Certainly looks as though the 720/5s have been able to pass through the acceptance process as you would expect as many of the early build were just stored once they were built I recollect.
Do the earlier builds require any modifications or updates to match the 720/5s, or are they identical (other than time of manufacture)? I'm wondering if there was anything learnt from the earlier units that informed changes to the 720/5s, that now needs to be retrospectively applied to the earlier units and could be the source of delay
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,284
Location
West Wiltshire
Following units have had a charge raised against them on 2nd July 24

701517/518/519/520/521/522/523/524/527/528/529/530

701002/057

https://find-and-update.company-information.service.gov.uk/company/10754652/filing-history
I think the list of charges is now

002, 004, 006, 009, 011, 012, 013, 014, 015, 016, 017, 018, 019, 020, 021, 022, 023, 024, 025, 026, 027, 028, 029, 030, 031, 032, 033, 034, 035, 036, 037, 038, 039, 040, 041, 042, 043, 044, 045, 046, 047, 048, 049, 050, 051, 052, 053, 054, 055, 056, 057, 505, 506, 507, 508, 509, 510, 511, 512, 513, 514, 515, 516, 517, 518, 519, 520, 521, 522, 523, 524, 527, 528, 529, 530

Missing units :
001, 003, 005, 007, 008, 010, 058, 059, 060
501, 502, 503, 504, 525, 526

51 of 60 10car, and 24 of 30 5car,
so 630 of 750 (84%) vehicles accepted


EDIT must be missing one, as there are 79 charges (1 general, 1 simulators, 1 spares, and thus 75 trains)
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
8,051
Location
Surrey
I think the list of charges is now

002, 004, 006, 009, 011, 012, 013, 014, 015, 016, 017, 018, 019, 020, 021, 022, 023, 024, 025, 026, 027, 028, 029, 030, 031, 032, 033, 034, 035, 036, 037, 038, 039, 040, 041, 042, 043, 044, 045, 046, 047, 048, 049, 050, 051, 052, 053, 054, 055, 056, 057, 505, 506, 507, 508, 509, 510, 511, 512, 513, 514, 515, 516, 517, 518, 519, 520, 521, 522, 523, 524, 527, 528, 529, 530

Missing units :
001, 003, 005, 007, 008, 010, 058, 059, 060
501, 502, 503, 504, 525, 526

51 of 60 10car, and 24 of 30 5car,
so 630 of 750 (84%) vehicles accepted


EDIT must be missing one, as there are 79 charges (1 general, 1 simulators, 1 spares, and thus 75 trains)
Be interesting to know whether SWR are now fully liable for leasing charges or not?
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,284
Location
West Wiltshire
Be interesting to know whether SWR are now fully liable for leasing charges or not?
Based on notes in recently published Rock Rail accounts, appears once accepted they are generating lease income.

There was in 2023 damages/compensation from Alstom, but much less than previous 2 years, I guess SWR gets rebated this late delivery and/or not performing money. They can then pay for extended 455 leases with it.

Looking at other notes, eg lease commitments etc, it suggests SWR have gradually been paying for more of the fleet (as they are accepted) so presumably now leasing about 84% of the fleet.

Of course if late delivery compensation is now drying up, rather suggests SWR are leasing both 701s and the legacy 455 fleet, without any compensation covering the double leasing.

Unclear to me why DfT would tolerate leasing two fleets (except for short transition overlap of few weeks as old trains are replaced by new)
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
8,051
Location
Surrey
Based on notes in recently published Rock Rail accounts, appears once accepted they are generating lease income.

There was in 2023 damages/compensation from Alstom, but much less than previous 2 years, I guess SWR gets rebated this late delivery and/or not performing money. They can then pay for extended 455 leases with it.

Looking at other notes, eg lease commitments etc, it suggests SWR have gradually been paying for more of the fleet (as they are accepted) so presumably now leasing about 84% of the fleet.

Of course if late delivery compensation is now drying up, rather suggests SWR are leasing both 701s and the legacy 455 fleet, without any compensation covering the double leasing.

Unclear to me why DfT would tolerate leasing two fleets (except for short transition overlap of few weeks as old trains are replaced by new)
DfT won't want to as it will be hurting their budget so could lead to cutbacks elsewhere but there hardly in a position to really influence SWR short of taking the contract away from them and bringing in a team that knows how to get new trains into service - James Burle from GA springs to mind
 

HamworthyGoods

Established Member
Joined
15 Jan 2019
Messages
4,487
DfT won't want to as it will be hurting their budget so could lead to cutbacks elsewhere but there hardly in a position to really influence SWR short of taking the contract away from them and bringing in a team that knows how to get new trains into service - James Burle from GA springs to mind

The issue at SWR with the 701 is not an issue with the new trains as such but the method of working - these are the first SWR units not under guard control and there are challenges with the method of working. Whilst the DOO cameras are the same as on the 345s issues are being raised as this is the first use of non guard controlled stock on SWR. This occurring whilst a national dispute is ongoing is challenging.

The single daily 701 diagram runs under a trial agreement with ASLEF.
 

Peter Sarf

Established Member
Joined
12 Oct 2010
Messages
9,840
Location
Croydon
Do the earlier builds require any modifications or updates to match the 720/5s, or are they identical (other than time of manufacture)? I'm wondering if there was anything learnt from the earlier units that informed changes to the 720/5s, that now needs to be retrospectively applied to the earlier units and could be the source of delay
Cab redesign I seem to recall. This involved moving the bulkhead further back as the cabs on 701s were smaller than on other Aventras. Not raised / discovered / addressed until after some/many had been built.
 

Sutton in Ant

Member
Joined
2 Mar 2021
Messages
256
Location
Sutton Surrey
DfT won't want to as it will be hurting their budget so could lead to cutbacks elsewhere but there hardly in a position to really influence SWR short of taking the contract away from them and bringing in a team that knows how to get new trains into service - James Burle from GA springs to mind
I believe that this new government is going to be putting the railways back into public ownership.
 

Waterlemon

Member
Joined
18 Sep 2023
Messages
82
Location
Waterloo
The issue at SWR with the 701 is not an issue with the new trains as such but the method of working - these are the first SWR units not under guard control and there are challenges with the method of working. Whilst the DOO cameras are the same as on the 345s issues are being raised as this is the first use of non guard controlled stock on SWR. This occurring whilst a national dispute is ongoing is challenging.

The single daily 701 diagram runs under a trial agreement with ASLEF.
There very much were issues with the 701's.
345's dont have DOO cameras
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,235
There very much were issues with the 701's.
So they have different cameras to the 710s and 720s? Surprising if true. I'd have thought they'd all be of a standard design.

== Doublepost prevention - post automatically merged: ==

Cab redesign I seem to recall. This involved moving the bulkhead further back as the cabs on 701s were smaller than on other Aventras. Not raised / discovered / addressed until after some/many had been built.
And redesigning the standard Aventra drivers desk which while acceptable elsewhere, was seemingly not acceptable to ASLEF locally.
 
Last edited:

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,284
Location
West Wiltshire
And redesigning the standard Aventra drivers desk which while acceptable elsewhere, was seemingly not acceptable to ASLEF locally.
A concept I have never really understood, how can ASLEF agree anything nationally (pay, conditions, design of a cab etc), if a local branch is allowed to veto the decision. Undermines the Executive.

It is all very strange to me, because I am only familiar with employment contracts that basically say your role and duties and in return for being paid that's what you do. I have never come across anything like if you don't like the decor or style of desk in your workplace then can refuse to work.

I kind of feel not being told real reason.
 

Flange Squeal

Established Member
Joined
17 Jul 2012
Messages
1,867
A concept I have never really understood, how can ASLEF agree anything nationally (pay, conditions, design of a cab etc), if a local branch is allowed to veto the decision. Undermines the Executive.
Pay and conditions aren’t negotiated and agreed nationally - they are negotiated between the operator and their local ASLEF company council. That’s why drivers on each TOC have different pay and conditions.
 

Clarence Yard

Established Member
Joined
18 Dec 2014
Messages
3,278
DfT won't want to as it will be hurting their budget so could lead to cutbacks elsewhere but there hardly in a position to really influence SWR short of taking the contract away from them and bringing in a team that knows how to get new trains into service - James Burle from GA springs to mind

The DfT influence is all over this because SWR is on an NRC so every significant move has to be agreed with them first. As stated above, the problem is staff relations - there are still those that do not want them at all because of the changed role of the guard.

Staff relations on SWR are a world away from those on GA and it has little to do with who manages them.
 

Invincible

Member
Joined
23 Apr 2022
Messages
856
Location
Surrey
Pay and conditions aren’t negotiated and agreed nationally - they are negotiated between the operator and their local ASLEF company council. That’s why drivers on each TOC have different pay and conditions.
Didn't the Conservatives change pay and conditions negotiations from the local operator to the national Rail Delivery group.
 

DMckduck

Member
Joined
26 Jul 2020
Messages
488
Didn't the Conservatives change pay and conditions negotiations from the local operator to the national Rail Delivery group.
They tried to across the board with both the RMT and ASLEF, it achieved precisely what anyone with a brain knew it would and that was nothing.

Privatisation and competition means every company has different terms and conditions and pay rates, so negotiating them under one umbrella will never make sense.
 
Joined
2 Jun 2023
Messages
1,096
Location
Richmond
I have recently learnt from my friend of mine who knows an SWR driver that the 701 software is not built from scratch (entirely Aventra software as we were all guessing) and instead based off the 345 software which itself is basically Electrostar software. And apparently completely to my surprise, the only train in the family to have software built from the ground up and not related to the Electrostar was the 710. Why they decided to go back to an old codebase instead of using the newer one is anyone's guess, my friend, a software engineer says.

He also said that according to this SWR driver when the train was delivered it had interlock light issues because it was expecting 6 doors per coach rather than 4....
 
Last edited:

wickham

Member
Joined
3 Feb 2021
Messages
710
Location
Knaphill
Re: Post 9634 and associated comments regarding charges raised in connection with the Class 701 fleet: I am a little confused as to the effective date of this batch. The document sates "Document created 25.06.24" and "Received for filing 02.07.24". Am I therefore incorrect in thinking that the effective date is actually 25.06.24 and not 02.07.24 as stated in the post ? I am not nit-picking but this does make a defference for those of us that keep records, ie: it is a different month !
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,235
I have recently learnt from my friend of mine who knows an SWR driver that the 701 software is not built from scratch (entirely Aventra software as we were all guessing) and instead based off the 345 software which itself is basically Electrostar software. And apparently completely to my surprise, the only train in the family to have software built from the ground up and not related to the Electrostar was the 710. Why they decided to go back to an old codebase instead of using the newer one is anyone's guess, my friend, a software engineer says.
The 345s had a major software update early this year which largely fixed the ongoing reliability problems.

Could it be that the 701s did have Aventra-specific software, but this was replaced with the 345 version on the basis of getting the trains working?

The 345s sound completely different to other Aventras, whereas the 701s sound like a standard Aventra. I had assumed the difference with the 345s was due to the software, but perhaps not?
 

wickham

Member
Joined
3 Feb 2021
Messages
710
Location
Knaphill
5Q84 1315 Marchwood to Wimbledon Park ran yesterday 09.07.24 - anyone know which unit was moved please ?
I note that another 5Q84 is booked to run tomorrow 11.07.24.
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,741
Joined
2 Jun 2023
Messages
1,096
Location
Richmond
An image showing some sidings, various network rail staff and emergency crew, as well as a 701 on one of the tracks.

Casualties exercise, 701037
 

Top