BBC have a report that Leeds tram network is being subjected to more government review and will now be delayed until late 2030's
https://www.bbc.co.uk/news/articles/c78vrzpzle2o
https://www.bbc.co.uk/news/articles/c78vrzpzle2o
Seems a perfectly sensible approach to have taken given the wide political support for this scheme but yet again central government comes up lets have another review and before we know its delayed and now subject to complete cancellation if the worst outcome materialises in 2029 general election.A planned tram system for West Yorkshire has been delayed after the government carried out a review of the project.
West Yorkshire Combined Authority (WYCA) had hoped that trams would be running on two lines in Leeds and Bradford in the early 2030s, however it is now likely to be the late 2030s.
The government had promised £2.1bn for the mass transit system, but has now told WYCA to take a more thorough approach to the development of the scheme.
West Yorkshire's mayor Tracy Brabin said she was frustrated by the delay, but added that she still believed the tram system would be in place eventually and there remained a "commitment" to ensure it happened.
To speed up delivery of the project, WYCA had hoped to plan the detail of the route while also submitting the business case for the system to the government, but it has now agreed to separate those two elements of the process.
Brabin said: "The review has advised that we take a more sequential approach.
"We had been running an innovative dual-track approach with the planning and the business case at the same time - and there was a risk to that.