Remaining GWR HST Diagrams

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Clarence Yard

Established Member
Joined
18 Dec 2014
Messages
3,268
The latest delivery schedule from Hitachi means the “tail” of the HST rundown will now be slightly elongated past late March. Exact details are being worked out now. They will all be gone by the summer timetable with the last few sets running West of England diagrams.

Less than 100 SX GWR trains are now being operated (LTP) by HST sets and this will be down to around 50 SX by Xmas. Initial thoughts are that this will be with only 13 diagrams but this has to be confirmed.
 

SwindonBert

Member
Joined
19 Feb 2017
Messages
187
Location
Swindon
Is it not that if the train terminates at Swindon it will be a DMU, and if it goes to London at will be a 125/800? Can't imagine any intercity services would terminate at Swindon.

If there's problems / engineering works on the line between Swindon & Paddington there often is
 

Rhydgaled

Established Member
Joined
25 Nov 2010
Messages
4,859
You will be able to tell from RTT if it is a unit or an HST/IET. The timing loads of a DMU wil show 15x etc and the HST/IET are timed as HST. Note, of course, that you not get the actual class diagrammed but will give you an indication whether DMU or otherwise.
I thought the 'received wisdom' on here was that RealTime Trains timing loads are not particularly useful for identification of what is actually diagrammed to work a service. Anyway, thanks for the information; with a DMU working vice HST I imagine these would be rather 'cosy'?

Is it not that if the train terminates at Swindon it will be a DMU, and if it goes to London at will be a 125/800? Can't imagine any intercity services would terminate at Swindon.
In normal practice that indeed would be the case. However if a service that normally runs through to London is cut back in the event of engineering work you may get a HST terminating at an odd location (for example, on the date in question the Swansea-London services are cut back to Swansea-Newport and I presume will still be 125/800s despite the fact they won't be going through to London).

In the case of my trip, one working that caught my attention was 2Z63 1346 Cheltenham Spa to Swindon. On a normal Sunday (according to GWR's PDF timetable B7) this is a through service to Paddington and RTT has it down as booked into platform 1 at Swindon on the 14th (although the following 15:46 off Cheltenham is booked into platform 2 at Swindon on the 14th so will definately be a short DMU despite this train also normally being a through one to PAD). RTT also states that both workings offer first class accomodation, which seems to counteract the fact they are timed for 75mph DMUs. Have any of the 166/165 units that have moved west retained first class accomodation?

The latest delivery schedule from Hitachi means the “tail” of the HST rundown will now be slightly elongated past late March. Exact details are being worked out now. They will all be gone by the summer timetable with the last few sets running West of England diagrams.
I wonder if we'll see a farewell tour jsut before the last sets leave.
 

PHILIPE

Veteran Member
Joined
14 Nov 2011
Messages
13,472
Location
Caerphilly
I thought the 'received wisdom' on here was that RealTime Trains timing loads are not particularly useful for identification of what is actually diagrammed to work a service. Anyway, thanks for the information; with a DMU working vice HST I imagine these would be rather 'cosy'?

In normal practice that indeed would be the case. However if a service that normally runs through to London is cut back in the event of engineering work you may get a HST terminating at an odd location (for example, on the date in question the Swansea-London services are cut back to Swansea-Newport and I presume will still be 125/800s despite the fact they won't be going through to London).

In the case of my trip, one working that caught my attention was 2Z63 1346 Cheltenham Spa to Swindon. On a normal Sunday (according to GWR's PDF timetable B7) this is a through service to Paddington and RTT has it down as booked into platform 1 at Swindon on the 14th (although the following 15:46 off Cheltenham is booked into platform 2 at Swindon on the 14th so will definately be a short DMU despite this train also normally being a through one to PAD). RTT also states that both workings offer first class accomodation, which seems to counteract the fact they are timed for 75mph DMUs. Have any of the 166/165 units that have moved west retained first class accomodation?

I wonder if we'll see a farewell tour jsut before the last sets leave.


I know that people often confuse Timing Loads and diagrams on RTT but something with as big difference as a unit and IET/HST would certainly show as these would have to be entered specially in this case as STP services. Still doesn't say what actual class though. Almost everything on this route (DMU) now is Turbo worked but 15x timings still used.

In the case of 2Z63, Platform 2 is being used at the same time by a Westbury to Swindon service turning back.
 

Rhydgaled

Established Member
Joined
25 Nov 2010
Messages
4,859
I know that people often confuse Timing Loads and diagrams on RTT but something with as big difference as a unit and IET/HST would certainly show as these would have to be entered specially in this case as STP services. Still doesn't say what actual class though. Almost everything on this route (DMU) now is Turbo worked but 15x timings still used.

In the case of 2Z63, Platform 2 is being used at the same time by a Westbury to Swindon service turning back.
Ok, thanks for the information. Looks like its all probably going to be Turbos then so no point me aiming for 2Z63 in particular.
 

kernowbususer

Member
Joined
14 Jan 2015
Messages
50
Location
Cornwall
The latest delivery schedule from Hitachi means the “tail” of the HST rundown will now be slightly elongated past late March. Exact details are being worked out now. They will all be gone by the summer timetable with the last few sets running West of England diagrams.

Less than 100 SX GWR trains are now being operated (LTP) by HST sets and this will be down to around 50 SX by Xmas. Initial thoughts are that this will be with only 13 diagrams but this has to be confirmed.

Are any more Cornwall/Devon diagrams due to change to IEP soon?
 

Wilts Wanderer

Established Member
Joined
21 Nov 2016
Messages
3,199
Am I correct in thinking there is a sole 9-car 802 in traffic? I thought these sets weren’t due into service until after all the 802/5 units were delivered.
 

Clarence Yard

Established Member
Joined
18 Dec 2014
Messages
3,268
Yes, 802101 has been delivered earlier than the rest so that the necessary type approvals could take place. It’s was always envisaged to use it as a spare set until the rest arrived.
 

FGW_DID

Established Member
Joined
23 Jun 2011
Messages
3,035
Location
81D & 81E
I have a question, and this topic seems as good a place to ask as any...

Are any of the services between Swindon and Cheltenham/Gloucester on Sunday 14th of October booked for a HST? I will be heading to London from Gloucester and need to be in Paddington by about 6pm. Unfortunately the normal Sunday service of five through trains from Cheltenham to Paddington appears to be cut to zero on that date, with a change of train at Swindon required. I would be happy to sample a 9-car 80x if no IC125s are diagrammed, but if possible I would like to get a long train rather than a 2-car DMU (if it is only 2-car DMUs, maybe I should board at Cheltenham instead of Gloucester to be confident of getting seats). Maybe I should also check on the 80x diagrams topic to ensure none of the Bristol-PAD services are booked for a lone 5-car 80x on that day...

@Rhydgaled

Have looked at the STP diagrams for that Sunday, there are no HSTs diagrammed at all to Glos/Cheltenham.
There is one service I can see that is booked for an 800(9) - 1G72 18.30 London Paddington - Cheltenham.

No need to check the 80x topics, despite what information some folk like to pedal on this forum there are no Paddington - Bristol TM - Paddington IET services booked for a lone 5 car! Pad - Bristol IET services are all booked for either 800(9) or 2x 800(5)*

*Dependant as ever on unit availability! :E
 
Last edited:

Adsy125

Member
Joined
22 Dec 2016
Messages
462
@Rhydgaled

Have looked at the STP diagrams for that Sunday, there are no HSTs diagrammed at all.
There is one service I can see that is booked for an 800(9) - 1G72 18.30 London Paddington - Cheltenham.

No need to check the 80x topics, despite what information some folk like to pedal on this forum there are no Paddington - Bristol TM - Paddington services booked for a lone 5 car! Pad - Bristol services are all booked for either 800(9) or 2x 800(5)*

*Dependant as ever on unit availability! :E
Are there no more HST diagrams to Bristol?
 

nat67

Established Member
Joined
23 Apr 2014
Messages
1,477
Location
Warwickshire
Hi folks i'm planning to do a HST spin on Saturday 13th October I know its harder to work out whats working what with vices and cancellations but will the 0623 WSM-PAD be still HST. And should the 0903 from PAD still be hauled.
Cheers folks.
 

cactustwirly

Established Member
Joined
10 Apr 2013
Messages
8,420
Location
UK
Hi folks i'm planning to do a HST spin on Saturday 13th October I know its harder to work out whats working what with vices and cancellations but will the 0623 WSM-PAD be still HST. And should the 0903 from PAD still be hauled.
Cheers folks.

0623 is a HST, the 0903 is likely to be an 802.
 

fgwrich

Established Member
Joined
15 Apr 2009
Messages
10,639
Location
Hampshire
Can anyone tell me how the Padd - Plymouth services are looking? I'm heading off to Devon next week around mid-day and would ideally like to catch a Pullman service on the HST set while I can.
 
Last edited:

Mark Webster

Member
Joined
29 Aug 2018
Messages
124
The first two Plymouth-padd trains were units this morning.
0451&0553
0451 did 0927 x padd-pz.
0553 did c12
 

Rhydgaled

Established Member
Joined
25 Nov 2010
Messages
4,859
@Rhydgaled

Have looked at the STP diagrams for that Sunday, there are no HSTs diagrammed at all to Glos/Cheltenham.
There is one service I can see that is booked for an 800(9) - 1G72 18.30 London Paddington - Cheltenham.
Thank you for looking. Since there are no long trains (and the earlier comment from somebody about GWR being short of crews on Sundays) I'm now leaning heavily towards going into Euston on Virgin instead of into Paddington on GWR.
 

PHILIPE

Veteran Member
Joined
14 Nov 2011
Messages
13,472
Location
Caerphilly
Thank you for looking. Since there are no long trains (and the earlier comment from somebody about GWR being short of crews on Sundays) I'm now leaning heavily towards going into Euston on Virgin instead of into Paddington on GWR.

By the way, and earlier discussion with you, ALL the Paddington to Cheltenhams ran last Sunday which may have been the first time for about a year.
 
Last edited:

CMRail

Member
Joined
3 Sep 2018
Messages
163
Location
Gloucester
Monday some more Cheltenhams go over. Should leave just very few left on the Cheltenham’s. All will go over by end of November meaning it’s the first route to be fully IET operated.
 