According to the Manchester Evening News
A spokesman for Northern and Network Rail said: “In order to make space on the network for the thousands of extra services, the timing of all GTR and most Northern services had to be changed.
“All of these new journeys needed to be individually approved by Network Rail to ensure the national rail network runs safely and smoothly.
“Unfortunately, as a result of the sheer number of changes required and the late running of some engineering improvements, the process took longer than anticipated, approvals for service changes were delayed and some timetable requests were changed.
“Whilst circumstances differ across the country, this meant that train companies had much less time to prepare for the new timetable which required trains and drivers to run on different routes.
“The differences between the timetables submitted and those approved created a requirement for training that had not been anticipated.
“This meant that the necessary specialist training was not able to be completed in time for drivers to learn new routes and for operators to address all the logistical challenges.”