The section of the Overground network between Richmond and Willesden Junction has been closed for the better part of 10 days or so. Does anyone know what work has been done to the line given that the District Line has remained in operation from Gunnersbury southwards? Just curious as to what work is so large that it requires such a long closure.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Class315

Member
Joined
9 Feb 2008
Messages
329
The closure was indeed for track and points renewal and replacement at Acton Wells Junction
 

306024

Established Member
Joined
23 Jan 2013
Messages
3,974
Location
East Anglia
I as told that there was a bridge that needed replacement as well at Acton Wells otherwise it couldn't support the cranes etc needed to do the track renewals, hence the longer than originally planned possession.
 

Taunton

Veteran Member
Joined
1 Aug 2013
Messages
12,273
The section of the Overground network between Richmond and Willesden Junction has been closed for the better part of 10 days or so. Does anyone know what work has been done to the line given that the District Line has remained in operation from Gunnersbury southwards? Just curious as to what work is so large that it requires such a long closure.
Replacing one Pandrol Clip always seems to take 10 days nowadays.
 

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,661
I hope they prepared that bit of line when the link between GWML and WCML (and MML?) is eventually electrified with 25kv ac Overhead.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,803
I as told that there was a bridge that needed replacement as well at Acton Wells otherwise it couldn't support the cranes etc needed to do the track renewals, hence the longer than originally planned possession.

Big track renewal (including a set that repeatedly fails), and a bridge strengthening job.
 

cle

Established Member
Joined
17 Nov 2010
Messages
5,637
This poor line has been dug up a million times over the last few years - and still no major improvements in frequency (unlike via Clapham) - and none planned either.

Gunnersbury is still a disgrace, despite the Business Park being supposedly obligated to improve it - rather than the white elephant bus station.
 

RichmondCommu

Established Member
Joined
23 Feb 2010
Messages
6,906
Location
Richmond, London
This poor line has been dug up a million times over the last few years - and still no major improvements in frequency (unlike via Clapham) - and none planned either.

Gunnersbury is still a disgrace, despite the Business Park being supposedly obligated to improve it - rather than the white elephant bus station.

However you had a route which had been starved of investment for decades and badly needed modernizing. Like anything else the longer you leave it the more it costs, and in the case of the railway that means long periods of the railway being shut.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,803
This poor line has been dug up a million times over the last few years - and still no major improvements in frequency (unlike via Clapham) - and none planned either.

Gunnersbury is still a disgrace, despite the Business Park being supposedly obligated to improve it - rather than the white elephant bus station.