I take no pleasure in being proved right, but back in December 2016 I posted in the other thread:
That prophecy really did not need a crystal ball!
Fair enough.
I wish it had worked - I instinctively don't like the stockpile of midlife EMUs that are going to be "spare" in a couple of years (even if you accept that the 314/315/317s are pretty much life expired there's about four hundred carriages of 321s without a future, potentially all of the 323s, the 350/2s etc).
But it's becoming evident that this is a lot harder in reality than it looks from the comfort of my armchair, so I've got to accept that the Renatus Project, the 769s, the accessible HSTs are becoming more trouble than they are worth.
Good idea on paper - but it looks like we can churn out brand new carriages easier than converting/ upgrading old ones - got to deal with the reality - despite the inevitable "My Idea For Future Uses For 1970/1980s Trains" threads.
Interesting someone mentioned Project Thor. They couldn't make bi-mode conversion work on a relatively new DMU with the Voyagers (from 2000). Makes you think how on earth would they made it work on EMU units from the 1980s with even more obsolete equipment.
The more days that pass the more it's not hard to think Porterbrook were just desperate to find a use for the 319s by whatever means possible - even if they knew they suspected bi-mode conversion would be unlikely. Grayling's perverse obsession with bi-mode trains simply to save money provided the perfected smokescreen.
The TOCs bought into it and I'm afraid it's the passengers who have suffered.
I mentioned Project Thor - something that seems obviously a good idea in hindsight but we never saw it tested (so can't be sure that it would have worked in practice).
Railway history seems littered with examples of things that we all agree now should and could have easily been done - the fourth carriages on the 185s is another example - but seemed too much trouble at the time. If the Forum exists in a decade there'll be some "new" members looking back at this period and asking "how hard could it have been to stick a diesel engine in a mid-life EMU, when there was a shortage of DMUs and up to a thousand EMU carriages coming off lease" but they just can't get it to work - very frustrating.
However, and I hate to be the guy defending Grayling, I think that the "obsession with bi-mode trains to save money" is a little unfair. If it hadn't been for the badly run GWML project (that cost twice as much to do have a job at double the initial price) then MML electrification wouldn't have been cancelled - I think any Transport Secretary would have had to take that Realpolitik decision (even if they were MP for an East Midlands seat).
Plenty of other electrification projects were cancelled/ deferred/ delayed - the Electric Spine, Transpennine, Chase Line, chunks of EGIP, Windermere - but for some reason bi-modes get the blame for electrification being cancelled.
I'm a rail enthusiast, I'm all in favour of electrification, but even I would be nervous pouring good money after bad (given the way that Network Rail/ DfT/ ORR handled the GWML electrification project) - I still believe that electrification is the future but I can't blame any politician for being reluctant to keep writing blank cheques until Network Rail proves that it can electrify lines to budgets/ deadlines.
I agree that Porterbrook have made a bad bet on 319 conversion - just as they have made a bad bet on the West Midlands franchise taking on all of the 323s.