Just that (in the UK) 'Public Domain' generally but not exclusively applies to copyrighted work upon which the copyright has expired or was so old it was never copyrighted in the first place.

What I think you mean by 'Public Domain' was that he 'uploaded it to the internet and thus lost practical control of it going forward'. In reality, this is true, even though the law would say that actually that work is copyrighted it - he created it, he owns it (still) and owns the copyright on it, hence not Public Domain.

Source: Mother is a copyright lawyer...I have been lectured on this matter at least once.
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Elecman

Established Member
Joined
31 Dec 2013
Messages
3,567
Location
Lancashire
So in other words - in the public domain. I am sure Elecman has his reasons but when stuff is in the public domain - well - it is in the public domain.

The reason being that notice is for railstaff not the general public. Attaching to the gate to the worksite is so that all staff passing that point will hopefully read it.
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
Hi. I have a dozen or so photos i took at Lostock and from the train into M/cr yesterday. Happy to share but as a new member I don't think I can PM you.

Great! Do you also have any historic ones you've taken?

I believe you have to post five times to "qualify" to be able to send PMs, you've already done three, so I suggest you just post a couple of very short ones, such as a reply to this, followed by a comment on what you've seen on the line, then you can send me a PM. I'll reply with my email address and hey, ho, off we go.
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
The reason being that notice is for railstaff not the general public. Attaching to the gate to the worksite is so that all staff passing that point will hopefully read it.

Tricky1, when we're up and running, if you send me the photo in question I should be able to blank the relevant bit. If I can't for any reason I'll not publish it.
 

Tricky1

Member
Joined
23 Jul 2018
Messages
6
Great! Do you also have any historic ones you've taken?

I believe you have to post five times to "qualify" to be able to send PMs, you've already done three, so I suggest you just post a couple of very short ones, such as a reply to this, followed by a comment on what you've seen on the line, then you can send me a PM. I'll reply with my email address and hey, ho, off we go.

Thanks. I've a few from the Lostock area earlier this and late last.
 

wrinkley

Member
Joined
6 Feb 2015
Messages
130
Mmmm mid to lateOctober. It is going to be tight.
The work involved is for track renewal, not electrification. The track between the station and just past Beaumont Road was renewed when the bend was eased about two years ago. The new rails are already lying inside the track on the down line at Dean Clough, see photo A680b.
 
Last edited:

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,461
Location
Preston Lancs
The work involved is for track renewal, not electrification. The track between the station and just past Beaumont Road was renewed when the bend was eased about two years ago. The new rails are already lying inside the track on the down line at Dean Clough, see photo A680b.
ok thanks for that. Helps enormously
 

Joseph_Locke

Established Member
Joined
14 Apr 2012
Messages
1,878
Location
Within earshot of trains passing the one and half
The work involved is for track renewal, not electrification. The track between the station and just past Beaumont Road was renewed when the bend was eased about two years ago. The new rails are already lying inside the track on the down line at Dean Clough, see photo A680b.

I'd guess it includes the stretch of life-expired stuff on the up line just before the speed drops to 75 approaching Bolton.

What's puzzling me (and my colleagues) is what on earth that is left to do that needs a 9-day blockade?
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
I'd guess it includes the stretch of life-expired stuff on the up line just before the speed drops to 75 approaching Bolton.

What's puzzling me (and my colleagues) is what on earth that is left to do that needs a 9-day blockade?
Installation of all the power-related gubbins and connection to the National Grid?
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,461
Location
Preston Lancs
What's puzzling me (and my colleagues) is what on earth that is left to do that needs a 9-day blockade?
There is a neutral section at Euxton Jct so no issue there one would think. There is nothing to link up to at Lostock so no problem there. So there is through Salford Central to the existing and at Ordsall. But I guess you are correct 9 days seems a lot.
 

twpsaesneg

Member
Joined
21 Jul 2009
Messages
480
There is a neutral section at Euxton Jct so no issue there one would think. There is nothing to link up to at Lostock so no problem there. So there is through Salford Central to the existing and at Ordsall. But I guess you are correct 9 days seems a lot.
I'm not sure precisely what the content of the blockade is, however, bear in mind Section Proving can be a long process (effectively energising different bits of the route and operating lineside switches to ensure that each switch does what it's supposed to and there's no jumpers in the wrong place).

This is very much a Could Be and not a Definitely Is though, so if someone else knows when that is happening feel free to correct me!
 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,587
If this blockade is for Section Proving and if (possibly a big if!) it all goes well, could we be seeing electric trains run in passenger service by the end of September? If so, do Northern have enough 319s to cover all the necessary diagrams?
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,461
Location
Preston Lancs
If this blockade is for Section Proving and if (possibly a big if!) it all goes well, could we be seeing electric trains run in passenger service by the end of September? If so, do Northern have enough 319s to cover all the necessary diagrams?
No harm running electric just don’t change the timetable yet - until next May.
 

Elecman

Established Member
Joined
31 Dec 2013
Messages
3,567
Location
Lancashire
If this blockade is for Section Proving and if (possibly a big if!) it all goes well, could we be seeing electric trains run in passenger service by the end of September? If so, do Northern have enough 319s to cover all the necessary diagrams?
Nope section proving is merely an essential part of proving the system fit for use. The ORR still has to approve all the paperwork before passengervtrains can use the new infrastructure and that takes as long as it takes as apparently there is only 1 person in the ORR qualified to make that descision on electrification schemes
 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,587
The ORR still has to approve all the paperwork before passengervtrains can use the new infrastructure and that takes as long as it takes as apparently there is only 1 person in the ORR qualified to make that descision on electrification schemes
Are there any other electrification schemes which might conflict with this one for the paperwork?
 

wrinkley

Member
Joined
6 Feb 2015
Messages
130
Isn't there a lot of wire runs still do though?

Is the track replacement, between Lostock Station and Bolton station according to the header on the letter, being delayed until September/October in order to get the wiring in that area completed first.
 
Last edited:

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
Trick1 has sent three batches of shots following his debut yesterday.

The first batch extends his initial set taken at Lostock on Monday. I've added them to his album here:

https://www.flickr.com/photos/127646831@N03/albums/72157696225129232

and also to the Combined Volume here:

https://www.flickr.com/photos/127646831@N03/albums/72157661069863633

The second batch shows Dean Clough last winter and the third shows works at Lytham, also last winter.

Family commitments mean it will almost certainly be tomorrow (Thursday) evening before I can add these last two.

Fab stuff, thank you Mr T.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,556
Are there any other electrification schemes which might conflict with this one for the paperwork?
GWML from Didcot to Swindon is currently being tested, and isn't supposed to be signed off until the end of the year
 

Ploughman

Established Member
Joined
15 Jan 2010
Messages
3,097
Location
Near where the 3 ridings meet
Nope section proving is merely an essential part of proving the system fit for use. The ORR still has to approve all the paperwork before passengervtrains can use the new infrastructure and that takes as long as it takes as apparently there is only 1 person in the ORR qualified to make that descision on electrification schemes
I seem to remember the same point being made on the Liverpool - Manchester wiring up.
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
I've been able to add Tricky1's additional photosets to his album here:

https://www.flickr.com/photos/127646831@N03/albums/72157696225129232

and to the Combined Volume here:

https://www.flickr.com/photos/127646831@N03/albums/72157661069863633

As most of this additional material was taken some time ago readers may find it easier to view them in Tricky1's album, as the older material is automatically placed in chronological order.

Super stuff, which shows progress on the railway, the foliage and the temperature!

Thank you Tricky1.
 
Status
Not open for further replies.

Top