Another video update from 'Trains,Planes, Phones and Drones' on YouTube, covering East West Rail Link update Winslow and Mursley sections

I thought the HS2 delays, if any, would be on the Euston-OOC and north-of-Birmingham sections. Very unlikely to affect EWR works I suspect.I really hope the HS2 debacle does not affect the construction timetable of EWR. I did raise my suspicions further up the thread, and I expect the worst. I can see the east and west sections of EWR completed and a yawning gap at Calvert courtesy of HS2.
The bridge over HS2 at Calvert is already in place.
Thanks, but embankments and associated works are not. I was under the impression HS2 were responsible for construction of part of EWR at this complex intersection? Having two sets of construction teams working on different projects at the same site would not seem a good idea?The bridge over HS2 at Calvert is already in place.
A proportion of that is sorting out the bat mitigation tunnel down at Greatmoor woods as well as E-W cost constraints.It's Aylesbury that is messed up with HS2, but that's not part of the initial work anyway.
Its only bad if there is no integration on the project management front and no one talks to each other. Though I suspect the civils earthworks are relatively straightforward if the structure is in.Thanks, but embankments and associated works are not. I was under the impression HS2 were responsible for construction of part of EWR at this complex intersection? Having two sets of construction teams working on different projects at the same site would not seem a good idea?
I don't think they are on the same site. A section of the EWR route for about a mile each side of the HS2 crossing is in the hands of HS2, with no access to EWR. HS2 Ltd are supposed to complete the bridges and earthworks by the middle of this year and then hand it back to EWR who will lay the track.Thanks, but embankments and associated works are not. I was under the impression HS2 were responsible for construction of part of EWR at this complex intersection? Having two sets of construction teams working on different projects at the same site would not seem a good idea?
I’m not sure if I mentioned it in one of my posts above, but this was the state of play at the E-W / HS2 crossing a month ago. The road bridge is still in the way, so there may be an issue with diverting the road? Otherwise the ramp on the Oxford side is complete and ballasted, and I believe the other side may be, up to the edge of the bridge site, too.I don't think they are on the same site. A section of the EWR route for about a mile each side of the HS2 crossing is in the hands of HS2, with no access to EWR. HS2 Ltd are supposed to complete the bridges and earthworks by the middle of this year and then hand it back to EWR who will lay the track.
Thanks, That is the impression I was under, essentially EWR just lay the track and do S&T on the bed prepared by HS2. The Aylsebury spur section junction will also be prepared by HS2 and no doubt the small section of junction track and out of service S&T done by EWR. You can clearly see the boundary of construction responsibility on the Marston Vale video above. The "ski ramp" over HS2 is being constructed by HS2?I don't think they are on the same site. A section of the EWR route for about a mile each side of the HS2 crossing is in the hands of HS2, with no access to EWR. HS2 Ltd are supposed to complete the bridges and earthworks by the middle of this year and then hand it back to EWR who will lay the track.
Not much of a “ski ramp” though. When I checked the HS2 drawings for the intersection area last year, (it’s in the closed HS2 thread somewhere), EWR basically crosses HS2 at what will be local ground level. I think many of the photos in this thread are significantly foreshortened and are not showing what it will look like when the landscaping is 100% complete.Thanks, That is the impression I was under, essentially EWR just lay the track and do S&T on the bed prepared by HS2. The Aylsebury spur section junction will also be prepared by HS2 and no doubt the small section of junction track and out of service S&T done by EWR. You can clearly see the boundary of construction responsibility on the Marston Vale video above. The "ski ramp" over HS2 is being constructed by HS2?
Edit: Can clearly be seen in post #1008 above which I have just seen!
I think the idea was that the various north/south roads in that section could only be closed one at a time. The bridge you’re referring to, (I think OXD/27), takes Addison Road over the EWR tracks and the east end of the new infrastructure depot tracks, which is why the girders you can see are relatively long. It will be a much larger span overall than the previous brick arch. It’s possible that they won’t demolish the existing road bridge OXD/28 just next to HS2 and tie the new underbridge route in until there’s a nearby alternate route for traffic, the new bridge in the distance would seem to be the best alternative route.So I hadn’t realised that, part of the delay seems to be in the form of a road bridge being constructed over East West, after it crosses HS2 at Claydon loop.
The only gap in the embankment, having seen all the recent photos appears to be in the immediate vicinity of bridge OXD/28, ie the short distance just west of the HS2 bridge. So I don’t believe there’s a significant problem."But another point shown in the photos is that the embankment east of the HS2 bridge appears relatively complete. So I don’t agree with the view posted earlier that EWR will be delayed by outstanding embankment works".
But the other embankment is not? I think the suggestion the site (site) will not be handed over on time is contained in post #994.
I think the pics of the intersection area progress are reassuring. I think it shouldn’t take that long to open the new road and divert traffic.Picking up on Bridge OXD 28 again, This week, Phil Marsh has captured the teams installing the beams to the bridge which will carry East West over the road (I missed the fact that these weren’t in place yet). So once that is complete, and work has been ramped up on the new replacement road, the old bridge can be demolished and the gaps between OXD & HS2 bridge can be filled in.
Not their decision to makeAIUI the local authority‘s stance is that any HS2 plant and heavy traffic cannot use the local road network?
I’m sure they can‘t prevent anything already allowed by the Act, but in general HS2 have already built separate haul roads along their worksites, and in some places they have had to build temporary overbridges to avoid flat road crossings. I believe it’s part of the reason comments on overhead videos often take the view it’s a ‘scar on the landscape’, even though it’s obvious much of the width of the present linear site will be fully reinstated.Not their decision to make