Southeastern metro fleet replacement/improvement

D365

Veteran Member
Joined
29 Jun 2012
Messages
13,157
As mentioned, the AT200 would be more appropriate. However, this has not come with level boarding (the only AT200s currently in existence are the 385s), so would require a new bodyshell design. I'd say that's bespoke.
Most, if not all of the upcoming rolling stock tenders stipulate at least partial level boarding. A bespoke requirement it is not.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

165009

Member
Joined
5 Sep 2016
Messages
266
Morning, does anyone know the status/whereabouts of 465045 and 466020 please? They're never on RTT when I search
 

165009

Member
Joined
5 Sep 2016
Messages
266
Yep, neither unit returns any results which has been the same every time I've checked them for the past few weeks, which made me think they've been withdrawn
 

brad465

Veteran Member
Joined
11 Aug 2010
Messages
11,380
Location
Taunton or Kent
Morning, does anyone know the status/whereabouts of 465045 and 466020 please? They're never on RTT when I search
Yep, neither unit returns any results which has been the same every time I've checked them for the past few weeks, which made me think they've been withdrawn
According to an internal source in an enthusiast group, 466020 is earmarked for being stripped for spares in the near future, though no date has yet been determined for this.
 

165009

Member
Joined
5 Sep 2016
Messages
266
According to an internal source in an enthusiast group, 466020 is earmarked for being stripped for spares in the near future, though no date has yet been determined for this.
Thanks Brad, don't suppose you've any idea on which depot and if it's visible?
 

vuzzeho

Member
Joined
11 Apr 2022
Messages
663
Location
London
Most, if not all of the upcoming rolling stock tenders stipulate at least partial level boarding. A bespoke requirement it is not.
Yes, but I was saying that Hitachi's offering does not have level boarding as part of the off the shelf design (385s). So, it would be a bespoke new version of the AT200, not an off the shelf one.
 

Waterlemon

Member
Joined
18 Sep 2023
Messages
81
Location
Waterloo
Steve White said today we could expect a decision to be announced in the first half of next year with introduction likely to be around 2029/2030.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,015
Location
West Wiltshire
Steve White said today we could expect a decision to be announced in the first half of next year with introduction likely to be around 2029/2030.
For a tender that started nearly 2 years ago, had an announced shortlist of 5 bidders 11 months ago. By now not really being any more precise than announcing sometime in 1.5 to 7.5 months is exceedingly vague.

Introduction nearer 6-7 years after starting the process is worryingly slow unless get something exceptional at end of process, rather than average or adequate.

Anyway good to know it's progressing, even if at snail pace.
 

ScotGG

Established Member
Joined
3 Apr 2013
Messages
1,585
Add in the customary delays and best case scenario 2033/34 for full introduction?
 

Stephen42

Member
Joined
6 Aug 2020
Messages
803
Location
London
For a tender that started nearly 2 years ago, had an announced shortlist of 5 bidders 11 months ago. By now not really being any more precise than announcing sometime in 1.5 to 7.5 months is exceedingly vague.

Introduction nearer 6-7 years after starting the process is worryingly slow unless get something exceptional at end of process, rather than average or adequate.

Anyway good to know it's progressing, even if at snail pace.
The first procurement notice was three years ago. Announcing a precise timeline when the business case requires external approval would be unwise, forcing a decision on a particular timeline is a good way to make a no more likely. Approval processes can also have unknown length, requests for further information before a decision can be made etc.

The shortlist of bidders was 18 months ago, this was also when the full tender information was sent out. I'd guess that compiling, producing and reviewing the requirements or external considerations factored into the timing of that rather than the shortlisting process itself. Most of the lessons learnt from previous fleet introductions across the industry boil down to "having X specified or factored into the contract would have made the introduction better". There are parts around managing when the contract needs altering or working around, but it's a lot easier if the contract doesn't need changing in the first place.

The business case would also need to consider how the fleet would be introduced. Are any depot works required? Are station/infrastructure changes needed? How are staff going to be trained? Do storage facilities need to be hired? How is the cross over of new and old fleet going to be managed at each point during introduction? The costs of all those plans need to be included so have to be known in detail.

I'd expect there's many people at Southeastern who could talk at length about the procurement progress and the amount of work gone into getting a good outcome. But disclosures about the procurement can open up the award to challenges and a 10 figure contract is well worth fighting over if there's any opportunity to do so. That means information in the public domain is going to be sparse and be stuff that all bidders have already been told.
 

Geogregor

Member
Joined
16 Sep 2016
Messages
455
Location
London
The first procurement notice was three years ago. Announcing a precise timeline when the business case requires external approval would be unwise, forcing a decision on a particular timeline is a good way to make a no more likely. Approval processes can also have unknown length, requests for further information before a decision can be made etc.

The shortlist of bidders was 18 months ago, this was also when the full tender information was sent out. I'd guess that compiling, producing and reviewing the requirements or external considerations factored into the timing of that rather than the shortlisting process itself. Most of the lessons learnt from previous fleet introductions across the industry boil down to "having X specified or factored into the contract would have made the introduction better". There are parts around managing when the contract needs altering or working around, but it's a lot easier if the contract doesn't need changing in the first place.

The business case would also need to consider how the fleet would be introduced. Are any depot works required? Are station/infrastructure changes needed? How are staff going to be trained? Do storage facilities need to be hired? How is the cross over of new and old fleet going to be managed at each point during introduction? The costs of all those plans need to be included so have to be known in detail.

I'd expect there's many people at Southeastern who could talk at length about the procurement progress and the amount of work gone into getting a good outcome. But disclosures about the procurement can open up the award to challenges and a 10 figure contract is well worth fighting over if there's any opportunity to do so. That means information in the public domain is going to be sparse and be stuff that all bidders have already been told.

All valid points but it boils down to one major question. When will the DfT, and the treasury, be ready to give green light. Everything else is secondary.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,015
Location
West Wiltshire
All valid points but it boils down to one major question. When will the DfT, and the treasury, be ready to give green light. Everything else is secondary.
And it's a great shame that none of the MPs asked that question for today's Parliamentary transport questions (although they probably would not yet a conclusive answer)
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,583
Let’s not forget that Steve White has been involved in selling trains, buying trains, and introducing new trains into service before. He knows what he’s doing.
 

Chris172

Member
Joined
3 Feb 2018
Messages
153
I read on southeastern website that they are going to retrofit a toilet on the 707s. The press release was released in January 2025, have they started the retrofitting?

 

brad465

Veteran Member
Joined
11 Aug 2010
Messages
11,380
Location
Taunton or Kent
I read on southeastern website that they are going to retrofit a toilet on the 707s. The press release was released in January 2025, have they started the retrofitting?

Don't believe they've started yet. Steve White did reveal when the 376 refurbishment began (in response to someone asking about 707 toilets) that the work takes a while to design apparently. I also suspect they won't want 707s out of service on refurbishment at the same time 376s are going through their full refurb.
 

GEC465

Member
Joined
10 Mar 2016
Messages
413
With the first 376 unit refreshed 011 is the last one to receive the blue livery. Thus marking and end of the connex SE livery
 

Phil R

Member
Joined
18 Jan 2020
Messages
162
Location
Guildford
Thanks - was that programme done solely in 2025 or were some done last year?
All done this year, or rather will be when 376011 is out later this week. 36 in 34 weeks with a site change late on to boot. It's been an impressively executed project.
 

brad465

Veteran Member
Joined
11 Aug 2010
Messages
11,380
Location
Taunton or Kent
All done this year, or rather will be when 376011 is out later this week. 36 in 34 weeks with a site change late on to boot. It's been an impressively executed project.
Do we know roughly how long the interior part of the refurb is taking per unit?
 

GEC465

Member
Joined
10 Mar 2016
Messages
413
Do we know roughly how long the interior part of the refurb is taking per unit?
Usually first few units are the longest but probably a week and a half to 2 weeks I assume once it picks up. I do wonder if 011 will be the last (again) to be done
 

ScotGG

Established Member
Joined
3 Apr 2013
Messages
1,585
Makes sense but if that's the reason it achieves sod all. They're stifling with white roofs. God knows how bad without.

Worst train IMO for summer heat. The windows are useless. Plenty of other non air con stock can get a decent breeze going such as Networkers (ventilation balls help on some stock too) but the 376s windows are hopeless.
 

Class 466

Established Member
Joined
5 Mar 2010
Messages
2,129
Location
Atherton, UK
Perhaps it’s to help with not heating up so much since they don’t have air conditioning, as with London buses?
Makes sense but if that's the reason it achieves sod all. They're stifling with white roofs. God knows how bad without.

Worst train IMO for summer heat. The windows are useless. Plenty of other non air con stock can get a decent breeze going such as Networkers (ventilation balls help on some stock too) but the 376s windows are hopeless.
it’s because the majority of this livery (like the 707s) is vinyl wrap rather than a repaint to save money. Not cost effective to repaint an area barely seen or noticed by most people.
 