Entry into service is for passenger (or freight) use, following Office of Road & Rail authorisation.
It is possible to be earlier than 19/02 if all the testing & commissioning is complete and ORR authorised provided.
- 769s to Stalybridge will use OLE from day 1.
- 802s which stop at Stalybridge will also use OLE from day 1.
- APCO is installed on both Ashton and Guide Bridge lines, so express TPE 802 services should be able to use OLE from day 1.
Yes, specifically the location of the DNO (distribution network operator) cubicles. That will complete commissioning for the tie in on the Guide Bridge line.