• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Crossrail - Construction updates and progress towards opening (now expected 24 May 2022)

Status
Not open for further replies.

Peter Sarf

Established Member
Joined
12 Oct 2010
Messages
9,681
Location
Croydon
Ease of updatability is also a factor in the increasing acceptance of bugs at release. If your bug can be fixed by an over-the-air update that can self-install with zero downtime to the end user, they're going to be much more forgiving than if it requires a man with a white-coat to come and swap all the ROMs in your mainframe over the period of a month (or worse, get his soldering iron out and start unwirewrapping!).

The other key factor is the industrialisation of software development - it's no longer a specialised industry with a few players working for huge companies who demand quality over price. Today price is the biggest driver of development, with "fix it once it's out there making money" a key measure for the people financing the work.

As for safety critical software being somehow above all this, all I can do is point to the holes in the ground that used to be 737 MAX's.
You have a very strange view of mainframe computers. From my experience we updated at the end of the working day and tested ready for the next morning. No soldering irons or other hardware changes.

As for a specialised industry with a few players it used to be quite the opposite. Most larger companies had their own software department and looked after their own software. There was more choice of operating systems. Despite that there were standard languages like COBOL.

I might be wrong but I think the main problem with the Boeing 737max was not exactly a software bug. It was a desire to make the plane perform like the previous versions of 737s to such an extent that the pilots knew no difference. I think the pilots were not even supposed to know there was an extra piece of artificial intelligence in the control stream. The 737max had a tendency to stall and the software was designed to put the plane into a dive to avoid this. But pilots were not to know of this feature and it led to some cases of planes diving into the ground. No one really thought through how the software should be specified.
Umm it takes as long as it takes isn't a robust way of running a project and it seems to me software has now been allowed to get so complicated its almost impossible to test it.

Need to get back to the level of simple, but very effective, electromechanical electronic control that was deployed on the Victoria Line in the mid 1960's.
I agree things are over complicated and thus rather fragile. Crossrail een when working smoothly will never cope with trains presented out of order due to delays on the older lines that are dealing with other services. Trouble is that the reason for making it so complicated is to maximse the use of the infrastructure. Infrastructure is so expensive that technology start to look attractive. Wat I maen is we really need less trains in the core and more cross london tunnels.
Minor point of order - every piece of complex software that is still being changed is riddled with bugs. Most very inconsequential enough they'll never be found, some quite the opposite...

Case in point: https://nickgregory.me/linux/security/2022/03/12/cve-2022-25636/


It's not just Linux - even the Apple kernel you mentioned has severe bugs discovered from time to time, i.e: https://www.cvedetails.com/cve/CVE-2006-4392/


I'm a software developer, so this is very much in my area of expertise. Complex software engineering is very, very, very hard, which is why the mantra is always make things as simple as you can, because it's primarily the interactions between components and systems that introduce spiralling complexity.
Yes. It is easy for non-software experts to underestimate the complexity which then leads to unrealistic expectations and unrealistic deadlines.
Maybe when it got old and the technology had been abandoned, i don't like to use obsolete as there is this temptation to believe everything new has to be better than what preceded it, but that simple technology delivered 10's millions journeys safely and reliably. Im not a luddite and realise there have been huge benefits but what im contending is technolgy in the second decade of the 21st century has many examples of it just getting too complicated in part I believe due to too much inter connectivity between systems. So in future we should just question if we want or need all this functionality that computers and software can provide. Reality is hardware is relatively cheap but software engineers aren't and certainly testing it all isn't.
It is true that we have become obsessed with things looking nice. Look at windows and the processing power required to produce all those different colours and shades of colours all on the screen. Now, ignoring photographs and videos, most of the software we use would be fine to use if it were just black and white.
Ironically this post just underpins an argument that I've posted on RailUK Forums more than once that the railway (and especially the UK railway) has allowed a plethora of random technical standards with indifferent interfaces to prevail, particularly since privatisation. This is where buyers flock to the cheapest bid where manufacturers offer their pet systems ignoring integration, that not insignificant element of cost of ownership, that excalates as incompatible systems and interfaces clash. The buyers have got what they paid for. Unfortunately, 'its buy cheap, struggle through with it' , - there's usually no 'buy twice' option.
Oh yes indeed. I recall replying to one of your posts "there is nothing like standards and there are no standards". As an example - how many different signalling systems are there on Crossrail and its extremities !.
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

fgwrich

Established Member
Joined
15 Apr 2009
Messages
10,641
Location
Hampshire
Had a brief wander around Paddington this afternoon on my way up north. I hadn’t realised the Bakerloo connection will be the deepest part of the station, running under both the CrossRail and Bakerloo line tunnels.
 

Attachments

  • 8DDB42E3-C38D-43B9-8765-885CC87C715B.jpeg
    8DDB42E3-C38D-43B9-8765-885CC87C715B.jpeg
    3.6 MB · Views: 264
  • 6BB12295-6092-4E1B-91BB-50252C5DC1CD.jpeg
    6BB12295-6092-4E1B-91BB-50252C5DC1CD.jpeg
    4.5 MB · Views: 262
  • B9DA7BC5-1B89-44A0-B234-F9BCB6466F13.jpeg
    B9DA7BC5-1B89-44A0-B234-F9BCB6466F13.jpeg
    4.3 MB · Views: 262
  • BC1FE3CC-0A3A-46F4-898F-531A8CF17A58.jpeg
    BC1FE3CC-0A3A-46F4-898F-531A8CF17A58.jpeg
    3.6 MB · Views: 259
  • 43444518-E617-4FC7-9407-214366D94B99.jpeg
    43444518-E617-4FC7-9407-214366D94B99.jpeg
    3.2 MB · Views: 255
  • F89569C5-71FB-4A79-8825-299BE4E9980A.jpeg
    F89569C5-71FB-4A79-8825-299BE4E9980A.jpeg
    4 MB · Views: 268

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,290
Had a brief wander around Paddington this afternoon on my way up north. I hadn’t realised the Bakerloo connection will be the deepest part of the station, running under both the CrossRail and Bakerloo line tunnels.
It had to be redesigned late on, and hence had a separate TWA order. I think as originally proposed it would only have had marginal headroom to cross over the Bakerloo and Crossrail running tunnels, ie it would have been too close to the mainline station concourse level.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,164
Location
West Wiltshire
A more accurate explanation is that there was basically zero investment in the tube after the Victoria Line was built until the late 1990s

Might not have been new lines (just Baker Street- Charing Cross and some Heathrow extensions)

But throughout 1970s was lots of new trains (1972, 1972 mk2, 1973, C77, D78 stock)
In 1980s many Central London stations were refurbished with new tiling, many for first time since being built
In late 1980s & early 1990s many escalators were replaced and ticket halls rebuilt for UTS ticket machine lines


Not sure if this should be in crossrail construction thread, or Paddington Square (on other side of station), but tunnelling has been finished on the step free access to Bakerloo platforms.

Excavation works have finished on the Paddington Bakerloo line station upgrade, which forms part of Shard developer Sellar’s Paddington Square project.

Improvement works on Paddington underground station will create a new, larger ticket hall, as well as step-free access to the Bakerloo line platforms and doubled escalator capacity. The works are linked to the £825M Paddington Square mixed-use development.

 
Last edited:

camflyer

Member
Joined
13 Feb 2018
Messages
1,165
The Three Guineas to the Hutton, eventually! Game on :lol:

Maybe not Reading to Shenfield but the central stations, Paddington to Whitechapel, are easily do-able with an optional extension to Woolwich for the brave.
 

306024

Established Member
Joined
23 Jan 2013
Messages
3,974
Location
East Anglia
Looking forward to doing the Elizabeth Line Pub Crawl
Some of us have already started.

Seven Kings is a bit of a walk now The Cauliflower has closed, and good luck at Goodmayes ;)

With two entrances at the Central London stations you can double the pubs to do there.
 

Backroom_boy

Member
Joined
28 Dec 2019
Messages
587
Location
London
Some of us have already started.

Seven Kings is a bit of a walk now The Cauliflower has closed, and good luck at Goodmayes ;)

With two entrances at the Central London stations you can double the pubs to do there.
Howabout a mini-crawl between two entrances at the same station? Where's the best candidate for that?
 

stuu

Established Member
Joined
2 Sep 2011
Messages
3,770
Howabout a mini-crawl between two entrances at the same station? Where's the best candidate for that?
Farringdon, there's enough pubs and bars to be properly hammered between the two entrances. TCR has plenty nearby but not many actually on the route
 

WelshBluebird

Established Member
Joined
14 Jan 2010
Messages
5,605
For those who are more familiar with Paddington, how long is the walk from the mainline station down to the Crossrail platforms? It looks pretty short based on where the entrance is at ground level but hard to tell past that really. Shorter or longer than say the walk to the Circle line etc platforms?
 

pacenotes

Member
Joined
4 Mar 2017
Messages
106
Depends on which Platform you get on the high line.
Platforms 12 & 14 have about a 10-minute walk where as platform 1 is right by the entrance to the Elizy line. At the top, you can see the train doors so its only one escalator down to the trains.
 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
11,006
Location
London
Depends on which Platform you get on the high line.
Platforms 12 & 14 have about a 10-minute walk where as platform 1 is right by the entrance to the Elizy line. At the top, you can see the train doors so its only one escalator down to the trains.

If you get off at the rear of your train on Platform 12/14 and head along the overbridge, I think it should be less than 10 minutes for a relatively fit person. It will be interesting to see what journey planners suggest for interchange time.

If the number of people currently getting off at Ealing Broadway is anything to go by, quite a lot of people will be doing this at Paddington.
 

Wolfie

Established Member
Joined
17 Aug 2010
Messages
7,430
Farringdon, there's enough pubs and bars to be properly hammered between the two entrances. TCR has plenty nearby but not many actually on the route
Liverpool Street/Moorgate could be interesting....
 

WelshBluebird

Established Member
Joined
14 Jan 2010
Messages
5,605
At the top, you can see the train doors so its only one escalator down to the trains.
That's good to hear! Will be interesting to see what the real world makes of journeys like Paddington to places on the Northern Line in comparison to using the Circle / H&C / Bakeroo (or even Central line from Lancaster gate) as today! The longer journeys across London will obviously have an advantage due to Crossrail being physically faster, but its the shorter distance / connecting journeys that seem to be to be more uncertain!
If you get off at the rear of your train on Platform 12/14 and head along the overbridge, I think it should be less than 10 minutes for a relatively fit person. It will be interesting to see what journey planners suggest for interchange time.
Does make me think if the overbridge is large enough for the additional traffic it may get, especially as there have been times (granted before COVID) where it was already pretty busy!
 

matt_world2004

Established Member
Joined
5 Nov 2014
Messages
4,581
That's good to hear! Will be interesting to see what the real world makes of journeys like Paddington to places on the Northern Line in comparison to using the Circle / H&C / Bakeroo (or even Central line from Lancaster gate) as today! The longer journeys across London will obviously have an advantage due to Crossrail being physically faster, but its the shorter distance / connecting journeys that seem to be to be more uncertain!

Does make me think if the overbridge is large enough for the additional traffic it may get, especially as there have been times (granted before COVID) where it was already pretty busy!
The overbridge is the slower route it will still be quicker to walk to the front of the train and access from platform 1
 

Non Multi

Member
Joined
11 Dec 2017
Messages
1,191
It shouldn't matter which way as there's escalators down into Paddington low level at both entrances. The overbridge will be the fastest way if you are on a coach at the country end or P14.
 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
11,006
Location
London
The overbridge is the slower route it will still be quicker to walk to the front of the train and access from platform 1

Maybe from P12 (its probably even), but unlikely from P14. Think it will probably be personal preference and the savings will be seconds.
 

camflyer

Member
Joined
13 Feb 2018
Messages
1,165
Farringdon, there's enough pubs and bars to be properly hammered between the two entrances. TCR has plenty nearby but not many actually on the route

Good shout. I had forgotten that there will be another entrance on the other side of Smithfield. Some excellent drinking options in the area. What with the arrival of Crossrail and the redevelopment of Smithfield, Farringdon looks to be on the up over the next few years.
 

Tim M

Member
Joined
9 Jul 2016
Messages
205
You have a very strange view of mainframe computers. From my experience we updated at the end of the working day and tested ready for the next morning. No soldering irons or other hardware changes.

As for a specialised industry with a few players it used to be quite the opposite. Most larger companies had their own software department and looked after their own software. There was more choice of operating systems. Despite that there were standard languages like COBOL.

I might be wrong but I think the main problem with the Boeing 737max was not exactly a software bug. It was a desire to make the plane perform like the previous versions of 737s to such an extent that the pilots knew no difference. I think the pilots were not even supposed to know there was an extra piece of artificial intelligence in the control stream. The 737max had a tendency to stall and the software was designed to put the plane into a dive to avoid this. But pilots were not to know of this feature and it led to some cases of planes diving into the ground. No one really thought through how the software should be specified.

I agree things are over complicated and thus rather fragile. Crossrail een when working smoothly will never cope with trains presented out of order due to delays on the older lines that are dealing with other services. Trouble is that the reason for making it so complicated is to maximse the use of the infrastructure. Infrastructure is so expensive that technology start to look attractive. Wat I maen is we really need less trains in the core and more cross london tunnels.

Yes. It is easy for non-software experts to underestimate the complexity which then leads to unrealistic expectations and unrealistic deadlines.

It is true that we have become obsessed with things looking nice. Look at windows and the processing power required to produce all those different colours and shades of colours all on the screen. Now, ignoring photographs and videos, most of the software we use would be fine to use if it were just black and white.

Oh yes indeed. I recall replying to one of your posts "there is nothing like standards and there are no standards". As an example - how many different signalling systems are there on Crossrail and its extremities !.
I’m not sure the Boeing 747Max or for that matter any aircraft or nuclear power station control systems can be compared to signalling. System safety is of course paramount, however it’s normal to keep aircraft in the air following a failure whereas stopping a train is possibly a bit easier.

Safety software has been in use in the U.K. for nearly 40 with the first Solid State Interlocking being commissioned at Leamington Spa. It should be noted that in those far off days development was coordinated by British Rail Research, Westinghouse and GEC-General Signal with compatible and interchangeable products. Privatisation has muddied the waters somewhat. What is important however is the use of common European standards in the design of safety software in railway applications. Reference CENELEC 50126, 50128 and 50129 plus other international standards, it’s worth noting these were originally based on U.K. Railway Industry Association standards.

Control Centre systems have benefited from Windows style applications. The original Singapore MRT system of the mid 1980’s used pre-Windows operating systems with very restricted memory capacities and lasted just over 15 years before being upgraded with a Windows based system. WestCAD as used extensively on NR is Windows based and is about 30 years old and has been a stable platform for most if not all of that period. The comment about perturbations on older lines delivering trains out of order into Crossrail is no different to any other network, and probably less of an issue say than around London Bridge/Blackfriers and Thameslink.

Crossrail integration at the interfaces with Network Rail is an interesting example of a less than ideal system. I can’t comment on the Control Centre Level, however the decision to use CBTC on the central section rather than ETCS was considered odd when the signalling system was out for Tender (I was involved in the winning bid, but only for the interlocking and trackside elements).
 
Last edited:

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,350
Does make me think if the overbridge is large enough for the additional traffic it may get, especially as there have been times (granted before COVID) where it was already pretty busy!

The overbridge is the slower route it will still be quicker to walk to the front of the train and access from platform 1
Potentially busier once the ticket gate installation is made on platforms 8/9, though the effect of that may be for more passengers to default to the escalators on the side of platform 12, not that these are that apparent from the H&C station.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,164
Location
West Wiltshire
Apologies for slightly indirect info, but appears some bus changes in Greenwich area, which were in the consultation (linked below) related to changes in SE London related to Elizabeth line opening are reported locally by bus staff, to be happening on Saturday 14th May.

Bus changes in London usually start on a Saturday morning (or commencement of night service few hours earlier), so wouldn’t read too much into the choice of day of the week.

Sorry can’t find any formally published info to link the bus changes, but suggests the line opening date would be within few days of 14th May if the bus changes can be verified.

 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
11,006
Location
London
Would fit in with a mid-May opening as predicted. That consultation is dated 2017 though.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,164
Location
West Wiltshire
Would fit in with a mid-May opening as predicted. That consultation is dated 2017 though.

The changes were in a consultation 4 years ago (when the line was going to open late 2018). There were 3 formal consultations (West London, East London, SE London) based on the 2017 proposals.

But found a link confirming changes going ahead 14th May, and as an example route 180 was one of those proposed to be changed when line opens, so looking like a Mid May opening

 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
11,006
Location
London
I would also think that some of the "new routes" might not happen given TfL's general funding situation.
 

AM9

Veteran Member
Joined
13 May 2014
Messages
16,046
Location
St Albans
I would also think that some of the "new routes" might not happen given TfL's general funding situation.
Might the view be that a relatively small cost of some feeder bus routes to Crossrail stations would bring far more in via the rail farebox given that the major investment in the line is complete.
 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
11,006
Location
London
Might the view be that a relatively small cost of some feeder bus routes to Crossrail stations would bring far more in via the rail farebox given that the major investment in the line is complete.

Well there's a lot of "might" and "possibly"! I'd certainly say it was ideal, but just taking stock of TfL's funding realities.
 

rd749249

Member
Joined
15 Sep 2015
Messages
187
14/5 is recognised as a possible start date by MTR according to the latest plan that I’ve seen.
 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
11,006
Location
London
14/5 is recognised as a possible start date by MTR according to the latest plan that I’ve seen.

Indeed and would fit it neatly with the May timetable change (even if it is completely self-isolated it makes sense).
 
Status
Not open for further replies.

Top