Network Rail have publicly set out the plan to close the A6006 at Normanton on Soar to allow demolition and replacement of Kirk Hill Bridge
The letter from Network Rail has no reference to the "E word" because apparently it's been about freight clearances all along. The 10 year, 279 page "MML Electrification progress updates" thread was a kind of fever dream and the planning application for this work that said it was for electrification was all down to a clerical error by the lad on work experience.
The image below is a screenshot from the letter sent to local stakeholders. To summarise.
- Work starts on site on 29th September
- The road closes completely on 6th October
- Bridge demolition at Christmas
- Construction during 2026
- All works complete and road reopened by 1st September 2026.

11 months does seem like a very long time to do the work.
Edited - improved clarity about the text contained in the image.
The letter from Network Rail has no reference to the "E word" because apparently it's been about freight clearances all along. The 10 year, 279 page "MML Electrification progress updates" thread was a kind of fever dream and the planning application for this work that said it was for electrification was all down to a clerical error by the lad on work experience.
The image below is a screenshot from the letter sent to local stakeholders. To summarise.
- Work starts on site on 29th September
- The road closes completely on 6th October
- Bridge demolition at Christmas
- Construction during 2026
- All works complete and road reopened by 1st September 2026.

11 months does seem like a very long time to do the work.
Edited - improved clarity about the text contained in the image.