Do you have any sensible quantitive evidence for this? Northern's capacity obligations are for 40% more passenger seats in peak hours into Manchester, Leeds, Liverpool, Sheffield and Newcastle by December 2019 (see
capacity train service requirements). Do you think this is insufficient?
In order to deliver this there are going to be extensive train lengthening programmes:
- 6*23m Leeds to York, Selby, Skipton and Manchester Victoria via Brighouse and Bradford
- 5*23m Manchester to Southport, Clitheroe, Kirby and Huddersfield
- 4*23/20m. Manchester to Buxton, Chester (via Northwich), Sheffield, Liverpool (CLC) and Glossop
- 3*20m Leeds to Knottingley and Huddersfield to Sheffield.
Apart from the Leeds to Manchester Victoria services, none of these need 195s (the Blackpool/York service is going to be running fast between Leeds and York).
I think the real risk at the moment is Network Rail not completing the platform lengthening programme. The CP5 Enhancements Plan is only showing Grip 3 complete by December 2019.