Porterbrook Cl.769 'Flex' trains from 319s, initially for Northern

Greybeard33

Established Member
Joined
18 Feb 2012
Messages
4,335
Location
Greater Manchester
I think I’m going to disagree. There are certain fleets, with life left in them, where diesel battery hybridisation can be done relatively easily and will have good benefit. Chiltern springs to mind, some of Northern, and arguably Cross Country.
And it should be remembered that the 769 is not particularly "green". It does not have regenerative braking, even in AC mode, and the 1980s DC traction motors and traction package are not very efficient by modern standards. The diesel engines run continuously in diesel mode, causing pollution in stations, unlike a diesel battery hybrid.

On a route that is only 20% under the wires, a 769 might well burn more fuel and emit more CO2 than a hybrid 195, despite the latter not taking advantage of the OLE.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

AM9

Veteran Member
Joined
13 May 2014
Messages
16,035
Location
St Albans
And it should be remembered that the 769 is not particularly "green". It does not have regenerative braking, even in AC mode, and the 1980s DC traction motors and traction package are not very efficient by modern standards. The diesel engines run continuously in diesel mode, causing pollution in stations, unlike a diesel battery hybrid.

On a route that is only 20% under the wires, a 769 might well burn more fuel and emit more CO2 than a hybrid 195, despite the latter not taking advantage of the OLE.
Nevertheless there aren't any battery hybrid 195 anywhere at all, let alone for a secondary service like that to Southport. The 769s are still far more green than a pair of 150s deployed in the place of the &^(s.
 

Greybeard33

Established Member
Joined
18 Feb 2012
Messages
4,335
Location
Greater Manchester
Nevertheless there aren't any battery hybrid 195 anywhere at all, let alone for a secondary service like that to Southport. The 769s are still far more green than a pair of 150s deployed in the place of the &^(s.
Not yet. But see
 

The Ham

Veteran Member
Joined
6 Jul 2012
Messages
12,036
But even with electrification progressing at it's current snail's pace, there will be fewer and fewer trains running services that don't spend a considerable amount of their journeys under wires. So a battery-diesel hybrid (probably battery-diesel-electric), multiple unit fleet would be quite a niche requirement. The additional weight, complexity and (ultimately through-life cost) of providing for full electric running under wires or over 3rd rail would make the proposed micro-fleet(s) look not particularly cost effective and more of a green gesture designed to stave off demands for electrification extensions.

Whilst such trains (i.e. DMU with batteries added) will become more and more niche, assuming that the batteries last for (say) up to 10 years that's probably about the story of timeframe before things will happen to allow them to be removed from service.

Even then it could be that the battery rafts could be used for other purposes.
 

Wyrleybart

Established Member
Joined
29 Mar 2020
Messages
2,633
Location
South Staffordshire
I didn't realise the 769s were proper bi-modes like the 755s.
They are actually dual voltage EMUs where Porterbrook have contracted Wabtec to fit a MAN engine raft under the driving trailer cars. The diesel alternator sets were designed to supply the equivalent of 750V DC to the bus. It is not quite as simple as that though.
 

childwallblues

Established Member
Joined
3 Jul 2014
Messages
3,857
Location
Liverpool, UK
I needed to ride five 769s so yesterday I was out and managed io get three of them 424 450 and 456. Also rode 434 and hoped to ride 448. I was waiting for it at Parbold but it got cancelled.
 

brad465

Veteran Member
Joined
11 Aug 2010
Messages
11,495
Location
Taunton or Kent
Apologies if this has been shared before, but this picture has been doing the rounds on Facebook and as I believe it's of a 769 car, thought I'd share it here:


1642715525239.png
 

Wyrleybart

Established Member
Joined
29 Mar 2020
Messages
2,633
Location
South Staffordshire
Picture is of 769426 which I believe is still at Cardiff?
Seems some doubt about where the unit actually is. AIUI the unit was deliveredto Canton with a different end car because it 's own was damaged. I then believe 769426 was taken back to Wabtec. That car looks like a 769 painted into base Northern livery, so would that have been the car used to deliver 769426 to Canton initially ?

I have no idea
 

Dspatula

Member
Joined
19 Dec 2019
Messages
182
Location
Manchester
Apparently someone managed to take a pantograph off a 769on Milies Platting bank yesterday, so that'll be one less for a while. 769434 by the looks of it. No photographic evidence so I can only go off what I've been told.
 

Geeves

Established Member
Joined
6 Jan 2009
Messages
2,638
Location
Rochdale
Oh yes it's definitely broken. Probably the first time the pantograph head went for a ride inside the train after being retrieved from the line side!

 

Attachments

  • IMG_20220203_135743.jpg
    IMG_20220203_135743.jpg
    4.9 MB · Views: 248

507020

Established Member
Joined
23 May 2021
Messages
1,983
Location
Southport
Apparently someone managed to take a pantograph off a 769on Milies Platting bank yesterday, so that'll be one less for a while. 769434 by the looks of it. No photographic evidence so I can only go off what I've been told.
Would that someone have been the driver by any chance? Surely no one else could have taken it off when it shouldn’t have been raised east of Victoria.
Oh yes it's definitely broken. Probably the first time the pantograph head went for a ride inside the train after being retrieved from the line side!
What has happened to it? Did it run off the end of the wires or has it hit something?
 

Greybeard33

Established Member
Joined
18 Feb 2012
Messages
4,335
Location
Greater Manchester
Would that someone have been the driver by any chance? Surely no one else could have taken it off when it shouldn’t have been raised east of Victoria.

What has happened to it? Did it run off the end of the wires or has it hit something?
Presumably the incident occurred on the 1131 Southport to Stalybridge:
It lost 6 minutes between Moses Gate and Farnworth, so maybe that was where the pantograph was initially damaged and 769434 reverted to diesel for the remainder of the working?

The return working from Stalybridge was terminated short at Victoria and 150133 later took over the remainder of the diagram.
 

david l

Member
Joined
27 Dec 2016
Messages
468
Location
Wigan
It would appear that 769434 arrived at Man Vic on ac (as booked), then left Man Vic towards Stalybridge in diesel mode (as booked) but the pan did not drop on the power changeover at Man Vic, ran out of wire on Miles Platting bank and hit Rochdale Road bridge. Train continued to Stalybridge (terminated) and returned to Man Vic in diesel mode, as booked. When switchover back to ac took place at Man Vic, there was no pan there to raise.
AFAIK when you change over from ac to diesel, the one button in the cab drops the pan and starts the diesels.
 

507020

Established Member
Joined
23 May 2021
Messages
1,983
Location
Southport
No, the time lost at Farnworth was due to a failure to call at Moses Gate.
How did this happen?
It would appear that 769434 arrived at Man Vic on ac (as booked), then left Man Vic towards Stalybridge in diesel mode (as booked) but the pan did not drop on the power changeover at Man Vic, ran out of wire on Miles Platting bank and hit Rochdale Road bridge. Train continued to Stalybridge (terminated) and returned to Man Vic in diesel mode, as booked. When switchover back to ac took place at Man Vic, there was no pan there to raise.
AFAIK when you change over from ac to diesel, the one button in the cab drops the pan and starts the diesels.
I had a suspicion this was more likely than a driver error. That is correct there is only a single button for “Pan down engine start” and “Pan up engine stop” but was the damage not noticed until after the train had returned to Manchester Victoria and not during the long layover at Stalybridge? Did the driver attempt to raise the pantograph at Victoria only to find that the engine stopped and there was no traction, get out to check and find that the pantograph had gone? Could the train not have continued to Southport on Diesel mode in that circumstance? Did it strike one of the gantries after the end of the wires?
 

Trackman

Established Member
Joined
28 Feb 2013
Messages
4,277
Location
Lewisham
AFAIK when you change over from ac to diesel, the one button in the cab drops the pan and starts the diesels.
That is correct there is only a single button for “Pan down engine start” and “Pan up engine stop”
I've only seen and been on one 769 many months ago.
I alighted at Bolton and watched the changeover.
The pan went up but the diesel engines were still running.
Right away- but as soon as the driver took power the diesel engines cut out- is this normal?
 

507020

Established Member
Joined
23 May 2021
Messages
1,983
Location
Southport
I've only seen and been on one 769 many months ago.
I alighted at Bolton and watched the changeover.
The pan went up but the diesel engines were still running.
Right away- but as soon as the driver took power the diesel engines cut out- is this normal?
Normally the Diesel cuts out before the train has left Bolton but sometimes when the dwell has been shorter I’ve seen the engines take longer to shut down.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,684
Location
Nottingham
How did this happen?

I had a suspicion this was more likely than a driver error. That is correct there is only a single button for “Pan down engine start” and “Pan up engine stop” but was the damage not noticed until after the train had returned to Manchester Victoria and not during the long layover at Stalybridge? Did the driver attempt to raise the pantograph at Victoria only to find that the engine stopped and there was no traction, get out to check and find that the pantograph had gone? Could the train not have continued to Southport on Diesel mode in that circumstance? Did it strike one of the gantries after the end of the wires?
Would the line light remain lit if the train was in diesel mode?. If not, the driver would have no way of knowing the pan was still up, and if so they may not have been trained to check it, as the usual failure mode of a pan is to drop unexpectedly not to stay up. Either way, the driver would have no reason to suspect that the pan had been damaged until they tried to raise it again at Victoria. When lowered it probably wouldn't be visible from platform level so a check at Stalybridge wouldn't show anything out of the ordinary. Once it was discovered to be missing, it would be the right course of action to fail the train because the damage might have made it unsafe to continue.
 

Trackman

Established Member
Joined
28 Feb 2013
Messages
4,277
Location
Lewisham
Normally the Diesel cuts out before the train has left Bolton but sometimes when the dwell has been shorter I’ve seen the engines take longer to shut down.
Could have been a coincidence, as I say I've only seen it once.
 

sportzbar

Member
Joined
11 May 2014
Messages
208
I've only seen and been on one 769 many months ago.
I alighted at Bolton and watched the changeover.
The pan went up but the diesel engines were still running.
Right away- but as soon as the driver took power the diesel engines cut out- is this normal?
When switching between modes the diesel generators disengage with the power now being provided by the over heads. What then happens is the generators slowly wind down and can take several minutes depending on the temperature. It's more efficient from a maintenance point of view rather than just shutting off straight away.
 

Roast Veg

Established Member
Joined
28 Oct 2016
Messages
2,320
There are certain fleets, with life left in them, where diesel battery hybridisation can be done relatively easily and will have good benefit. Chiltern springs to mind, some of Northern, and arguably Cross Country.
I hope the XC argument is poor, because any life extension of the Voyagers would be most unwelcome.
 

Greybeard33

Established Member
Joined
18 Feb 2012
Messages
4,335
Location
Greater Manchester
It would appear that 769434 arrived at Man Vic on ac (as booked), then left Man Vic towards Stalybridge in diesel mode (as booked) but the pan did not drop on the power changeover at Man Vic, ran out of wire on Miles Platting bank and hit Rochdale Road bridge. Train continued to Stalybridge (terminated) and returned to Man Vic in diesel mode, as booked. When switchover back to ac took place at Man Vic, there was no pan there to raise.
AFAIK when you change over from ac to diesel, the one button in the cab drops the pan and starts the diesels.
I believe the pan should have dropped automatically once it reached full extension, after running off the end of the wire. But perhaps there was insufficient time for this to occur before it hit the Rochdale Road bridge? The bridge is only about 150m beyond the end of the wiring at Bromley Street. About 8s at 40mph.
 

AM9

Veteran Member
Joined
13 May 2014
Messages
16,035
Location
St Albans
I believe the pan should have dropped automatically once it reached full extension, after running off the end of the wire. But perhaps there was insufficient time for this to occur before it hit the Rochdale Road bridge? The bridge is only about 150m beyond the end of the wiring at Bromley Street. About 8s at 40mph.
It's also a fundamental part of the original 319 design so hardly a failing of the 769'ness of the train. On a few occasions that I remember, the 319s* would come a cropper when transitioning from ac to DC where the driver hadn't dropped the pantograph before the wiring overrun ran out.
* there was a recent case of a 700 clouting the structure over the ramp up to Blackfriars a few month ago.
 

Llama

Established Member
Joined
29 Apr 2014
Messages
1,959
It would appear that 769434 arrived at Man Vic on ac (as booked), then left Man Vic towards Stalybridge in diesel mode (as booked) but the pan did not drop on the power changeover at Man Vic, ran out of wire on Miles Platting bank and hit Rochdale Road bridge. Train continued to Stalybridge (terminated) and returned to Man Vic in diesel mode, as booked. When switchover back to ac took place at Man Vic, there was no pan there to raise.
AFAIK when you change over from ac to diesel, the one button in the cab drops the pan and starts the diesels.
Not saying 100% that you are wrong there but that doesn't appear to be what happened from the info we have so far.

Yes it's one button to press (after putting the master switch to neutral) on 769s to drop the pan and start the diesel engines. There is indeed a line light on the desk which should also be lit when the unit is in diesel mode with at least one engine running properly (just as 319s do when on DC mode).

When changing from diesel to AC mode the engines can take a while to run down, it's normal to have set off from Bolton in the up direction before they've stopped.
When changing to diesel mode it's apparent that from the engines actually starting to traction power being demanded to can be as little as 10 seconds, I'm no mechanical engineer but I wouldn't expect that is good for reliability.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,684
Location
Nottingham
Not saying 100% that you are wrong there but that doesn't appear to be what happened from the info we have so far.

Yes it's one button to press (after putting the master switch to neutral) on 769s to drop the pan and start the diesel engines. There is indeed a line light on the desk which should also be lit when the unit is in diesel mode with at least one engine running properly (just as 319s do when on DC mode).

When changing from diesel to AC mode the engines can take a while to run down, it's normal to have set off from Bolton in the up direction before they've stopped.
When changing to diesel mode it's apparent that from the engines actually starting to traction power being demanded to can be as little as 10 seconds, I'm no mechanical engineer but I wouldn't expect that is good for reliability.
So if the same light signifies the diesel is running and that AC power is present, the driver has no indication that the pan has dropped when switching to diesel, other than to get out and have a look. Maybe it would go out for a few seconds in between dropping the pan and the diesel starting up, but that would be easy to miss.
 