BBC reporting planned engineering works to renew Dartford Jct, where the North Kent line and Dartford Loop Line meet/diverge, over February half term, with preparatory work the weekend before and follow-up work on two later dates:
www.bbc.co.uk
Will it have the same point setup as before? Also, anyone know what the platform adjustment planned at Dartford station is?
Rail lines to close for major Dartford Junction engineering works
Network Rail said an investment of £10m is being made at Dartford Junction to improve reliability.
Rail passengers are being warned of major engineering works in the Dartford area, which will see some rail lines closed for nine consecutive days.
Network Rail said an investment of £10m is being made at Dartford Junction, one of the busiest points of the railway in Kent, to improve reliability and punctuality.
The closure is scheduled for the February 2026 school half-term, beginning on Saturday, 14 February.
Network Rail said: "The £10m investment in new track at Dartford will help give the tens of thousands of passengers travelling over the junction each day more punctual journeys."
Buses will replace trains between Gravesend, Dartford, Slade Green, Barnehurst and Crayford 14-22 February, Network Rail said.
There will also be preparation work on 8 and 9 February, plus follow-up work on 1 March and 5 April.
It said this approach allows it to consolidate activity, as opposed to up 30 weekends of disruption using weekend only access.
The work will include the renewal of switches and points, new tracks and power supply installations, and platform adjustment at Dartford.
Southeastern and Thameslink services will be affected, with all routes through Dartford subject to change.
Will it have the same point setup as before? Also, anyone know what the platform adjustment planned at Dartford station is?