Construction has started on the hotel next to Cambridge North station. This was sent in a
Travel Plan Plus newsletter.
https://www.cambridge.gov.uk/media/7029/print-a5-nec-southcambs-booklet.pdf
Travel Plan Plus newsletter.
There is a consultation on developments in the area with details here:McAleer & Rushe Contracts UK have been appointed by Brookgate for the construction of a new 217 bed Novotel Hotel at Cambridge North Station (CNS). Main contract works will commence on Monday 25 February 2019 with Practical Completion scheduled for September 2020.
The Multi-Utility Trench (MUT) works will be carried out end of March and substantially completed by end of March 2020. The new utilities are being placed for this phase of works but also for future phases. This will have significant impact on pedestrians and cyclists (both to and from the station). When these services extend into this strip adjacent to Cowley Road it will require the full closure of this cycle and footpath until the end of October 2019. This closure will require the diversion of cyclists and pedestrians down the pathway of the guided bus route.
When this area is reopened, the cycle way on the west side of Milton Ave will continue to remain closed as the utility works continue towards the station. Pedestrians will therefore be directed to the east side of Milton Ave as will cyclists who will be requested to dismount and join the pedestrians on the same pathway. Safety consultants wish to separate cyclists from construction activities which is one of the factor for redirecting cyclists to the station via the guided bus route in order to maintain that separation. All cyclists will be encouraged to use this route.
End of March 2019, following activities will take place:
Please note these dates may change depending on the progress of works onsite.
- Closure of the pedestrian and cycle path parallel to Cowley Road
- Closure of access gate (“short cut” from Cambridge Business Park onto the pedestrian/cycle route)
- Diversion of pedestrians and cyclists to guided bus route
- Routing of buses and coaches to temporary turn-around on the car park approach road and closure of bus route down to station
- Closure of Milton Ave Link Road
- Guided bus route - Localised restrictions to roadway around site
![]()
https://www.cambridge.gov.uk/media/7029/print-a5-nec-southcambs-booklet.pdf
The consultation is running for 6 weeks from Monday 11 February until 5pm on Monday 25 March 2019.
Seven drop in events are proposed in the area. This is your chance to come and talk with one of the planning officers about the plan and how plans can be submitted to the Councils. Below are key dates which would be relevant for employees. For other locations, please see here.
- 27 February 2019 from 6:30am – 8:30am and 4:00pm – 7:30pm, Cambridge North Station, Cowley Rd, Cambridge, CB4 0WZ
- 01 March 2019 from 10:00am – 4:00pm, St John’s Innovation Centre, Johnson Room, Cowley Road, Cambridge, CB4 0WS
- 05 March 2019 from 10:00am – 4:00pm, Trinity Centre, Suite 12, 24 Cambridge Science Park, Milton Road, Cambridge CB4 0FN