The OHLE on the TAM is also earthed for vast majority, meaning it is pointless to trains running under it anyway. This is due to the low bridges other infrastructures they could not guarantee clearance from. ...............................
+
This is absolute nonsense. Some of the other "facts" stated in this thread recently make no sense either
I suppose the reality is that this really means
"The OHLE on the TAM is also earthed for the vast majority
OF NEUTRAL SECTIONS," ?.
Which would make far more sense to me (a relative lay man).
The rest of the sentence is a bit odd.
I am more and more convinced that the 398 roll-out is reaching the stage where pessimism kicks in. But it is not necessarily correct (or helpful). It has happened with all new fleets to a greater or lesser extent and this is perhaps a lot more involved than just replacing 455s with 701s. Think more like the 810s with their new OHLE. I am not saying there are no problems BUT I am inclined to believe there is nothing spectacular. People close to other projects from the past may sympathise with this view. After all who said it was going to be a walk in the park.
EDIT 13:47
Mention up thread was made of the 398s needing yellow ends adding at a late stage and/or problems with the headlights. I might be wrong but if the head lights were bright enough for Network Rail use then they would very likely be far to bright and not dipped for road use. So a solution seems to be to revert to yellow ends to satisfy use on Network Rail lines and have not-too-bright lights for road use. But that is just my guess.
Furthermore the timetable of works for 2026 provided by
@MikePJ on the
South Wales 'Metro' updates thread is interesting.
It seems to show solutions for a number of the issues raised on this thread.
I will paste it here as quoting not working :-
Aha! That style of powerpoint Gantt chart looked very familiar and so your post prompted me to go and look at the consultation page, and indeed it is from the newly-released 2026 project plan ("G5 notice of intended scope") - see attached.
Here's a summary of what's supposed to happen this year:
- 31st January: Aberdare toilet completion
- 9th Feb: Merthyr Vale and Treorchy toilet completion
- End Feb: Merthyr Tyfil, Abercynon & Tonypandy toilet completion
- March 23rd: Cardiff Bay branch wires to go live
- March 31st: Ty-Glas platform extension entry into service; Cwmbach and Llwynypia toilet completion
- April to mid-June: 398s enter service on Cardiff Bay - Pontypridd services
- July - September: 398s replace 756s on the TAM lines and 756s replace 231s and 150s on Rhymney/Bargoed <> Barry Island services
- August - high voltage connection of Ninian Park Feeder station to core valley lines overhead line network
- October - Bute Town station (note that it's written as two words) Platform 2 opening.
- Dec 13th: No 150s on the TAM lines, new faster timetable. (Note that 150s on Rhymney will still be around because they're still needed for the Vale of Glamorgan service)
- Various unspecified level boarding works are also listed, as are various signalling and track works that I don't understand from the relatively cryptic notes.
These project plans are intended to notify other industry bodies of the planned works, so TfW don't necessarily have to stick to them. But the plan and dates do capture a snapshot of what's expected at the time it was drawn up, so its fair to say that 398 introduction is definitely still on the agenda.
Attachments
CVL G5 Notice of Intended Scope for the Transformation Programme to be implemented during 2026...pdf
511.1 KB.