• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Wigan to Bolton electric services

Status
Not open for further replies.

Gathursty

Established Member
Joined
31 May 2011
Messages
2,651
Location
Wigan
I notice there was a test train under the newly wired Wigan - Bolton line. What is the timetable for electric services on this line?

I'd like to have a ride one weekend.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

TrainzBK

Member
Joined
9 Apr 2018
Messages
46
At present services are still operated by the 769 with a power changeover at Bolton. The power changeover is planned to move to Ince eventually but there is currently no timeframe for this.
 

HST125Scorton

Member
Joined
4 Jun 2019
Messages
158
Location
Atherton
Overnight test running on the OHLE was ran during the early hours. On Tuesday 3rd June 323224 & 323227 worked 3Z98 0118 WGN to WGN via BON. While on Wednesday 4th June 331017 & 331026 worked 3Z98 0118 WGN to WGN via BON. Out of the two test paths only the ex 0118 path ran. I do believe the testing was successful. I'm not 100% sure but it was mentioned that the switch over will move to Ince from the end of this month. "Should" be all 769 Bi-Mode on that route from December timetable changes with only the diesels 15x services via Atherton. Plans may change before that.
 

DimTim

Member
Joined
11 Aug 2013
Messages
194
Why is the power changeover remaining as the test trains were electric from Wigan NW?
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,295
Location
Bolton
Why is the power changeover remaining as the test trains were electric from Wigan NW?
Trains will change at Ince because there are no wires Wigan Wallgate to Southport inclusive, so they can't use them there.
Overnight test running on the OHLE was ran during the early hours. On Tuesday 3rd June 323224 & 323227 worked 3Z98 0118 WGN to WGN via BON. While on Wednesday 4th June 331017 & 331026 worked 3Z98 0118 WGN to WGN via BON. Out of the two test paths only the ex 0118 path ran. I do believe the testing was successful. I'm not 100% sure but it was mentioned that the switch over will move to Ince from the end of this month. "Should" be all 769 Bi-Mode on that route from December timetable changes with only the diesels 15x services via Atherton. Plans may change before that.
I think once the ORR authorisation is given it will be a quick process.
I notice there was a test train under the newly wired Wigan - Bolton line. What is the timetable for electric services on this line?

I'd like to have a ride one weekend.
Unfortunately you won't be able to ride a 323 or 331 at the moment.
 

Gathursty

Established Member
Joined
31 May 2011
Messages
2,651
Location
Wigan
Trains will change at Ince because there are no wires Wigan Wallgate to Southport inclusive, so they can't use them there.

I think once the ORR authorisation is given it will be a quick process.

Unfortunately you won't be able to ride a 323 or 331 at the moment.
Thanks for the reply. I'll have to be a bit more patient.
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,295
Location
Bolton
Thanks for the reply. I'll have to be a bit more patient.
Fingers crossed for some engineering works or a Sunday that sees a 323 or 331 swapped in, although that will probably be a 2026/2027 thing if it does come along. Obviously the Sunday situation is quite parlous at present and for at least the remainder of the current timetable.
 

pokemonsuper9

Established Member
Joined
20 Dec 2022
Messages
4,633
Location
Greater Manchester
I've noticed some power changeover shaped signs have appeared at Hindley and Ince. They're covered up for now so I can't be certain that's what they are.
 
Status
Not open for further replies.

Top