Transpennine Route Upgrade and Electrification updates

kmc1962

Member
Joined
25 Feb 2024
Messages
12
Location
Huddersfield
Some time ago, there was talk that Brighouse Station would need to be upgraded prior to the Huddersfield Station blockades. Now that the Huddersfield closure is almost upon us, has anything actually been done at Brighouse?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

skyhigh

Established Member
Joined
14 Sep 2014
Messages
6,886
Some time ago, there was talk that Brighouse Station would need to be upgraded prior to the Huddersfield Station blockades. Now that the Huddersfield closure is almost upon us, has anything actually been done at Brighouse?
They are/have been doing work there the last couple of weeks, though I have no idea what.
 

KN94

Member
Joined
12 Mar 2025
Messages
71
Location
Stalybridge
Some time ago, there was talk that Brighouse Station would need to be upgraded prior to the Huddersfield Station blockades. Now that the Huddersfield closure is almost upon us, has anything actually been done at Brighouse?
They're putting in a semi-permanent structure, presumably for staff needs and I believe the car park is being closed and only used for the buses and staff.
I'm not sure about any platform work. I'd imagine a lot of that work was done before TPE started calling there. The platform isn't long enough for six cars but that is a bigger fix which probably isn't worth doing.
 

GhostManDN91

Member
Joined
2 Oct 2022
Messages
147
Location
Wigan
I'm guessing trains longer than 4 carriages can still call at Brighouse with SDO or whatever trains use for short platforms?
 

_toommm_

Established Member
Joined
8 Jul 2017
Messages
6,301
Location
South West London
This has probably been mentioned, but with Mirfield station being redone, has the curve from Deighton been straightened out? I remember from commuting my drink would be sent flying at Heaton Lodge Jn.,and after Morley tunnel, but it seems going from Deighton to Mirfield it doesn't fly anymore, but it definitely still does in the opposite direction.
 

Tim_UK

Member
Joined
9 Jan 2019
Messages
225
This has probably been mentioned, but with Mirfield station being redone, has the curve from Deighton been straightened out?

I don’t think that has changed. The existing lines will be the slow lines on a very similar layout to today.


On the other hand, the new fast lines will have a massive gentle curve.
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,307
Location
Bolton
They're putting in a semi-permanent structure, presumably for staff needs and I believe the car park is being closed and only used for the buses and staff.
I'm not sure about any platform work. I'd imagine a lot of that work was done before TPE started calling there. The platform isn't long enough for six cars but that is a bigger fix which probably isn't worth doing.
A toilet for passengers has also been installed, and there is lots of new paint.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,191
Location
West Wiltshire
DfT has issue press release that Church Fenton - York is complete

  • electrification and upgrades along the rail line between Church Fenton and York are completed on time and on budget – a major step in rebuilding Britain’s transport infrastructure
Completed upgrades to Church Fenton to York rail line will bring passengers faster trains and more reliable services.

Thousands of passengers are now one step closer to faster, more frequent and reliable trains across the North, as the electrification of the Church Fenton to York rail line is completed today (5 August 2025), part of the £11 billion government-funded Transpennine Route Upgrade (TRU).

Faster trains will cut journey times between York and Leeds by 10 minutes and Manchester and Leeds from 50 minutes to 42 minutes, with up to 6 fast services an hour – making it easier for people to get to work, do business and travel across the region.

These upgrades will bring passengers faster trains, whilst a new signalling system and bridge upgrades will make trains more reliable and allow more services to run.

Extensive station improvements along the route will also improve accessibility and facilities at the busiest stations across the North.

 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,668

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,621
Location
Northampton
The hyperbole surrounding this part of the project is frankly embarrassing. I get it but, it doesn't need this level of release in my opinion!
Gone are the days of government letting anything slide into the 'in other news...' section. But good to see the press release following on reasonably quickly from the ORR authorisation. Does anybody know if TPE have already started panning up at Church Fenton north yet?
 
Joined
8 Feb 2021
Messages
1,060
Location
Manchester
Gone are the days of government letting anything slide into the 'in other news...' section. But good to see the press release following on reasonably quickly from the ORR authorisation. Does anybody know if TPE have already started panning up at Church Fenton north yet?
802 APCO now at Ulleskelf/River Wharfe bridge, live since Sunday 03/08
 

Scotrail88

Member
Joined
21 Jul 2014
Messages
454
802 APCO now at Ulleskelf/River Wharfe bridge, live since Sunday 03/08
Would there be the ability for Scarborough trips on 802 to use it for the short distance between York and Ulleskelf?

Would obviously need to be arr/dep the appropriate platform at York.
 

Paul AC

Member
Joined
3 Aug 2025
Messages
242
Location
Timperley
From that gov.uk press release:
Today’s upgrade will enable electric TransPennine Express (TPE) trains to run from Manchester Victoria to Stalybridge and Church Fenton to York – electrifying both ends of the route.
Or, more correctly, from Manchester Victoria to a couple of miles short of Stalybridge, and from a mile or so beyond Church Fenton to York.
 

nr758123

Member
Joined
3 Jun 2014
Messages
646
Location
West Yorkshire
From that gov.uk press release: Today’s upgrade will enable electric TransPennine Express (TPE) trains to run from Manchester Victoria to Stalybridge and Church Fenton to York – electrifying both ends of the route.

Or, more correctly, from Manchester Victoria to a couple of miles short of Stalybridge, and from a mile or so beyond Church Fenton to York.
From an earlier Network Rail press release, in 2013
The next major improvements will arrive in December 2014, when electric trains will be able to run from Liverpool to Manchester via Newton le Willows and Wigan and from December 2016, when they will run between Preston and Blackpool, Manchester and Preston and Manchester and Stalybridge. This will be followed by the completion of trans-Pennine electrification from Stalybridge through Huddersfield on to Leeds, York and Selby by December 2018.
The North West electrification programme is being delivered in five phases between December 2013 and December 2016:
  • Phase 1: Between Castlefield Junction and Newton Le Willows by December 2013
  • Phase 2a: Between Liverpool and Newton Le Willows
  • Phase 2b: Between Huyton and Wigan
  • Phase 2c: Between Ordsall Lane and Manchester Victoria, all by December 2014
  • Phase 3: Preston to Blackpool, by May 2016
  • Phase 4: Manchester Victoria to Preston (Euxton Junction), by December 2016
  • Phase 5: Manchester Victoria to Stalybridge, Guide Bridge to Stalybridge, December 2016
So I make the Stalybridge electrification eight years late, not "on time" as is now being claimed.
 

Spartacus

Established Member
Joined
25 Aug 2009
Messages
3,833
From an earlier Network Rail press release, in 2013


So I make the Stalybridge electrification eight years late, not "on time" as is now being claimed.

That was before the scope changed significantly, changing from a simple electrification of existing infrastructure to a full route upgrade with civil engineering work on varying scales almost throughout. Ineviably timeframes changed too.
 

darylyates17

Member
Joined
8 Nov 2015
Messages
489
Location
St Helens
From that gov.uk press release:

Or, more correctly, from Manchester Victoria to a couple of miles short of Stalybridge, and from a mile or so beyond Church Fenton to York.
I wonder when the Neville Hill-Church Fenton section will be completed allowing Leeds-York to be fully electrified?
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,307
Location
Bolton
802 APCO now at Ulleskelf/River Wharfe bridge, live since Sunday 03/08
TPE previously chose, for whatever reason, to spend several years not using the Apco at Colton Jn, north of Newcastle, and later at Stalybridge, even though they were installed and authorised. I interpreted the question as being are they actually doing so rather than is the infrastructure ready, which hasn't been in doubt.

My interpretation of your answer is that they do use all, or at least this particular one, of the relevant Apco points but I'm not certain?

== Doublepost prevention - post automatically merged: ==

The hyperbole surrounding this part of the project is frankly embarrassing. I get it but, it doesn't need this level of release in my opinion!
It does seem like a bit of an exaggeration to say:
Electric trains running between York and Church Fenton is a significant step forward in the Transpennine Route Upgrade programme.

== Doublepost prevention - post automatically merged: ==

I wonder when the Neville Hill-Church Fenton section will be completed allowing Leeds-York to be fully electrified?
The integrated rail plan suggested 2032 approximately, but that document hasn't been government policy for a long time. The replacement policy is ambiguous. @Bald Rick disagreed with the hypothetical 2032 date as being several years too late even when it was first announced.
 
Last edited:

Manutd1999

Member
Joined
21 Feb 2021
Messages
549
Location
UK
From the outside, civil works between Hudds. and Dewsbury seem to be progressing well and could be mostly complete in 2026(?). Track and wiring could then follow in 2027.

According to this presentation, Neville Hill-Church Fenton is on a similar timeline, so Huddersfield to York could be fully wired by ~2028.

That leaves the Stalybridge-Hudds section, which seems to be running slightly further behind. That said, getting a TWAO by2026 should be doable (?). Civil works could then follow on nicely from the Dewsbury section in 2027 onwards.

Completion of the whole scheme by 2030 could/should be feasible.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,621
Location
Northampton
However, there has been very little publicity about completing sections of MML. Even before it was "paused".
There was a big press release for completion of Kettering-Wigston, it was just rather late! Granted, they didn't make a song and dance about Market Harborough.
 

3RDGEN

Member
Joined
6 Mar 2023
Messages
638
Location
Hull
Replacement of the foot crossing at Copmanthorpe was part of the Church Fenton - York works but I am not aware it's progressed after the planning application was withdrawn? Unless that happens the line speed can't be increased in that area on the Leeds lines can it?

From the outside, civil works between Hudds. and Dewsbury seem to be progressing well and could be mostly complete in 2026(?). Track and wiring could then follow in 2027.

According to this presentation, Neville Hill-Church Fenton is on a similar timeline, so Huddersfield to York could be fully wired by ~2028.

That leaves the Stalybridge-Hudds section, which seems to be running slightly further behind. That said, getting a TWAO by2026 should be doable (?). Civil works could then follow on nicely from the Dewsbury section in 2027 onwards.

Completion of the whole scheme by 2030 could/should be feasible.
The NR CP7 Enhancements Plan - June 25 "https://www.networkrail.co.uk/wp-content/uploads/2025/06/CP7-EDP-June-2025.pdf" has;

Huddersfield - Ravensthorpe - Leeds - Feb 2030.

Leeds - Church Fenton - April 2030.

Stalybridge - Huddersfield will be CP8 I assume so isn't mentioned but 2032 has been quoted.
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,668
Leeds to Church Fenton feels like it should be sooner based on progress. I see Neville Hill is starting, with the subgrade for the new alignment of main line and sidings progressing nicely.
 

43095john

Member
Joined
16 Jan 2009
Messages
102
Location
UK
Would there be the ability for Scarborough trips on 802 to use it for the short distance between York and Ulleskelf?

Would obviously need to be arr/dep the appropriate platform at York.
No, The Scarborough 802 workings still remain on Diesel. Some of these use P4 at York and there is no APCO balises at York Station.

It has happened before during times of disruption where a Newcastle 802 working has had to terminate in Platform 4, but had to stop on Platform 3 to avoid going into P4 with a Pantograph Up
 

Scotrail88

Member
Joined
21 Jul 2014
Messages
454
No, The Scarborough 802 workings still remain on Diesel. Some of these use P4 at York and there is no APCO balises at York Station.

It has happened before during times of disruption where a Newcastle 802 working has had to terminate in Platform 4, but had to stop on Platform 3 to avoid going into P4 with a Pantograph Up
Would think with some planning it would be possible to use platforms suitable for this.
 

wilsontown

Member
Joined
11 Feb 2012
Messages
144
The bit that caught my attention there was that they're claiming a time saving of 10 minutes between York and Leeds. Given that the fastest trains now do it in about 22 minutes, where does that come from?
 

Killingworth

Established Member
Joined
30 May 2018
Messages
6,487
Location
Sheffield
The bit that caught my attention there was that they're claiming a time saving of 10 minutes between York and Leeds. Given that the fastest trains now do it in about 22 minutes, where does that come from?
Wild optimism if it were true, but it says 10 minutes between York and Manchester, only 2 minutes of that between York and Leeds. It's carefully worded to say 'will cut', but not when. The full glowing announcement is here; https://www.gov.uk/government/news/rail-boost-for-the-north-transpennine-upgrade-one-step-closer

Faster trains will cut journey times between York and Manchester by 10 minutes and Manchester and Leeds from 50 minutes to 42 minutes, with up to 6 fast services an hour – making it easier for people to get to work, do business and travel across the region.
 