Transpennine Route Upgrade and Electrification updates

stibz

Member
Joined
7 May 2014
Messages
83
Meanwhile Network Rail have submitted plans for a compound near Ravensthorpe station.


Been there well over a month now, all set-up, access through old power station, they cut a lot of trees down too, on the old power station tipping ground beside the present line running from Dewsbury, where they have plans to build the "Baker Viaduct".
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Spartacus

Established Member
Joined
25 Aug 2009
Messages
3,836
Been there well over a month now, all set-up, access through old power station, they cut a lot of trees down too, on the old power station tipping ground beside the present line running from Dewsbury, where they have plans to build the "Baker Viaduct".

This is a new one, opposite the farm on Lees Hall Road, near Lees Hall itself.
 

GardenRail

Member
Joined
26 Mar 2023
Messages
504
Went for a look at Batley the other day. Bridge done, but left half finished, left to the weeds, and not even finished the tarmac.PXL_20230825_133235089.jpgPXL_20230825_133554671.jpgPXL_20230825_133006122.jpgPXL_20230825_132814338.jpgPXL_20230825_132718916.jpgPXL_20230825_132948708.jpg
 

jonesy3001

Established Member
Joined
13 Jul 2009
Messages
3,317
Location
Otley, West Yorkshire
Was looking at the timetables on the northern website and this was on the site for the early morning services from the 26th to the 29th of september, what are they doing overnight on the Victoria to stalybridge line thought the overheads on that line had been done?
 

Attachments

  • Screenshot_20230827_100421_Microsoft 365 (Office).jpg
    Screenshot_20230827_100421_Microsoft 365 (Office).jpg
    54.8 KB · Views: 45

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,865
Location
Beeston (Notts)
Was looking at the timetables on the northern website and this was on the site for the early morning services from the 26th to the 29th of september, what are they doing overnight on the Victoria to stalybridge line thought the overheads on that line had been done?
It's probably final works to allow the overheads to be switched on at the Stalybridge end, such as installing jumpers in overlaps/at crossovers, cutting in Section Insulators, any earthing/bonding work etc.
 

jonesy3001

Established Member
Joined
13 Jul 2009
Messages
3,317
Location
Otley, West Yorkshire
It's probably final works to allow the overheads to be switched on at the Stalybridge end, such as installing jumpers in overlaps/at crossovers, cutting in Section Insulators, any earthing/bonding work etc.
Cannot find anything for the guide bridge line unless they're doing the works this weekend coming, will the overheads been switched on all together or in parts?
 

stibz

Member
Joined
7 May 2014
Messages
83
Went for a look at Batley the other day. Bridge done, but left half finished, left to the weeds, and not even finished the tarmac.View attachment 141698View attachment 141699View attachment 141700View attachment 141701View attachment 141702View attachment 141703
ALL work around the Batley to Hudderfield area has seen nothing done in 3 weeks, just all stopped, nothing appears to happen on the days/nights at weekends, when the line is closed to Huddersfield. Like everyone abandoned ship, very strange, I can see from my house if anything happenes near Ravensthorpe station, nothing now for weeks.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,865
Location
Beeston (Notts)
ALL work around the Batley to Hudderfield area has seen nothing done in 3 weeks, just all stopped, nothing appears to happen on the days/nights at weekends, when the line is closed to Huddersfield. Like everyone abandoned ship, very strange, I can see from my house if anything happenes near Ravensthorpe station, nothing now for weeks.
Wasn't there a stand-down of works on TRU West quite recently?
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,559
Was looking at the timetables on the northern website and this was on the site for the early morning services from the 26th to the 29th of september, what are they doing overnight on the Victoria to stalybridge line thought the overheads on that line had been done?

It's probably final works to allow the overheads to be switched on at the Stalybridge end, such as installing jumpers in overlaps/at crossovers, cutting in Section Insulators, any earthing/bonding work etc.

Cannot find anything for the guide bridge line unless they're doing the works this weekend coming, will the overheads been switched on all together or in parts?
Still registration adjustments and wiring at Guide Bridge, commissioning of Guide Bridge TSC, short circuit testing at Countess St, telecoms testing (VLVT - Voltage Longitudinal Voltage Transverse), dynamic test train.
Entry into service is expected on/before 19/02/2024.
 

stibz

Member
Joined
7 May 2014
Messages
83
Just tried asking security onsite as to why no work, the guy said he knew nothing, but they might be on a safety course and might be back next week. So we'll have to wait and see.
 

lincolnshire

Member
Joined
12 Jun 2011
Messages
884
Indeed, something about there being too many near-misses/close-calls and the like.
Highly understandable then!
The above was the same as I was told too many safety issues so all work suspended till they come up with something new safety wise after a review.
 

jonesy3001

Established Member
Joined
13 Jul 2009
Messages
3,317
Location
Otley, West Yorkshire
Still registration adjustments and wiring at Guide Bridge, commissioning of Guide Bridge TSC, short circuit testing at Countess St, telecoms testing (VLVT - Voltage Longitudinal Voltage Transverse), dynamic test train.
Entry into service is expected on/before 19/02/2024.
So will emus be using the wires in the may timetable change or before the 19/02/2024?
Noticed the trains to hadfield on the sunday 24th september are replacement buses has that got something to do with the wires or something completely different.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,865
Location
Beeston (Notts)
So will emus be using the wires in the may timetable change or before the 19/02/2024?
Noticed the trains to hadfield on the sunday 24th september are replacement buses has that got something to do with the wires or something completely different.
Might well be something to do with the wires - perhaps the new Guide Bridge TSC goes live then? That'll require a complete block to electric traction in the affected section (which, AIUI, starts at Ardwick).
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
So there is a TSC at Stalybridge as well as the grid feeder at Heyrod and a long extension lead to Ordsall Lane?
Yes, it's normal to have a TSC at a Y-shaped junction, so that either line route be isolated and worked on while electric trains can continue to run on the other.

In this case I would have expected it to be a bit further east, which was why I asked the question in #7129.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,540
Location
Preston Lancs
Yes, it's normal to have a TSC at a Y-shaped junction, so that either line route be isolated and worked on while electric trains can continue to run on the other.

In this case I would have expected it to be a bit further east, which was why I asked the question in #7129.
Makes sense. Thanks.
 

Elecman

Established Member
Joined
31 Dec 2013
Messages
3,582
Location
Lancashire
So there is a TSC at Stalybridge as well as the grid feeder at Heyrod and a long extension lead to Ordsall Lane?
Yes indeed as it’s a junction just as there is at Guide Bridge. No different to the ones installed at Ordsall Lane and Lostock Junctions
 

507020

Established Member
Joined
23 May 2021
Messages
1,983
Location
Southport
So will emus be using the wires in the may timetable change or before the 19/02/2024?
Noticed the trains to hadfield on the sunday 24th september are replacement buses has that got something to do with the wires or something completely different.
Are we not expecting the 769s and 802s to begin using the wires from the day they are energised, without having to wait for a timetable change?
 

507020

Established Member
Joined
23 May 2021
Messages
1,983
Location
Southport
Probably need testing first before anything can use them.
Commissioned would have been a better choice of words than energised, but unless this happens before December I don’t expect it to coincide with a timetable change.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,559
Probably need testing first before anything can use them.
Entry into service is for passenger (or freight) use, following Office of Road & Rail authorisation.
It is possible to be earlier than 19/02 if all the testing & commissioning is complete and ORR authorised provided.
Are we not expecting the 769s and 802s to begin using the wires from the day they are energised, without having to wait for a timetable change?
  • 769s to Stalybridge will use OLE from EIS day 1.
  • 802s which stop at Stalybridge will also use OLE from EIS day 1.
  • APCO is installed on both Ashton and Guide Bridge lines, so express TPE 802 services should be able to use OLE from EIS day 1.
Any particular reason why there?
Thats the location of Stalybridge TSC
Yes, specifically the location of the DNO (distribution network operator) cubicles. That will complete commissioning for the tie in on the Guide Bridge line.
*APCO= Automatic Power Changeover
*EIS= Entry into service
 
Last edited:

Elecman

Established Member
Joined
31 Dec 2013
Messages
3,582
Location
Lancashire
Entry into service is for passenger (or freight) use, following Office of Road & Rail authorisation.
It is possible to be earlier than 19/02 if all the testing & commissioning is complete and ORR authorised provided.

  • 769s to Stalybridge will use OLE from day 1.
  • 802s which stop at Stalybridge will also use OLE from day 1.
  • APCO is installed on both Ashton and Guide Bridge lines, so express TPE 802 services should be able to use OLE from day 1.


Yes, specifically the location of the DNO (distribution network operator) cubicles. That will complete commissioning for the tie in on the Guide Bridge line.
The DNO for Stalybridge TSC is already in and live
 