I thought I would post the following update on the Whitby line and the funds allocated to it from the Boulby mine works.
This comes courtesy of a FOI request to North Yorkshire Council from the Whitby Community Network in July this year.
The executive summary of the response is as follows:
- NYC have partially claimed the funds and will continue to do so.
- They believe that the funds allocated will be sufficient to enable the eight trains a day each way.
- Dependant on the design process, they envisage that the eight trains a day should be in place by around 2027.
So all in all, excellent news, particularly since things had gone alarmingly quiet on this front - Whitby may finally be on the verge of getting its rightful railway service back.
www.whitbycommunitynetwork.org
This comes courtesy of a FOI request to North Yorkshire Council from the Whitby Community Network in July this year.
The executive summary of the response is as follows:
- NYC have partially claimed the funds and will continue to do so.
- They believe that the funds allocated will be sufficient to enable the eight trains a day each way.
- Dependant on the design process, they envisage that the eight trains a day should be in place by around 2027.
So all in all, excellent news, particularly since things had gone alarmingly quiet on this front - Whitby may finally be on the verge of getting its rightful railway service back.
Woodsmith Mine and S106 funds for improved rail services – Whitby Community Network CIC
Whitby Community Network said:In 2015 North Yorkshire County Council was party to an S106 agreement with York Potash Ltd (at the time, currently Anglo American) for provision of a Rail Infrastructure Contribution. This was for “provision of up to £4,550,000 (index linked) towards the cost of infrastructure upgrades required to facilitate the Rail Services on the Middlesbrough to Whitby rail line”. It additionally stated “In the event that the Rail Infrastructure Contribution provides insufficient funds to procure an additional four services between Middlesbrough and Whitby to use its reasonable endeavours to investigate and apply for all alternative sources of funding”.
Please define
Whether the payment of the agreed sum has been paid to North Yorkshire Council in line with these terms? If it has not been paid, please define when it will be paid by?
What infrastructure upgrades have been facilitated by these funds?
Whether the funding was indeed judged sufficient to to provide the desired 8 daily services between Whitby and Middlesbrough? If the answer is that it was not sufficient, whether NYC has applied for suitable additional funding to provide these 8 daily services?
By which date the Whitby to Middlesbrough line will provide the 8 daily services?
The reply from NYC was as follows
"Partial payment of the S106 sums have already been drawn down by NYC and the current expectation is that the remaining funds will be drawdown this year.
The S106 funds have facilitated local line speed enhancements and it is currently expected that the remaining infrastructure upgrades will be delivered over the next two years.
Work on detailed design and costs on the planned infrastructure upgrades is being finalised this year, however the current expectation is that the S106 funds will be sufficient to facilitate the desired 8 daily services.
The current expectation for a start of service date for the 8 daily services is June 2027 however that date is indicative and subject to the detailed design and costs work being finalised, and an agreed programme of works with Network Rail to deliver the infrastructure upgrades."