.
 

MatthewHutton

Member
Joined
17 Aug 2024
Messages
1,084
Location
Oxford
I'm not a driver but I'm old enough to remember roads that were dualled by "just slapping another lane down". Long sections of the A1 were like this. They were very dangerous because they did not have grade separation at junctions.

Grade separation on roads is expensive, just as it is on railways. A good current example is the Black Cat-Caxton Gibbet project, where about half of the project cost is the grade separated junction at the Black Cat.
The A34/404/30/303 sections that were done a while ago have all/mostly grade separated junctions or roundabouts.

EDIT the M40 junction 15 improvement was £71m in 2008 - black cat could have something similar and that would be a lot cheaper.
 
Last edited:

The exile

Established Member
Joined
31 Mar 2010
Messages
9,475
Location
Somerset
Yet we still haven't learnt to coordinate infrastructure today! Look at the new A428 on Google Maps, very similar route to EWR and they could be putting in the EWR alignment alongside it now while they're at it.
Or at least constructing one with full provision for the other. Of course the danger there is that what you’ve paid money providing for never happens (see Berlin’s U10)
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,667
Location
Northampton
If HS2 had followed Motorway corridors (M40, M6, M42 and M1) like HS1 and LGV Nord do, the level of land acquisition would have been much less, while NIMBY resistance would have been much lower (hard to complain about a new railway being built where there's already an even larger and noisier road). Yes speeds wouldn't have been as high, but given this is mainly a capacity seller, they shouldn't have to be.
I believe there's now a push against being too close to Motorways because it leaves a corridor of unusable land. However the idea that NIMBY resistance would have been any lower to a route following the M40 on the surface is wishful thinking.
Yet we still haven't learnt to coordinate infrastructure today! Look at the new A428 on Google Maps, very similar route to EWR and they could be putting in the EWR alignment alongside it now while they're at it.
UK politicians have lost the art of making a decision. The A428 route around Black Cat/St Neots isn't necessarily very helpful to EWR (it stays quite far away from the town the railway wants to serve), neither is the approach to Cambridge (because EWR will come in from the South) but the section past Cambourne could be facilitating the railway.
 

MatthewHutton

Member
Joined
17 Aug 2024
Messages
1,084
Location
Oxford
I believe there's now a push against being too close to Motorways because it leaves a corridor of unusable land. However the idea that NIMBY resistance would have been any lower to a route following the M40 on the surface is wishful thinking.
I think the train people are pretty bad at understanding what would and wouldn’t be acceptable to people in the countryside.

I think though to be fair you’d need to see an actual proposal to judge whether the M40 or M1 route would have been less controversial. Depends how many road crossings you’d need
 

deltic

Established Member
Joined
8 Feb 2010
Messages
3,721
Some parts of some projects are inevitably "bespoke".

For example, the two most critical bits of the eastern leg of East West Rail are going to be rebuilding Bedford and rebuilding Cambridge. Although there are some previous rebuilds to learn from, such as London Bridge and Reading, rebuilding Bedford and rebuilding Cambridge are inevitably bespoke.
Every project is unique but generally every component has been done before many times over. Back to the idea that projects should be thought of as lego bricks ie taking standard blocks but maybe combining them in different ways as required. Once a project is thought of as bespoke we end up reinventing the wheel, piling on cost and delay.
 

FMerrymon

Member
Joined
11 Dec 2024
Messages
362
Location
Reading
I appreciate the question about costs here is general rather than focused on HS2. HS2 had/has its own issues of course, but the biggest issues we have with costs are systemic, HS2 just reveals them more. We can see the issue with costs on other projects - Crossrail 1 might have been delivered for £18.9bn, but Crossrail 2 is estimated at £45bn in current prices - yes, the scope is different, but it gives some idea of scale of costs. Lower Thames Crossing is 14 miles and is now estimated to be £11bn. Houses of parliament refurbishment could be up to £40bn. EWR Bedford-Cambridge is 31 miles of new track and is over £5bn, for 100mph not electrified and isn't significantly cheaper than the expected cost of HS2 phase 2a. A428 Back cat to Caxton Gibbet is £1bn for 10 miles of upgrade.
There's a narrative forming, particularly from the media, that only blames hs2 as a project - speed+tunnels+bat shed+incompetence. Whilst they may be factors, its an over simplification of the issues and misses crucial context and the environment of operating in the UK.

The NIC report from 2024 is well worth reading: https://upload.wikimedia.org/wikipedia/commons/d/d7/NIC-Costs-Report-Final-Oct-2024.pdf
The Fingleton nuclear regulatory review has insights and recommendations that covers other types of infrastructure projects and worth taking a look at: https://majorprojects.org/wp-content/uploads/2025/12/nuclear-regulatory-review-2025.pdf
The NAO produced this report on lessons learnt from large projects: https://www.nao.org.uk/wp-content/u...-decision-making-on-mega-projects-summary.pdf

Before we look at HS2 more closely, we should consider the issues affecting all projects.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,965
If HS2 had followed Motorway corridors (M40, M6, M42 and M1) like HS1 and LGV Nord do, the level of land acquisition would have been much less,

Unlikely. The land required is a function of the scale of the railway, not where it is. Arguably, it would havebeen more if it followed the motorways, as the alignment of the railway would have to be straighter than the motorway (imagine going round the Otmoor curve at 200mph, it’s a challenge at 80!), and therefore likely need to cross the motorway multiple times, and cut corners leaving parts of land with no access.


while NIMBY resistance would have been much lower

That I agree with.



EDIT the M40 junction 15 improvement was £71m in 2008 - black cat could have something similar and that would be a lot cheaper.

The M25 / A3 junction improvemnt is over £300m in 2026.…

(Anb the black cat has already been rebuilt twice in my time driving)

== Doublepost prevention - post automatically merged: ==

I think the train people are pretty bad at understanding what would and wouldn’t be acceptable to people in the countryside.

“Train people” aren’t doing it. The people employed in developing that part of the project are the same individuals who work on highway projects, power projects, etc.
 

FMerrymon

Member
Joined
11 Dec 2024
Messages
362
Location
Reading
I fed a few of the papers and some HS2 specific ones (will share later) into claude for a summary of the papers:

The four root causes (NIC framework, endorsed by Stewart Review)

The NIC identifies four systemic root causes, and the Stewart Review explicitly endorses this framework. All four must be addressed together — the NIC is clear that government providing strategic direction is "foundational" and without it the other reforms won't reliably work.


Root cause 1: Lack of clear strategic direction

The UK's stop-start approach to infrastructure investment destroys the conditions needed for efficient delivery. When the pipeline is uncertain, contractors price in risk, don't invest in skills or capital equipment, treat each project as discrete, and the workforce fragments. The NIC contrasts this with offshore wind, where the Contracts for Difference model provided long-term funding certainty and costs fell by two-thirds between 2015 and 2022. For rail electrification specifically, the UK's intermittent approach created a workforce deficit of 1,000–2,000 people per year and a 12% salary premium, while Germany's steady programme achieves materially lower unit costs.

The PwC benchmarking study found the same pattern internationally: countries with multi-year high-speed rail programmes benefited from continuity of client professionals, industry investment, innovation, and historical data for risk allowances. The UK's approach produces the opposite — a fragmented industry with low investment, low productivity, and high overhead.

The Stewart Review recommends that NISTA be given overall leadership of the UK infrastructure programme (R79) and that a dedicated Minister for Infrastructure and Construction be considered (R78). Stewart also notes that the regulated sectors, particularly energy, have a better delivery track record, suggesting private funding and leadership structures like the RAB model bring beneficial discipline. The construction sector workforce has shrunk by 340,000 workers (14%) between 2019 and 2023, with older workers leaving and too few younger workers joining — a problem the NIC says will worsen without action.


Root cause 2: Client and sponsor challenges

The NIC's analysis found that over 50% of available cost reductions require action before construction begins. The pattern across the documents is consistent: budgets are set too early on immature designs, requirements aren't iterated against affordability, and then reality forces expensive redesign during construction.

The Stewart Review provides the sharpest HS2-specific evidence. Stewart found that "a culture of driving down cost to manage affordability has been absent from the Programme." Requirements and scope were owned by DfT but cost and schedule by HS2 Ltd, with inadequate iteration between them. Political decisions drove scope changes without robust cost challenge. Stewart recommends using a Financial Shareholder to challenge political decision-making that impacts cost (R43), requiring time to iterate requirements, scope, design and cost before committing (R42, R46), and establishing a Project Controls sub-board to scrutinise cost forecasts (R45).

The NAO's HS2 update provides the contract-level detail. HS2's main works civils contracts incentivised contractors to prioritise schedule over cost management. There was little commercial consequence for starting construction before design was confirmed, and complex design assurance processes led to fragmented design work that increased costs. HS2 Ltd had limited cost information from the supply chain, reducing its ability to assess which cost increases were genuinely necessary.

The PwC benchmarking study found that comparator projects internationally established affordability constraints at an early stage and incorporated cost considerations into all alignment, design and scope decisions. PwC concluded that HS2 Phase Two would benefit significantly from an affordability target established through rigorous understanding of the assets to be delivered — something that was notably absent.

The NAO's mega-projects report adds a governance dimension: the standard model where a single department is accountable often fails at mega scale. Where views differ between departments and HM Treasury about the purpose of a project, decision-making suffers. The NAO recommends defining a formal "mega-project" category with different governance requirements, potentially with HM Treasury or NISTA having a formal position on the project board during early stages. Stewart reinforces this with the structural observation that projects can become too big for a single entity to manage — HS2 Ltd's scope of responsibilities could have been reduced, for example by using a separate delivery structure for Euston.


Root cause 3: Inefficient consenting and compliance

The NIC provides unusually specific evidence. NSIP approvals increased by 65% between 2012 and 2022, reaching an average of about four years and over five and a half years in complex cases. The proportion of schemes subject to judicial review spiked to 58% from a long-term average of around 10%. Even after HS2's hybrid bill, more than 8,000 further consents were required from local authorities, the Environment Agency, and Natural England. The Lower Thames Crossing planning application alone cost £267m, illustrating the direct cost of the consenting system itself.

The NIC identifies structural problems: the system has become more complex and contested; individual actors are aligned to their own organisational objectives rather than the overarching goal; and late design changes driven by compliance add costs during construction. Delay is expensive in its own right — the NIC cites the A428 scheme where a one-year delay from a meritless legal challenge imposed £24m in inflationary costs with no design change. The NIC's earlier study proposed solutions that could reduce consent times from four years to two.

The Stewart Review endorses the government's September 2024 proposed reforms to planning, noting that without significant reform, major projects will continue to face cost and schedule delay. The NAO's mega-project report adds that the ICE found immature designs and consents "greatly contributed to cost escalation on HS2" and recommended that sponsors must be "ruthless in gate reviews" until design and planning are sufficiently mature.


Root cause 4: Constrained supply chain

The UK is an international outlier in the fragmentation of its construction sector. The NIC reports approximately 23,000 companies in civil engineering, nearly 90% employing fewer than eight people. Tier one contractors commonly use 50–70 subcontractors per project. The PwC benchmarking study found this fragmentation drives a 12% cost difference compared to less fragmented international comparators, through layered administration costs, profits, and risk premiums at each tier. The NIC's analysis shows that multiple layers of subcontracting overheads can make up more than 50% of a project's total cost.

The Stewart Review found that HS2 stretched the civils supply market beyond its capacity and that the structure of the UK market, with Tier 1 suppliers relying heavily on outsourced design and sub-contracting, has fundamental shortcomings. Stewart recommends NISTA conduct a review of the capacity and capability of the civils construction sector (R80).

Construction sector labour productivity has flatlined for 15 years. The NIC links this directly to lack of pipeline certainty — firms can't justify investing in capital, technology, or skills without confidence in future work. Where certainty exists, the market responds: Laing O'Rourke invested in off-site manufacture for housing on the promise of a significant pipeline and achieved a 60% improvement in production rates. The Tunnelling and Underground Construction Academy, set up for Crossrail, is now training staff for other projects. The Construction Leadership Council's analysis of 20,000 projects found those with the best front-end planning had 20% lower costs and were delivered 10–15% faster.


Cross-cutting: the gold-plating and risk aversion problem

This runs through multiple documents but is articulated most powerfully in the Nuclear Regulatory Review (2025). While focused on nuclear, the review identifies three structural drivers of over-specification that apply across infrastructure. First, a culture where the system cannot reward success but can punish failure, encouraging risk aversion at every level. Second, prioritisation of process over outcomes — elaborate process serves as a protective mechanism, dispersing responsibility and reducing the need for judgement. Third, misaligned incentives — cost-plus contracts and weak competitive pressure remove incentives for efficiency, creating what the review calls "a culture of costly compliance."

The review provides striking examples: a ventilation design change during the ABWR assessment cut emissions by one ten-thousandth of the legal dose limit at enormous expense. Safety cases have become so long and complex that no single person can read and understand them. The review describes a "one-way ratchet" where regulatory complexity grows over time because no single actor has the agency to reduce it.

The NIC's evidence from rail is parallel: Network Rail identified £156m in efficiencies in its CP7 programme simply by reviewing safety standards without compromising safety. The PwC benchmarking study found HS2 Phase Two's key assets were being developed to higher specifications than comparator schemes, driving a 5% cost difference.

The nuclear review's recommended remedy — contractual mechanisms that incentivise proportionate solutions and a culture reset where outcomes matter more than process — has clear read-across to transport and other sectors.


The meta-finding: the UK knows what to do but repeatedly fails to do it

This is arguably the most important thing the documents say. The NIC notes that past studies have identified these problems but their findings have "not been applied at scale or with the consistency needed." The Stewart Review observes that the last government report on the construction sector was from 2019. The NAO's mega-projects report notes that comprehensive guidance on effective governance already exists — the problem is consistent application. The nuclear review describes a "culture of resignation" where people simply accept that projects must be slow and expensive.

Multiple documents stress that piecemeal interventions won't work. The NIC's conclusion is that "only a system wide effort targeting the root causes — rather than piecemeal interventions — will enable the UK to reap the rewards." This means reform has to be sustained across political cycles, which loops back to the foundational requirement for long-term strategic commitment.
 

MatthewHutton

Member
Joined
17 Aug 2024
Messages
1,084
Location
Oxford
The M25 / A3 junction improvemnt is over £300m in 2026.…
Right. Another modern very expensive project.

== Doublepost prevention - post automatically merged: ==

“Train people” aren’t doing it. The people employed in developing that part of the project are the same individuals who work on highway projects, power projects, etc
HS2 is very big city centric. Even Coventry our 10th largest city hasn’t been treated particularly well - and certainly the fairly large East Midlands cities haven’t.
 