I’m afraid the source of this information is not dubious in anyway, and it’s time TFW we’re more open and about the current situation.
I’ll explain more now in detail and the current situation on 398 project is as follows:
- Driver training - currently only a handful of instructors known as tier 1 and a select number of test drivers are trained to drive them. The initial plan was for these test drivers to operate between Cardiff Central and Severn Tunnel Junction to accumulate the fault free hours. Due to restrictions from Network rail, we were not allowed to operate them on the mainline or CVL due to timetable constraints. A plan was then made to send them to old Derby to run them there. All runs on the valleys have been for route proving, and in the summer last year a major fault occurred which reset the hours to zero again. Tier 2 instructors are yet to be trained up to deliver the training, and there is no official programme to date signed off and ready to be deployed. The pilot course has been delayed again due to constant failures. The new date for this is approximately late March, and this will need to signed off with both Aslef and RMT.
- Faults - at current the 398’s have had windscreen modifications due to the fact they were not laminated to railway specification. In doing this work seals were replaced which has covered over the original drainage system from the roof. Rainwater is now an issue, and is accumulating on the roof, which is leaking into vital electrical system, including the brake control units that are located in the roof. Two units failed at Treherbert last Friday with this issue. They are also having trouble with braking and running in multiple, and do not seem to like being coupled up. The windows will need to come out and be redone or an alternative drainage system implemented.
- Proposed operation - the 398’s are going to be operating in combined battery and overhead mode, the current system compared to the 756 is going to be an issue, and battery capacity is worst than thought. Class 756 units for comparison can do 70-80 miles on a charge where these can do roughly around 6 miles. The 756 also have a backup in forms of a diesel generator, these don’t have that. Operation around the city line, and any hold up is likely to result in a unit becoming stranded, and there is talks internally about what to do in the event of this happening. The 398’s require ideally full OLE support, and due to issues with capital and operational limitations this was not achievable. There is also an issue with the proposed door process, and senior management want full DCO operation of the doors, and tests have shown this process to be inadequate and it would be better suited to a driver open, guard close style method of work. However, this has been played down despite timing trails showing it to be quicker than the proposed method of work.
- Taffs Well depot - the design of the depot was restricted due to land being unable to be obtained, the current curve means only 398’s can be stored here. It takes so long for one unit to exit the depot due to the 3mph restriction on this that running units out for service in the morning is going to be an issue. A proposed idea was to couple units up and split them in the platform, however they would need a fitter to uncouple. The current plan would only see one fitter on shift at a time.
- 231 to mainline - A program to provide training to driver instructors has commenced and mainline will be learning these soon. I’d imagine remaining 150’s will be swapped out to cover the TAM to facilitate this.
- Toilets - installation of toilet facilities is underway at various platforms on the CVL, however budget has restricted works and these are delayed.
At current there are no 398’s signed off as fit and it’s unlikely the product will be available anytime soon. Its not what people want to hear, but safety is a priority and no matter how embarrassing it maybe, the concept in reality is just not working out as planned.