East-West Rail (EWR): Oxford-Bletchley construction progress

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Oxfordblues

Member
Joined
22 Dec 2013
Messages
1,133
The rails are I believe from Scunthorpe, welded possibly at Eastleigh, the sleepers from Doncaster and the ballast from virtual quarries at Hinksey and Basford Hall.
 

richieb1971

Established Member
Joined
28 Jan 2013
Messages
2,047
The rails are I believe from Scunthorpe, welded possibly at Eastleigh, the sleepers from Doncaster and the ballast from virtual quarries at Hinksey and Basford Hall.
Thanks for that. British efficiency at its finest then!!! Ok, where does the end product get made? I'd assume that end product gets loaded onto a train somewhere and makes its way to EWR/HS2.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,308
Thanks for that. British efficiency at its finest then!!! Ok, where does the end product get made? I'd assume that end product gets loaded onto a train somewhere and makes its way to EWR/HS2.
What do you consider as ‘end product’? The main long lengths of rail, sleepers and ballast arrive independently. Only the S&C panels are made up elsewhere, (Nottingham I think), but they are then partially dismantled for delivery, and reassembled on site before top ballasting.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,749
Location
Nottingham
What do you consider as ‘end product’? The main long lengths of rail, sleepers and ballast arrive independently. Only the S&C panels are made up elsewhere, (Nottingham I think), but they are then partially dismantled for delivery, and reassembled on site before top ballasting.
Progress Rail produce S&C in Sandiacre, near Toton depot, which is assembled and loaded onto Network Rail wagons at the one-time Freightliner depot at Beeston. Other suppliers are probably available.
 

richieb1971

Established Member
Joined
28 Jan 2013
Messages
2,047
End product would be rail as we see it laid but prepared for transport to it's destination. Seems from others responses a lot of the parts are delivered from separate sources and fabricated to the end product onsite.
 

richieb1971

Established Member
Joined
28 Jan 2013
Messages
2,047
The end product is track, and that is ‘made’ on site, as it is by far the most efficient way of transporting it.
I've never seen a train with the ingredients on it. Only trains with 100s of feet of track. Must be something Im missing in the wild.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,639
Location
Northampton
I've never seen a train with the ingredients on it. Only trains with 100s of feet of track. Must be something Im missing in the wild.
It is quite rare to have the luxury of time to assemble track on site. But yes, plenty of renewals do work by delivering the materials one by one. It's most efficient that 1 or more trains has only ballast on it, then the next train only sleepers, then the next train only rails, etc.
Pre-assembled panels are quick to install so good for possessions, but for such a large job as EWR the economics of delivering entire trainloads of sleepers at once are rather persuasive.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,953
I've never seen a train with the ingredients on it. Only trains with 100s of feet of track. Must be something Im missing in the wild.

You probably have, but may not have realised it.

A decent proportion of freight trains on the network are carrying ballast (new or used), either from the quarries to the Distribution Centres (network trips), or from those centres to jobs. Ballast is carried in box wagons or Hooper wagons, and you wouldn’t be able to tell what’s in the wagons unless you ‘know’.

Similarly sleepers are transported from the factory to the DCs in bulk, then again on to site when needed.

The trips to site are normally on Friday / Saturday late evening or night, the network trips are every weekday.
 

fgwrich

Established Member
Joined
15 Apr 2009
Messages
10,651
Location
Hampshire
It is quite rare to have the luxury of time to assemble track on site. But yes, plenty of renewals do work by delivering the materials one by one. It's most efficient that 1 or more trains has only ballast on it, then the next train only sleepers, then the next train only rails, etc.
Pre-assembled panels are quick to install so good for possessions, but for such a large job as EWR the economics of delivering entire trainloads of sleepers at once are rather persuasive.
I think the biggest luxury has to be the impressive HARSCO / Balfour Beatty NTC machine. Both for renewals like project speed on Okehampton or new lines like this / A2B etc.
 

richieb1971

Established Member
Joined
28 Jan 2013
Messages
2,047
You probably have, but may not have realised it.

A decent proportion of freight trains on the network are carrying ballast (new or used), either from the quarries to the Distribution Centres (network trips), or from those centres to jobs. Ballast is carried in box wagons or Hooper wagons, and you wouldn’t be able to tell what’s in the wagons unless you ‘know’.

Similarly sleepers are transported from the factory to the DCs in bulk, then again on to site when needed.

The trips to site are normally on Friday / Saturday late evening or night, the network trips are every weekday.
Ballast trains are usually in trains labelled network rail. Seen them many times. They have the discharge shoots at the bottom. Sleepers never seen. Rail head is really long and pre moulded it would be pretty obvious it was rail head. Would rail head exceed the length of the wagon it wad carried on?
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
I've never seen a train with the ingredients on it. Only trains with 100s of feet of track. Must be something Im missing in the wild.
Have you never seen a train with just rail, without sleepers, in long welded-up lengths bending round curves? Remarkable sight.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,953
I think the biggest luxury has to be the impressive HARSCO / Balfour Beatty NTC machine. Both for renewals like project speed on Okehampton or new lines like this / A2B etc.

Approaching its 20th Birthday! (Just turned 19). It failed immediately after laying its first sleeper (on a job, not in testing) back in 2004 near Manningtree…

Ballast trains are usually in trains labelled network rail. Seen them many times. They have the discharge shoots at the bottom.

That is just new top ballast going from distribution centre to site, and even then only some of it. Twice as much again goes for bottom ballast in box wagons or side tippers. - the latter have NR markings on but the former don’t always. Then the bulk ballast network tips from the quarries can be in all sorts of box wagons.


Rail head is really long and pre moulded it would be pretty obvious it was rail head. Would rail head exceed the length of the wagon it wad carried on?

There is a special long welded rail train which takes the rail from Scunthorpe to site. The rail is almost always delivered well ahead of the work being done, and almost always at night. Some came through Bedford fairly recently, as it happens.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Lots of pictures of trains carrying just sleepers on the Levenmouth Building a Railway Facebook page. This is just one from near the top.

 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,308
At the Bletchley end... where will the crossover point be from TVSC? Bicester Village?
There’s still another boundary at Wolvercote - the stretch from there to Bicester is controlled from Marylebone. This was confirmed a while ago in this thread.
 
Last edited:

12LDA28C

Established Member
Joined
14 Oct 2022
Messages
5,058
There’s still another boundary at Wolverton - the stretch from there to Bicester is controlled from Marylebone. This was confirmed a while ago in this thread.

Huh? How does a boundary at Wolverton affect trains running between Oxford and Milton Keynes?
 

Dr A.Johnston

Member
Joined
6 May 2016
Messages
50
An interesting video appeared today re the Claydon/Calvert HS2/EWR crossing site.


Made a point that when HS2 finishes the bridges it will be handed over to EWR teams to finish the embankments and tracklaying.
 

al green

Member
Joined
2 Oct 2011
Messages
159
An interesting video appeared today re the Claydon/Calvert HS2/EWR crossing site.


Made a point that when HS2 finishes the bridges it will be handed over to EWR teams to finish the embankments and tracklaying.
My understanding is that it is HS2 who have to finish off the missing embankments for EWR either side of the HS2 bridge. Then EWR Ltd can lay tracks on them.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,308
My understanding is that it is HS2 who have to finish off the missing embankments for EWR either side of the HS2 bridge. Then EWR Ltd can lay tracks on them.
Yes, I think that’s what’s been understood for a while, IIRC one of the EWR newsletters earlier this year said just that.
 