Class 701 'Aventra' trains for South Western Railway: progress updates

3141

Established Member
Joined
1 Apr 2012
Messages
2,118
Location
Whitchurch, Hampshire
The middle seats on Southeastern Networkers are regularly used when the train is busy, a lot of people are happy to squeeze in, rather than stand
Yes. When I lived in Oxfordshire and regularly travelled on Chiltern's Class 165s it was normal to use the middle seats. Of course there are some people who are wider than most who may find that difficult, but the majority will sit in a centre seat in preference to standing unless their journey is very short. The trains that preceded the 165s mostly had 2 + 3 seating and nobody made a fuss about it; similarly with 4 SUBs, 4EPBs and 4VEPs.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,166
They've reported it before, while they probably could given how late the units are, I doubt they will now Alstom are improving the situation.
In any case I see no way the Treasury would authorise a replacement order of new stock. SWR would simply have to life extend its 455s and potentially source other suitable stock coming off lease, eg the Southern 455s.
 

Mordac

Established Member
Joined
5 Mar 2016
Messages
2,386
Location
Birmingham
Do ASLEF actually have a problem with the cab, or are they just throwing everything at the wall because they don't want to do the doors?
 

Bigfoot

Established Member
Joined
2 Dec 2013
Messages
1,417
Do ASLEF actually have a problem with the cab, or are they just throwing everything at the wall because they don't want to do the doors?
There are many issues. One of which is most definitely the cab.
Anon SWR Team are once again reporting rumours of a cancellation of the order.
There was a recent inspection/visit from SWR.and union people. Horrendous was the opinion of the "finished" train. Still riddled with faults, mostly software but many physical issues too.
 

Islineclear3_1

Established Member
Joined
24 Apr 2014
Messages
6,589
Location
PTSO or platform depending on the weather
In any case I see no way the Treasury would authorise a replacement order of new stock. SWR would simply have to life extend its 455s and potentially source other suitable stock coming off lease, eg the Southern 455s.
"If" SWR took on the Southern 455's, wouldn't this cause issues with yet another micro-fleet in terms of diagramming/maintenance etc? I know it's only a few but surely it would make sense to get their own stored 455's back into use
 

fgwrich

Established Member
Joined
15 Apr 2009
Messages
10,632
Location
Hampshire
"If" SWR took on the Southern 455's, wouldn't this cause issues with yet another micro-fleet in terms of diagramming/maintenance etc? I know it's only a few but surely it would make sense to get their own stored 455's back into use
It would - it has to be remembered that, not only are the Southern 455s still traditional DC tractioned units (and more expensive to maintain and operate) but also incompatible with the SWR 455s due to different PA and Passcom systems. Any units transferring over from Selhurst to Wimbledon would need the same modifications that the 456s had when they transferred across in 2014.
 

nlogax

Established Member
Joined
29 May 2011
Messages
6,022
Location
Mostly Glasgow-ish. Mostly.
Can someone explain in simple terms why at this very late stage new build 707s would be preferable over 701s which are for the most part already built? Granted there are still fixes needed in h/w and s/w but...still.
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,166
"If" SWR took on the Southern 455's, wouldn't this cause issues with yet another micro-fleet in terms of diagramming/maintenance etc? I know it's only a few but surely it would make sense to get their own stored 455's back into use
Yes, it would, but will SWR have enough rolling stock to cope with future demand? Having lost 30 707s and 24 456s surely not, even if the Class 458 programme is cancelled.

== Doublepost prevention - post automatically merged: ==

Can someone explain in simple terms why at this very late stage new build 707s would be preferable over 701s which are for the most part already built? Granted there are still fixes needed in h/w and s/w but...still.
One thing I would say about the claims that 707s are being ordered, I haven't seen the PIN (Prior Information Notice), ITT (Invitation to Tender) or the tender award announcement for this very large rolling stock order.

The whole story has to be complete nonsense. Companies and government organisations can't just go to a supplier and place an order without a competitive tendering exercise.
 

C96

Member
Joined
31 Mar 2018
Messages
45
Yes, it would, but will SWR have enough rolling stock to cope with future demand? Having lost 30 707s and 24 456s surely not, even if the Class 458 programme is cancelled.

== Doublepost prevention - post automatically merged: ==


One thing I would say about the claims that 707s are being ordered, I haven't seen the PIN (Prior Information Notice), ITT (Invitation to Tender) or the tender award announcement for this very large rolling stock order.

The whole story has to be complete nonsense. Companies and government organisations can't just go to a supplier and place an order without a competitive tendering exercise.
Is there a way to go to the second place runner up without going through another tender?
Surely it makes sense to have that clause. Especially if something happens meaning the winner pulls out.
 

DanNCL

Established Member
Joined
17 Jul 2017
Messages
5,123
Location
County Durham
The whole story has to be complete nonsense. Companies and government organisations can't just go to a supplier and place an order without a competitive tendering exercise.
SWR as a private company can directly award an order without any tendering exercise - indeed I seem to recall that South West Trains did exactly that when it came to getting the 707s. The only TOCs subject to competitive tendering rules are LNER, Northern, Southeastern, TFW and ScotRail.
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,166
SWR as a private company can directly award an order without any tendering exercise - indeed I seem to recall that South West Trains did exactly that when it came to getting the 707s. The only TOCs subject to competitive tendering rules are LNER, Northern, Southeastern, TFW and ScotRail.
It's the Treasury's money. SWR is barely a private company (and is actually classified as public sector by the ONS). It merely get a management fee for doing what it's told. There is absolutely no way it can just go and buy what it wants without tendering.
 

43096

On Moderation
Joined
23 Nov 2015
Messages
18,796
The whole story has to be complete nonsense. Companies and government organisations can't just go to a supplier and place an order without a competitive tendering exercise.
Yes they can if there are extenuating circumstances. During the pandemic there were plenty of contracts placed without going through the tendering process. Likewise, what is a direct award contract to a TOC?

In rolling stock, the Dutch placed a contract with Bombardier for TRAXX locos after the Fyra fiasco and I think ÖBB have ordered without tender from Siemens after they cancelled the Talent3 order with Alstom. That’s not dissimilar to the situation SWR are in.
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,166
Can someone explain in simple terms why at this very late stage new build 707s would be preferable over 701s which are for the most part already built? Granted there are still fixes needed in h/w and s/w but...still.
And I'm sure that assuming that DCO would be the proposed method of operation there would suddenly be issues with the 707s as well...

== Doublepost prevention - post automatically merged: ==

Yes they can if there are extenuating circumstances. During the pandemic there were plenty of contracts placed without going through the tendering process. Likewise, what is a direct award contract to a TOC?

In rolling stock, the Dutch placed a contract with Bombardier for TRAXX locos after the Fyra fiasco and I think ÖBB have ordered without tender from Siemens after they cancelled the Talent3 order with Alstom. That’s not dissimilar to the situation SWR are in.
Right, so the Treasury will let SWR spend public money on new rolling stock because the rolling stock still currently in build can't be introduced due to industrial relations problems specific to SWR.

Of course they won't. And who's going to pay the bill to Alstom for the 701s?
 

43096

On Moderation
Joined
23 Nov 2015
Messages
18,796
Right, so the Treasury will let SWR spend public money on new rolling stock because the rolling stock still currently in build can't be introduced due to industrial relations problems specific to SWR.

Of course they won't. And who's going to pay the bill to Alstom for the 701s?
You are assuming that the 701s are fit for service other than just the industrial relation issues. We don’t know what the contract terms are - there may be a termination clause for non-delivery. In which case no one is paying Alstom.

In any case, nowhere did I say it would happen; I pointed out that your statement about competitive tendering was incorrect. Perhaps read what was written and get off your high horse?
 

Mollman

Established Member
Joined
21 Sep 2016
Messages
1,712
Location
Preston
Yes they can if there are extenuating circumstances. During the pandemic there were plenty of contracts placed without going through the tendering process. Likewise, what is a direct award contract to a TOC?

In rolling stock, the Dutch placed a contract with Bombardier for TRAXX locos after the Fyra fiasco and I think ÖBB have ordered without tender from Siemens after they cancelled the Talent3 order with Alstom. That’s not dissimilar to the situation SWR are in.
But they would still have to post a notice in the public realm to do that, as they do when placing a direct franchise award.
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,166
But they would still have to post a notice in the public realm to do that, as they do when placing a direct franchise award.
Exactly. There are still rules to be followed.

== Doublepost prevention - post automatically merged: ==

Is there a way to go to the second place runner up without going through another tender?
Surely it makes sense to have that clause. Especially if something happens meaning the winner pulls out.
That's assuming that Siemens did come second (or even bid) and their price remains unchanged five years later. Unlikely I'd think.
 
Last edited:

C96

Member
Joined
31 Mar 2018
Messages
45
Well something has got to give. Can’t have a push to get people back to the office and use trains, whilst crippling the commuting lines.

Especially where in SWT times it used to being able to turn a profit, the money is needed for the treasury.
 

warwickshire

On Moderation
Joined
6 Feb 2020
Messages
2,304
Location
leamingtonspa
Personally myself yes I can see the 458 programme being cancelled and 458530 to 458536 being kept rather than scrapped to keep more units, However the 701s, most likely will come into service but very very extremely slow process with the 455 staying on a lot longer most likely at least until December 2023 timetable change.
However makes you wonder at times if swr cannot admit to a error in getting rid of the 456s earlier than expected ?
Like other tocs swr has been caught out passengers are returning quicker than expected, especially the leisure and off peak commuters.
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,166
Well something has got to give. Can’t have a push to get people back to the office and use trains, whilst crippling the commuting lines.

Especially where in SWT times it used to being able to turn a profit, the money is needed for the treasury.
The thing is, of all the South East commuter networks, it is probably the SW where commuters are most likely to be able to work from home (hence the huge collapse in passenger numbers into Waterloo) and therefore least likely to have any significant bounce back of commuting. It may be that DfT/Treasury have already written off any attempt to woo commuters into Waterloo back into the office and focus on cuts instead. If the claims are true that it is industrial relations that are preventing the 701s entering service I simply cannot see the DfT/Treasury being in any way sympathetic to further investment in SWR, preferring to let the network rot instead and blaming incompetent management and intransigent unions for it all.
 

C96

Member
Joined
31 Mar 2018
Messages
45
If it is the union holding it up. Could SWR still sign off as the train works. Just not for operations
 

Bigfoot

Established Member
Joined
2 Dec 2013
Messages
1,417
The problem here is the trains don't work still. Even now after years of existence they still have endless faults.
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,166
The problem here is the trains don't work still. Even now after years of existence they still have endless faults.
Has any train ever entered service completely fault-free? There surely comes a point where you just have to bite the bullet. Think of the 458s for example.
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,166
Which were at one point 'returned' to the builder
And hastily brought back when SWT decided they were brilliant trains after all (nothing to do with the ultra-cheap lease offered to take them back of course...).
 

Energy

Established Member
Joined
29 Dec 2018
Messages
5,135
And hastily brought back when SWT decided they were brilliant trains after all (nothing to do with the ultra-cheap lease offered to take them back of course...).
I think a lot of work had been done to them to improve the reliability, a cheap lease is probably what incentivised SWT over just ordering more 450s (not difficult or too expensive, the 350/2s were ordered at a similar time).
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,166
I think a lot of work had been done to them to improve the reliability, a cheap lease is probably what incentivised SWT over just ordering more 450s (not difficult or too expensive, the 350/2s were ordered at a similar time).
It was because Porterbrook made it worth SWT's while in its franchise bid to dump the 442s and bring the 458s back on an ultra-cheap lease because the units had nowhere else to go. I can assure you that were initially very poor when they returned - we had over six months of hellish service on the Reading line with failed trains, cancellations and short formations. It was only subsequently that the very successful efforts were made to get the the units up to scratch - because something had to be done.
 

AlexNL

Established Member
Joined
19 Dec 2014
Messages
1,715
If it is the union holding it up. Could SWR still sign off as the train works. Just not for operations
I suppose they can, but if SWR formally accept the trains they will have to start paying for them.

Of course Alstom and Rock Rail will want just that, but that's not in SWRs interest. A train which can't be used to carry bums on seats is a useless train.
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
13,166
It all seems a far cry from the upbeat articles in Modern Railways and Today's Railways a couple of months ago. Taking those articles at face value the first batch of units would have been accepted by SWR by now and training in would be in full progress. These were to be a mix of units built from new with SWR-spec cab layouts and earlier units built with Aventra standard cab layouts, subsequently rebuilt to SWR specification.
 