There is no culture of secrecy, it is simply the fact that until Wabtec provide a set of coaches there is nothing else to reoprt. That is the delay, when the coaches arrive we are good to go. If the coaches don't arrive in time (For December TT change) there is a contingency. Details of that wont be released because hopefuly it wont be needed!
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

TheMuttley

Member
Joined
4 Feb 2018
Messages
43
There is no culture of secrecy, it is simply the fact that until Wabtec provide a set of coaches there is nothing else to reoprt. That is the delay, when the coaches arrive we are good to go. If the coaches don't arrive in time (For December TT change) there is a contingency. Details of that wont be released because hopefuly it wont be needed!
Whilst I do respect your point of view, could it be that you do not perceive that there is anything to report because you are "on the inside", i.e., you do receive all the emails etc which keep staff informed of the plan and you do have the discussions with managers etc where these are elaborated and explained, if necessary. I'm just suggesting that perhaps, if you had access to the same information as people "on the outside", you might think differently?

That said, thank you for the update - I don't believe that Scotrail have explained that there is merely a fixed 3 month delay to the project, and nothing more, if that is indeed what you are suggesting. Where's my "breaking news" banner... ;)
 

scotraildriver

Established Member
Joined
15 Jun 2009
Messages
1,846
Staff don't receive any emails or regular updates either. Managers don't either unless they are directly involved in the project. The vast majority of staff are not interested or involved. They just do their job and what happens happens. I've done the HST course so I'm more aware than others on whats happening with it. I've finished the course so now I won't get any further info until I drive one in anger for the first time. People join these forums because they have an interest and like to know whats happening but most folk don't. There would be little point in producing a weekly update as it would read something like "this week we fitted the carpets" "this week we painted the coaches" etc etc. How many people really care? Better to crack on and hopefully people will appreciate these trains when they are in service as they are really very very nice. Remember too the first refurbished sets always take way longer than the rest. Now the problems are identified and solutions agreed hopefully deliveries will ramp up quite quickly. You seem to think there is a big cover up, there really isn't. There is nothing to know on the "inside" that isn't in this thread apart from maybe a few pictures! Honest!
 
Last edited:

TheMuttley

Member
Joined
4 Feb 2018
Messages
43
You seem to think there is a big cover up, there really isn't
Believe me, I'm not suggesting a cover-up, more a distinct laziness at transparent updates (for whatever reason).

I should point out that I think the project is something Scotrail should ultimately be "proud" of, in due course. That's the whole reason why I think Scotrail should be doing more to engage the public - although I think we're going to have to agree to disagree about the extent to which that is possible!
 

gingertom

Established Member
Joined
19 Jun 2017
Messages
1,335
Location
Kilsyth
FGW ? A bit behind the times. GWR are also having problems with only one set in use and that is on a trial set at the moment,
yeah, me bad for not managing to keep up with all the changes. What i was getting at is ScotRail isn't the only TOC to have their stock refurbs and door fits delayed at Wabtec, not because one operator's work has been prioritised over another.
 

greyman42

Established Member
Joined
14 Aug 2017
Messages
5,368
Would it not be possible to use unrefurbished Mark 3 stock until Wabtec can supply refurbished stock. I am aware of slam door/ retention tanks, but I am sure the public would be happy enough with them.
 

Northhighland

Member
Joined
19 Aug 2016
Messages
606
Believe me, I'm not suggesting a cover-up, more a distinct laziness at transparent updates (for whatever reason).

I should point out that I think the project is something Scotrail should ultimately be "proud" of, in due course. That's the whole reason why I think Scotrail should be doing more to engage the public - although I think we're going to have to agree to disagree about the extent to which that is possible!

Completely agree with this line, it is a project that should engender pride, this will be a completely different service when the HST's are in use. I personally think the biggest criticism from the public will be they are too short, I am fairly sure they will add signifiant passenger numbers to inter-city travel by virtue of improved trains and improved timetable.

What disappoints is the Scotrail attitude towards customers. The reasons for not communicating given by so many "insiders" on here are show the culture that exists, one where passengers are not important. If you travel from Inverness to the central belt leaving at 5:30 or 6:50am, do a full day's work in the central belt and then have to stand for an hour from Glasgow to Perth, on a rammed, hot, class 170 then get a seat at Perth for the remaining two hours in a carriage that is hot and has luggage strewn everywhere, then you are really interested in when that is going to improve. You do follow the promises made by the Scottish Government at the time of letting the franchise, you do follow the performance of Abiello, who provide much poorer customer service than what went before them.

What is needed is some truth from Wabtec. The unforeseen issues line is simply not credible. Yes corrosion could be worse than thought, so that might take a week or two to work out what to do, might take a wee while longer each coach. But that was unexpected? Really, on a 40 year old coach? None of that would explain why in 6 months they have managed to release one set to GWR. No other set complete. Why? Are there 6 ish other sets in a state of almost completion? Have all the problems been understood and fixed? Is there now a new delivery programme from Wabtec?

If as it looks, it is simply Wabtec have an imbalance between resources and workload, then it is legitimate to ask questions of Abiello and SG as to what due diligence was done on the HST option at the time of letting the franchise.

These are legitimate questions that we as taxpayers and as passengers are entitled to ask. Neither stakeholder should be treated as a nuisance, which is the attitude that seems to come across here. Rail never seems to learn who its stakeholders are or how to communicate with them, the same mistakes are repeated over and over.
 

Highlandspring

Established Member
Joined
14 Oct 2017
Messages
2,777
You realise that no one posting on this thread is doing so on behalf of ScotRail or Transport Scotland in an official capacity? Neither is compelled to visit this forum to answer questions from 'stakeholders'. No one who has commercially sensitive or privileged knowledge of the project is going to post details on here for obvious reasons. There's plenty of stuff I know about what's going on in Scotland that can't be posted without risking my job and I'm sure many other members are in the same position. If you have questions it might be better to address them directly to the bodies involved through official channels of communication rather than moaning on here about a 'culture of secrecy'.
 

John R

Established Member
Joined
1 Jul 2013
Messages
6,110
I'm amazed that you can't see the problem with this culture of secrecy that you so casually reference. Information strategies, managing expectations and a basic requirement to keep the public informed is a key part of running any business.

I'm amazed you can't see that businesses have a reasonable expectation that they can manage the release of information relating to its business without having employees taking it upon themselves to put it in the public domain, whereby by internet fora or any other means. It's not a culture of secrecy - its normal business practice. Where the information relates to what will be a significant commercial contract between the two organisations, it is very clear that both parties would have a very valid interest in ensuring that any public statement as to the progress of the contract is agreed as to content and timing.

Just because a few people on a forum have an interest in a particular subject doesn't and shouldn't obligate a business to release information at a time of those people's choosing.
 

43096

On Moderation
Joined
23 Nov 2015
Messages
18,846
I'm amazed you can't see that businesses have a reasonable expectation that they can manage the release of information relating to its business without having employees taking it upon themselves to put it in the public domain, whereby by internet fora or any other means. It's not a culture of secrecy - its normal business practice. Where the information relates to what will be a significant commercial contract between the two organisations, it is very clear that both parties would have a very valid interest in ensuring that any public statement as to the progress of the contract is agreed as to content and timing.

Just because a few people on a forum have an interest in a particular subject doesn't and shouldn't obligate a business to release information at a time of those people's choosing.
Glad to see one or two people “get it”.

Too many enthusiasts seem to think they have some sort of divine right to information.
 

TheMuttley

Member
Joined
4 Feb 2018
Messages
43
I'm amazed you can't see that businesses have a reasonable expectation that they can manage the release of information relating to its business without having employees taking it upon themselves to put it in the public domain, whereby by internet fora or any other means. It's not a culture of secrecy - its normal business practice. Where the information relates to what will be a significant commercial contract between the two organisations, it is very clear that both parties would have a very valid interest in ensuring that any public statement as to the progress of the contract is agreed as to content and timing.
I fundamentally disagree that this is a "normal" business; this is quite an unusual position of a franchise which operates on quite special terms. I can think of many examples of similar situations which are commercially sensitive (this is not!) where far more information is provided, ironically. Whilst Wabtec may not wish their delay to be public, it is, by definition - the lack of trains is a give-away. What does Scotrail have to lose?
Many on these forums have "guessed" at what has caused the delays but I am yet to hear any definitive news, from either Wabtec or Scotrail. The familiar line "what's to tell?" is utterly ridiculous, given that the July target for implementation has been and gone without any Scotrail set reaching Scotland, let alone entering service - what's to tell? How about Scotrail starts by acknowledging the delay, explaining why (whether the delay is a one-off delay or likely to disrupt the rest of the schedule) and what measures are being taken to solve it or take action to mitigate the impact. This is not rocket science - any information strategy should provide for this. Numerous contributors have stated this repeatedly. If you're trying to tell me that the Scotrail employee responsible for this contract is sitting in their office, completely baffled by the fact that their trains haven't arrived and hasn't attempted to contact or liaise with Wabtec in any way... are you serious? Of course there is information "to tell" - it's just that Scotrail is unwilling to "tell" it.
Just to clarify, I am not expecting or suggesting that forum members who may be employed by Scotrail (or are privileged to information in some other way) provide informal updates on forums like this; that would be completely destructive to a well-managed information strategy. My point is that there isn't an information strategy - just a vacuum with no explanation, no revised schedule, no reassurance, nothing! In that vacuum, don't be surprised if people turn to forums like this. Which leads me on to my next point...
Just because a few people on a forum have an interest in a particular subject doesn't and shouldn't obligate a business to release information at a time of those people's choosing.
I think you are significantly under-estimating the number of people who are actively interested in this (remembering that this is a public forum, so membership alone is not reflective of how many times comments have been indexed and viewed via search engines etc) as well as how many people have no choice. I'm disappointed that Scotrail just doesn't understand that it has a stakeholder, contractual and even ethical obligation to keep the public informed.
Too many enthusiasts seem to think they have some sort of divine right to information.
Hmm, so now I must be an "enthusiast"? I thought I was contributing to this forum as a passenger, but if contributing as an enthusiast will help get some answers about whether my journey will improve soon, then, yes, I'm an enthusiast.
 

John R

Established Member
Joined
1 Jul 2013
Messages
6,110
I fundamentally disagree that this is a "normal" business; this is quite an unusual position of a franchise which operates on quite special terms. I can think of many examples of similar situations which are commercially sensitive (this is not!) where far more information is provided, ironically. Whilst Wabtec may not wish their delay to be public, it is, by definition - the lack of trains is a give-away. What does Scotrail have to lose?
I'd disagree. By definition if one party is failing to deliver according to the terms of the contract then it almost certainly is commercially sensitive. That's for the two parties to judge, not an enthusiast or passenger. Not of course that we have a copy of said contract between Scotrail and Wabtec, which I guess you'll be asking for next, along with details of any discussions between the two, and any commercial settlement. As to what does Scotrail have to lose - it's normally better when managing commercial relationships to try and work through issues in a constructive manner, not air your dirty linen in public.
 

TheMuttley

Member
Joined
4 Feb 2018
Messages
43
it's normally better when managing commercial relationships to try and work through issues in a constructive manner, not air your dirty linen in public
I agree entirely, but ignoring the terminology, the two are not mutually exclusive. Providing an honest update regarding work progress does not preclude Scotrail from supporting and working with Wabtec to complete the contract; the "dirty linen", so to speak, has already been aired through channels which Scotrail and/or Wabtec clearly cannot control, as well as the basic fact that the trains simply have not been delivered!
 

DelW

Established Member
Joined
15 Jan 2015
Messages
6,012
What is needed is some truth from Wabtec. The unforeseen issues line is simply not credible. Yes corrosion could be worse than thought, so that might take a week or two to work out what to do, might take a wee while longer each coach. But that was unexpected? Really, on a 40 year old coach? None of that would explain why in 6 months they have managed to release one set to GWR. No other set complete. Why? Are there 6 ish other sets in a state of almost completion? Have all the problems been understood and fixed? Is there now a new delivery programme from Wabtec?
I wonder if one or more aspects of the refurb, of both GWR and Scotrail sets, are awaiting feedback from the GWR trial set? I should imagine the toughest test of new finishes and equipment would be letting Joe Public on board, with dirty shoes, sticky fingers, misbehaving children, drunks etc. If there are any frailties exposed by the GWR set, it would be better to fix them on the production line now, rather than have to bring the sets back to Wabtec for updates when passengers have become used to them. That would probably cause far more complaint than delaying their introduction does.
 

Carntyne

Member
Joined
8 Jul 2015
Messages
1,026
I agree entirely, but ignoring the terminology, the two are not mutually exclusive. Providing an honest update regarding work progress does not preclude Scotrail from supporting and working with Wabtec to complete the contract; the "dirty linen", so to speak, has already been aired through channels which Scotrail and/or Wabtec clearly cannot control, as well as the basic fact that the trains simply have not been delivered!
ScotRail provided an update in May to the Scottish Parliament and the media by the looks of things, just because you've not been spoon fed the information doesn't mean it doesn't exist. https://www.bbc.co.uk/news/uk-scotland-scotland-politics-44054334
 

TheMuttley

Member
Joined
4 Feb 2018
Messages
43
ScotRail provided an update in May to the Scottish Parliament and the media by the looks of things, just because you've not been spoon fed the information doesn't mean it doesn't exist. https://www.bbc.co.uk/news/uk-scotland-scotland-politics-44054334
These comments were made to the Rural Economy and Connectivity Committee, not the media. That specific committee's role is to scrutinise Scottish Government policy and is not a means for Scotrail/Abellio to report to the Scottish ministers nor the accepted or recognised channels for Scotrail/Abellio to engage with the public. In this context it is, quite frankly, the last resort for activities of the Scottish Ministers (of which the Scotrail franchise is one) to be held accountable to MSPs. The very fact that you are citing it as a source of updates (and scolding me in the process for not being able to find it; incidentally, I read that news article when it was published, in May) is itself testament to the fact that Scotrail themselves have failed to provide material updates to the press. For your information, here is Scotrail's media releases page, in case you were looking for it.
 

Carntyne

Member
Joined
8 Jul 2015
Messages
1,026
The very fact that you are citing it as a source of updates (and scolding me in the process for not being able to find it; incidentally, I read that news article when it was published, in May) is itself testament to the fact that Scotrail themselves have failed to provide material updates to the press.
Like this, with a comment from the Chief Operating Officer, you mean? Google is great.
https://www.scotsman.com/news/transport/age-of-the-train-delayed-by-wrong-kind-of-carpet-1-4772224
 

TheMuttley

Member
Joined
4 Feb 2018
Messages
43
Like this, with a comment from the Chief Operating Officer, you mean? Google is great.
https://www.scotsman.com/news/transport/age-of-the-train-delayed-by-wrong-kind-of-carpet-1-4772224
I presume you're referring to this (which, yes, I've read as well, as have most of the readers of this forum, I would argue):-
"We had hoped our suppliers, [trains owner] Angel Trains and Wabtec, could have delivered the first InterCity train to our deadline. Their delays prevent us from beginning to transform how we connect customers across Scotland’s seven cities. Our suppliers have faced challenges with their delivery schedule, and we are working closely with them to get these iconic trains running as soon as we can.”
This is a material update? Whilst I genuinely acknowledge what you are trying to point out, I would argue that this does not constitute a material update. Firstly, it merely points out the obvious (the trains are delayed) and states that everyone is doing their best to deliver them (we assume that). The "carpet" comment does not come from Scotrail and there is no indication of timescales, or explanation of the nature of the issues experienced. Again, I am not suggesting a blow-by-blow account of the issues but surely Scotrail could be a little more forthcoming?

I fear that I am commenting a bit too much on this issue so I'm going to stop, with an acknowledgement that it is not Scotrail's responsibility to provide a detailed commentary to the public (passengers or enthusiasts), as many have pointed out. However, I would still argue that Scotrail could be more transparent about the project, without compromising their relationships with contractors.
 
Joined
17 Jul 2017
Messages
61
All depends on whether the information is there to deliver. If there's nowt to tell, there's nowt to deliver.
No information to deliver is itself information.

Google is great.
I googled Alex Hynes. More posts from him about fancy ticket punch designs and kids going to see trains than any information on why the HSTs aren't here.
If you're going to back slap and self promote everything great, don't be surprised people aren't happy when there's zilch coming from the very man who said the first set would be here by now!
 

TheMuttley

Member
Joined
4 Feb 2018
Messages
43
More posts from him about fancy ticket punch designs and kids going to see trains than any information on why the HSTs aren't here.
@DackandBlecker Exactly! I kept trying to think what was bugging me about this - it's the complete mismatch in volume of updates; if it's something Scotrail are happy to talk about there's plenty of updates but none when it's something like the HSTs - that completely undermines the argument about what constitutes "normal" updates. Last comment, I promise... haha
 

John R

Established Member
Joined
1 Jul 2013
Messages
6,110
Exactly! I kept trying to think what was bugging me about this - it's the complete mismatch in volume of updates; if it's something Scotrail are happy to talk about there's plenty of updates but none when it's something like the HSTs - that completely undermines the argument about what constitutes "normal" updates. Last comment, I promise... haha
That's standard practice everywhere. Businesses of any kind are always much more forthright in trumpeting good news, and keeping publicity about adverse things to a minimum. It's hardly surprising really is it?
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
33,695
Location
Scotland
I'm amazed that you can't see the problem with this culture of secrecy that you so casually reference.
It's not about a 'culture of secrecy'. It's about organisations having a single official mouthpiece so that the correct info is presented. While I have no doubt that @Highlandspring is referring to the most recent and up-to-date info he's seen, unless he's on the board he has no way to know if that's actually the plan or simply a plan. Allowing employees to share info is a recipe for confusion 'I saw this posted on a forum, now you're saying that.' and so on.
 

mde

Member
Joined
17 Nov 2016
Messages
513
I googled Alex Hynes. More posts from him about fancy ticket punch designs and kids going to see trains than any information on why the HSTs aren't here.
If you're going to back slap and self promote everything great, don't be surprised people aren't happy when there's zilch coming from the very man who said the first set would be here by now!
So, if you think he has information that he's going to share, why not ask him directly? You've clearly found his social media feed going by the content described. I wouldn't be surprised if you didn't get the comprehensive reply some people are looking for though - because (a) it's commercially sensitive, (b) and it'll be a moving target based on works at Wabtec and their internal programmes (e.g. guard and driver training - do they have enough to run service?)

You could always ask Transport Scotland under the Freedom of Information (Scotland) Act for any recorded information they hold, but, do be aware that they can redact it if it is deemed to be commercially sensitive.
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
33,695
Location
Scotland
...do be aware that they can redact it if it is deemed to be commercially sensitive.
And for those who are tempted to post "It's not commercially sensitive, Scotrail is a monopoly franchise let by the Government." - keep in mind that Scotrail isn't Wabtec's only customer, so the details of any compensation/change of terms with Scotrail will be commercially sensitive with respect to their contract with other lessors.
 

kkong

Member
Joined
8 Sep 2008
Messages
1,161
I very much doubt that Abellio Scotrail are contractually obliged by a contract variation to 'introduce x amount of HSTs by x date'.

Yes they are. The franchise agreement requires them to have 27 HST sets (14 x 4-car and 13 x 5-car) in the fleet by December 2018.

Please refer to the table on page 5 of this amendment to the franchise: https://www.transport.gov.scot/media/33334/amendment-agreement.pdf

I am sure this requirement is being actively discussed at present with a view to a further contract variation, because it is clearly undeliverable.
 

43096

On Moderation
Joined
23 Nov 2015
Messages
18,846
Yes they are. The franchise agreement requires them to have 27 HST sets (14 x 4-car and 13 x 5-car) in the fleet by December 2018.

Please refer to the table on page 5 of this amendment to the franchise: https://www.transport.gov.scot/media/33334/amendment-agreement.pdf

I am sure this requirement is being actively discussed at present with a view to a further contract variation, because it is clearly undeliverable.
Getting that number of sets into service in around 8 months was always going to be undeliverable. Abellio are clowns for signing up to it.
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
33,695
Location
Scotland
Abellio are clowns for signing up to it.
They probably expected to miss the target, but not by this big a margin. If, for example, three quarters of the units were in service the conversation would be a lot easier to have than it looks like it's going to be.
 

gingertom

Established Member
Joined
19 Jun 2017
Messages
1,335
Location
Kilsyth
Getting that number of sets into service in around 8 months was always going to be undeliverable. Abellio are clowns for signing up to it.
I don't think Abellio would have signed up to it if Wabtec had said they couldn't do it.
 