I agree, I just wish the GWSR weren't so coy about making it a stated intention to extend to Honeybourne. Clearly it won't happen tomorrow, Broadway has to be completed, the new service introduced and 'bedded in'. A period of consolidation is inevitable. And an extension can't begin until funding is available.
My understanding is that once the work at Broadway is completed maybe in 2 years time and the new services & passenger numbers are known, then decisions & discussions on further extensions could be made.

Any extension must make business sense in cost, profitability, volunteer staffing etc and be supported by members of the railway and other interested parties.

The Honeybourne area will be tricky / costly due to it being NR land and subject to significant railway enhancement proposals. The decision to extend north or south will now probably be heavily dependant on those third parties, Cheltenham in the south and Worcestershire / Stratford / NR in the north.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

jimm

Established Member
Joined
6 Apr 2012
Messages
5,276
I agree, I just wish the GWSR weren't so coy about making it a stated intention to extend to Honeybourne. Clearly it won't happen tomorrow, Broadway has to be completed, the new service introduced and 'bedded in'. A period of consolidation is inevitable. And an extension can't begin until funding is available.

There is nothing coy about the current position of the GWSR board.

It was stated in black and white in the quote below that was attributed to press officer Ian Crowder in an article in the current Railway Magazine.

"There are no immediate plans for any further extensions in the foreseeable future - either north or south."

The article then lists a series of investment priorities to improve facilities at Toddington and Winchcombe for rolling stock and volunteers and improved security systems at key locations.

Future extensions will take a long time even when a decision is made - at the Broadway scheme's rate of progress, even if they started this year, they wouldn't complete the similar distance to Honeybourne until 2030.
 

AndyY1951

Member
Joined
19 Oct 2017
Messages
193
Location
Preston, Lancashire
That statement is a masterly bit of ambiguity any politician would be proud of!
No immediate plans' - fair enough, the railway has plenty on its plate for the next few years. 'The foreseeable future' - this could mean anything.
Why can't the railway say something along the lines of 'It is our ambition to extend to make connection with the National Network at Honeybourne at some time in the future. This will not happen for perhaps ten years, and depends on many factors, but it is the long-term plan'. This wouldn't commit the railway to anything, but would be a statement of intent.
Your '2030' isn't that far adrift from my guess that hopefully it could and should be happening within a decade. I hope I'm still around to see it!
 

reddragon

Established Member
Joined
24 Mar 2016
Messages
3,274
Location
Churn (closed)
Its just been announced that Wychavon District Council are to Build the Car Park at Broadway Station.

I am delighted to be able to tell you that Wychavon District Council (Wychavon) approved the construction of a car park at Broadway at their executive meeting on Wednesday 10 January 2018. The funds were allocated to the project and the chief executive was given authority to acquire the land from us and build the car park. Privately I have been advised that it should be open by August 2018.

That's good news for the progression of the station
 
Last edited by a moderator:

DCL_Rider

Member
Joined
7 Feb 2015
Messages
9
Location
Leamington
Its just been announced that Wychavon District Council are to Build the Car Park at Broadway Station.


That's good news for the progression of the station
Indeed. the Video of the council meeting shows some Councillors keen for connection at Honeybourne and even through running from Cheltenham RC to Bridgnorth via Worcester and Kidderminster!
Perhaps the ambiguity by GWSR is trying to see what support (funding) comes forth from local authorities and even NR?!
 

STEVIEBOY1

Established Member
Joined
31 Jul 2010
Messages
4,001
Indeed. the Video of the council meeting shows some Councillors keen for connection at Honeybourne and even through running from Cheltenham RC to Bridgnorth via Worcester and Kidderminster!
Perhaps the ambiguity by GWSR is trying to see what support (funding) comes forth from local authorities and even NR?!


Indeed. the Video of the council meeting shows some Councillors keen for connection at Honeybourne and even through running from Cheltenham RC to Bridgnorth via Worcester and Kidderminster! Now that would be good. :D
 

reddragon

Established Member
Joined
24 Mar 2016
Messages
3,274
Location
Churn (closed)
Indeed. the Video of the council meeting shows some Councillors keen for connection at Honeybourne and even through running from Cheltenham RC to Bridgnorth via Worcester and Kidderminster!
Perhaps the ambiguity by GWSR is trying to see what support (funding) comes forth from local authorities and even NR?!

With all the hard work to reach Broadway, there are other pressing priorities. There are 2 good reports from yesterdays progress meeting . .

Video 1 contains presentation by Ian Stewart (Volunteer Resources Director), Colin Fewell (Commercial Director) and Richard Johnson (Chairman)

https://youtu.be/uXOky-fFznw

In video 2, Colin Fewell talks about the timetable for 2018 and the plans for Broadway opening weekend and volunteer special trains

https://youtu.be/GP2FlspZRIQ


Apart from the huge unknown of volunteer needs for 2018, Broadway station needs finishing (signals / platform 2 / bridge etc) but also there is a lot of maintenance to catch up on including track renewals and bridge works highlighted on the video and the bridges blog.

The general view is that it will take the railway 5 years to be ready for anything else!

Perhaps if the local councils get together, a plan could be put together to do enabling work to extend the railway, particularly on bridges, clearance, fencing and ownership of the track bed. This could then be followed by a LEP grant to extend.
 

reddragon

Established Member
Joined
24 Mar 2016
Messages
3,274
Location
Churn (closed)
It looks like extra trains have been added to the Easter weekend. Perhaps pre-bookings are higher than expected!

https://www.gwsr.com/Opening_to_Broadway__30_March_to_2_April_2018--post--45.html

Stop press: We have put in place an additional train service for this period which departs from Cheltenham. We now have trains starting their journies from both Broadway and Cheltenham at 0940, plus a third train starting from Toddington at 1100.
 

CarltonA

Member
Joined
22 Apr 2012
Messages
877
Location
Thames Valley
GWR 6023 'King Edward II' is coming to the GWsR in May.
That should spice things up a bit!

I'm looking forward to that, were Kings often to be seen on the line in days gone by? There wont be much difference in weight between 35006 and 6023, hopefully they will be seen together.
 

4141

Member
Joined
21 Dec 2015
Messages
170
No, Kings were never seen on that line - Castles were the largest used...
 

Shenandoah

Member
Joined
19 Jun 2015
Messages
116
Location
Thunder Bay
When the North Warwickshire line from Tyseley was in the hands of the GWR and in the early days of BR(W) I lived near Shirley and the line was at the bottom of our property, on a low embankment. I saw most classes of GW locomotives plus some the the WD Austerities and for a short period, in the morning, a GWR railcar service from Cardiff. One locomotive class I did not see, I was informed that they were out of gauge for the line, were King class locomotives. Was this prohibition applicable to the whole line or just the northern part , for instance north of Stratford upon Avon?
 

4141

Member
Joined
21 Dec 2015
Messages
170
When the North Warwickshire line from Tyseley was in the hands of the GWR and in the early days of BR(W) I lived near Shirley and the line was at the bottom of our property, on a low embankment. I saw most classes of GW locomotives plus some the the WD Austerities and for a short period, in the morning, a GWR railcar service from Cardiff. One locomotive class I did not see, I was informed that they were out of gauge for the line, were King class locomotives. Was this prohibition applicable to the whole line or just the northern part , for instance north of Stratford upon Avon?
The whole line down past Cheltenham and Gloucester, and from there to Swindon, Bristol and Cardiff were all out of bounds to Kings as far as I'm aware!
 

Shenandoah

Member
Joined
19 Jun 2015
Messages
116
Location
Thunder Bay
Thank you 4141. I guess the new heritage railway had created better clearances now. Besides, the line is only a very short piece compared to the original.
 

reddragon

Established Member
Joined
24 Mar 2016
Messages
3,274
Location
Churn (closed)
The attendance of the King has been confirmed along with some answers about the only King thought to have traversed the line

http://gwsrsteamloco.blogspot.co.uk/2018/02/a-regal-gala-visitor.html
https://www.gwsr.com/enthusiasts/major_events.html

I can now confirm that we are in negotiation with the Didcot Railway Centre, and subject to contract, I am more than a little pleased to be able to present to you the first guest engine that we can announce for the Cotswold Festival of Steam "Give My Regards to Broadway" gala on the 26th - 28th May in the shape of 6023, King Edward II.

It's believed that the only occasion a King has ever run over this route before was a 'positioning move' for No. 6000 King Geoirge V in the mid-1970s.
 

DCL_Rider

Member
Joined
7 Feb 2015
Messages
9
Location
Leamington
Today, 9th March 2018 7903 Foremarke Hall headed the first steam hauled train into newly rebuilt Broadway station. The purpose was to effect a gauging run with a typical train of 8 coaches.
Video on You Tube
 

4141

Member
Joined
21 Dec 2015
Messages
170
A good report on BBC Midlands Today just now, with some nice shots - worth catching on IPlayer later!
 

reddragon

Established Member
Joined
24 Mar 2016
Messages
3,274
Location
Churn (closed)
I had my ride to Broadway today. 35006 is being used so that the GWR engines are spic & span GW fashion for Easter!

Very smooth track. A bit spooky being in a very new but 100 year old style station!

So many locals & TV crews!
 

gazthomas

Established Member
Joined
5 Jun 2011
Messages
3,466
Location
Llandudno
What a superb achievement! Would a southbound extension to Cheltenham itself be possible?
 

reddragon

Established Member
Joined
24 Mar 2016
Messages
3,274
Location
Churn (closed)
An extension through Cheltenham is entirely feasible, but due to the scale of the works needed, it probably needs external funding and main contractors for many of the tasks needed to be done.
 

ABB125

Established Member
Joined
23 Jul 2016
Messages
4,343
Location
University of Birmingham
What a superb achievement! Would a southbound extension to Cheltenham itself be possible?
As far as the Prince of Wales stadium is about doable, but does involve going through Hunting Butts tunnel, the state of which I am not aware of. Beyond the stadium, the trackbed is a cycle path, so further extension would be rather difficult. Besides, one of the old bridges had been replaced with a new pedestrian-style bridge.
 

STEVIEBOY1

Established Member
Joined
31 Jul 2010
Messages
4,001
It is still their plan to go on beyond Broadway towards the Oxford/Evesham line & onto Stratford-(Warwickshire)?
 

reddragon

Established Member
Joined
24 Mar 2016
Messages
3,274
Location
Churn (closed)
I think that once carriage sheds are built, bridges & track works are done and other improvements, plus of course finishing Broadway Station, then options such as double tracking & extending north become an option.

A big dependency is development at Long Marston and the potential to re-open Stratford to Honeybourne as a main line by NR.
 