I remember Philip Phlopp explaining how expensive they were and they're really not cheap. If you want to run a battery railway then your feeder stations would need to be even more expensive, because they now need to provide enough power for trains to charge up rapidly.
But feeder stations, like most high voltage electrical substation equipment, tends to scale very well with increasing power output. So a 25kV supply point with twice the power does not cost twice the price.
And the minimum power that a 25kV GSP can normally support would be several megawatts in most cases.
A 2-car EMU could charge a 1MWh energy storage system in ten minutes (from entirely flat) with a 6MW power availability, which would not be enormously onerous to provide.
The enormous cost of the overhead lines on the modern railway have driven all other electrification costs into the background.
A twin track railway costs
£5m per kilometre. GSPs cost a few tens of millions each at most, especially as this would be a relatively simple GSP with precisely one output circuit breaker since it only feeds the platform roads and not a complex feeding system with cross-feed potential.
Then, your expensive grid supply will turn off when the charging trains drive away and run on their battery power. Instead of having a constant flow of moderate power you need to have bursts of very high power and then lots of nothing. This would have a very big effect on the electrical grid, even where you have lots of renewables available. I wouldn't be surprised if the power requirements for charging up a WHL train were greater than the total domestic supply to the town of Fort William.
We are on the 132kV network now. It can handle spikes of a few megawatts with only relatively minor reinforcing work.
Then again a single phase pole line paralleling the railway outside the boundary fence is going to cost a tiny fraction of the cost of GSPs or total electrification. 2 Conductors connected antiphase into a 50kV circuit, with only an autotransformer (and probably a local circuit breaker) provided at each recharging station.
The connection to the grid can be made at a location where a single phase load of a few megawatts that comes and goes is extremely trivial, if it can even be noticed against background phase imbalances.
Even a 132kV wood-pole overhead line only costs on order of ~£100k/km. So a 25-0-25kV circuit is likely to be around this cost or less.
Running power cables along the track means you are shifting the balance further towards the costs and benefits of traditional electrification.
No it doesn't.
The cost of a line paralleling the railway outside the fence is a tiny fraction of the cost of electrification.
I also doubt that providing a high-voltage traction supply along the track would be significantly cheaper than installing OHLE anyway. It's more efficient to try to fit such a linear thing along the existing linear railway land, following all of the existing curves and remaining accessible to maintenance crews using RRVs.
Why the hell would it be on railway land?
You would put it in the field a hundred yards away, and it would follow the most efficient possible alignment between the charging points.
So it goes nowhere near the curves since it can just go over hills etc
Even if the land can be bought to cut corners, the curves in the railway often exist for good geographic or geological reasons, and you would need to ensure access along the non-railway section. Since you would be using RRVs for the rest of the maintenance along the linear railway, you would want to be able to access the non-railway sections with RRVs too for efficiency's sake.
Can't RRVs go anywhere where normal 4x4s can go?
How do you think the electricity grid does maintenance on power distribution systems?
Your wood pole power line would need a similar amount of piling operations as overhead line gantries would and would take a similar amount of time.
Normal spacing for 33kV circuits according to Scottish Power's uncontrolled specification is something like 100m.
I don't think we do that much on the railway, especially considering the curves.
Also piling a wooden pole in the middle of a field is somewhat less expensive than doing a steel or concrete post next to an active railway.