If that's the case, that's a real shame.Info I had was "Barrhead only": EK and Larkfield were no longer planned for electrification at this time based on the document I saw.
If that's the case, that's a real shame.Info I had was "Barrhead only": EK and Larkfield were no longer planned for electrification at this time based on the document I saw.
It’s a pretty stiff, continuous climb (six miles or so?) from Thornliebank to Hairmyres. Note that the trial a few months ago went to Barrhead rather than EK. Could a battery unit handle it?
In which case operating BEMUs to EK would be the only realistic alternative.Info I had was "Barrhead only": EK and Larkfield were no longer planned for electrification at this time based on the document I saw.
Are you basing that on anything concrete?EK is being wired.
I've been diverted that way many years ago coming from EK - Central. I think it was originally included on the basis of "useful diversion and easy infill". I can't think of any "regular" traffic offhand.What traffic(if any) uses the Larkfield curve? I’m assuming not even any passenger ECS workings go that way?
Occasionally petroleum trains to/from Grangemouth use the Larkfield curve. The next one is booked for 23 April.I've been diverted that way many years ago coming from EK - Central. I think it was originally included on the basis of "useful diversion and easy infill". I can't think of any "regular" traffic offhand.
This bridge GBK/013 Nithsdale Road is adjacent to another bridge, CTC/035 Nithsdale Road which is over the Cathcart Circle line between Muirhead Central Junction and Pollokshields West station. The latter bridge was rebuilt in 1959-60 when the Cathcart Circle was electrified. Perhaps this makes it more difficult to replace GBK/013.7 months of closure seems a long time
It’ll need to be or the catenary won’t stay up.Are you basing that on anything concrete?
It’ll need to be or the catenary won’t stay up.
I almost wrote something to that effect, but thought better of it…..
This reference to the East Kilbride scheme would suggest that whilst electrification to Barrhead is going ahead, the wording "preferred option to be progressed to final business case stage" means that as yet there is no firm commitment to wire to East Kilbride.
Further down, it says: "It is important to note that the East Kilbride Final Business Case is anticipated to be published this year and will contain detailed information on the works proposed to progress to construction."
The announcement that it's going to be electrified. Lots of hot air over the last few posts...Are you basing that on anything concrete?
Nope, literally just adding a second platform albeit in a way that wouldn't preclude future doubling.I haven't read it all yet but according to page 12 the (then-?) preferred option includes double tracking EK station. Presumably this would extend as far west as the existing loop near Hairmyres.
It’s been 6 months since it was announced. After the u-turn on double tracking I wouldn’t rule out another change of plan, especially when there’s great pressure to cut costs.The announcement that it's going to be electrified. Lots of hot air over the last few posts...
Empty coaching stock to and from Corkerhill and East Kilbride use it Monday to Friday, reversing at Polmadie. Essential for Glasgow Central guards' and Corkerhill drivers' route retention.What traffic(if any) uses the Larkfield curve? I’m assuming not even any passenger ECS workings go that way?
Good shout. Wiring the steep 4-mile section up to Busby would remove any BEMU performance concerns.One possibility might be to electrify the already-double-tracked western half of the EK branch, where any decisions about positioning the OLE supports cannot get in the way of any future doubling.
Might there be some logic in deferring electrification of the East Kilbride branch until such time as the long term impact of Covid is better understood and the issue of the all important double tracking can be revisited?
Given that platforms are getting extended, trains can be longer. In the peak it can take a larger service. So probably should be fine the way it is.Personally I remain to be convinced that doubling Busby/East Kilbride, while nice to have, is essential; The current infrastructure supports a half-hourly service, is there ever likely to be the traffic to justify an increased frequency ? Not to mention how such an increase would be accommodated between Busby Junction and Glasgow Central, and at Central itself.
It depends on Covid’s long term impact on travel patterns. It’s not that long ago that an increased frequency was the publicly stated plan so the potential must be there.The current infrastructure supports a half-hourly service, is there ever likely to be the traffic to justify an increased frequency ?