Two promised rail upgrades in northern England and the Midlands that were shelved by the government in June, breaking election pledges, are to be restarted, the transport secretary will say on Wednesday.
The electrification of the TransPennine Express route and Midland mainline, which had been described as vital elements of a £38bn upgrade to the rail network for the north, were cancelled from Network Rails five-year plan in June.
Patrick McLoughlin blamed Network Rail, but it became apparent that his department had been warned a year before the election that the works were in doubt.
The scrapping of the schemes was an embarrassment for the chancellor, George Osborne, in particular, who had promised major transport enhancements as part of a new northern powerhouse.
The unpausing with a revised timetable and specification to be announced in Leeds on Wednesday is carefully timed ahead of the Conservative conference in Manchester next week.
•Work on electrification of TransPennine and Midland Mainline to restart
•TransPennine line will deliver faster journeys and more capacity to help deliver a Northern Powerhouse
•Midland Mainline improvements will mean electrification to Kettering and Corby by 2019
Work to electrify TransPennine and Midland Mainline railways will resume under plans announced today, Wednesday 30 September 2015, as part of Sir Peter Hendy’s work to reset Network Rail’s upgrade programme.
Sir Peter Hendy has outlined to the Secretary of State for Transport how work could continue. The Secretary of State has replied to the Chair of Network Rail asking Network Rail to un-pause this work.
•Letters about rail electrification of TransPennine and Midland Mainline routes
Network Rail will work with the Department for Transport (DfT) and Rail North to develop a new plan for electrification of the TransPennine line between Stalybridge and Leeds and on to York and Selby to focus on delivering key passenger benefits as quickly as possible. This is an improvement on the previous plan which only changed the power supply of the trains.
The new plan will deliver faster journey times and significantly more capacity between Manchester, Leeds and York. The upgrade is expected to provide capacity for 6 fast or semi-fast trains per hour, take up to 15 minutes off today’s journey time between Manchester and York and be complete by 2022. When the work is finished, the whole route from Liverpool to Newcastle (via Manchester, Leeds and York) will be fully electrified and journey times will be significantly reduced compared to today’s railway.
Network Rail will also recommence work to electrify Midland Mainline, the vital long-distance corridor which serves the UK’s industrial heartland. Sir Peter Hendy is proposing that line speed and capacity improvement works already in hand are added to, with electrification of the line north of Bedford to Kettering and Corby by 2019 and the line North of Kettering to Leicester, Derby/Nottingham and Sheffield by 2023.
New Northern and TransPennine rail franchise awards will be announced before the end of the year. The new franchises will:
•deliver new train carriages and remove out-dated Pacer trains
•introduce free Wi-Fi on trains
•offer a one-third increase in capacity with 200 additional services on weekdays and Saturdays and 300 more train services on Sundays
The total programme of rail electrification and upgrades will completely transform the railways for passengers in the north and Midlands and help ensure that every part of Britain benefits from a growing economy.
Secretary of State for Transport Patrick McLoughlin said:
“
As a one nation government we are making sure every part of Britain benefits from a growing economy. Connecting up the great cities of the north is at the heart of our plan to build a Northern Powerhouse. This government will see the job through and build a better, faster and more reliable railway for passengers in the north and Midlands.”
Chairman of Network Rail Sir Peter Hendy said:
“The temporary pause in the programme has given us the space to develop a better plan for passengers. People can expect more services and faster journeys. We face some difficult challenges, and there is more work still to do, but the Secretary of State’s decision means we can now move forward with our plans to electrify TransPennine and Midland Mainline”.
Network Rail will work with the Department for Transport (DfT) and Rail North to develop a new plan for electrification of the TransPennine line between Stalybridge and Leeds and on to York and Selby to focus on delivering key passenger benefits as quickly as possible.
The whole project including detailed planning was paused. Sir Peter Hendy has recommended that full detailed planning should commence immediately and be completed by end of 2017, with electrification commencing early 2018 for completion by 2022. The Secretary of State has accepted the recommendation and requested they are "progressed with some urgency".Hold your horses folks - the DfT announcement doesn't actually say that electrification is back on for TransPeninne, it just reiterates what we already know - in that...
Talk about double speak !
.
I recognise that there is more work to do on your overall re-plan and that successful delivery of these projects has some cost implications. As you say, it is right that Network Rail are as ambitious as possible in seeking to meet pressures from within existing resources in the first instance, before making a call for additional public funds
I thought the industry thinking was that a more comprehensive upgrade of the line (signalling and linespeed enhancements) was required before wires are put up. Does this announcement imply that an upgrade will not be occurring?
To me it implies that upgrade, or at least an improvement vs what is there today, will happen.
It's the Tory party conference in Manchester next week - Osborne had to show his Northern Powercut was plugged in again. Political expediency rules. I wonder when the "unpausing" will begin - 2025 or 2030 ?
Well, according to kind Uncle Jeremy, all will be different when his steady hand holds the Socialist tiller in Britain and I am most surprised to see you feel that a Conservative government will be in power in 2025 and 2030.
What about the recently generated euphoria of the Socialist "Brave New World" that will be so overwhelming that we will see the Labour Party as the natural party of power, overwhelmingly endorsed by the electorate, for future eons....or so we are told.
It's the Tory party conference in Manchester next week - Osborne had to show his Northern Powercut was plugged in again.
Political expediency rules.
I wonder when the "unpausing" will begin - 2025 or 2030 ?
Yes, that is the reason for the announcement being made now.
The original approval for TP electrification was in November 2011, no doubt after some investigation work and costing by Network Rail.
Nearly 4 years later, we still do not have a design, and the completion dates must still be guesswork.
6tph doesn't seem any more than was originally expected (although NR subsequently found it couldn't support 6tph).
There already was a CP5 plan (independent of electrification) called Leeds-Manchester journey time improvements.
I think we are being sold a late/more costly CP5 plan as an "upgrade" stretching into CP6.
Objective of keeping to narrow CP5 costs achieved (with the overrun pushed into CP6!).
Now we just have to delete a CP6 project to make way for it.
The late start on site (2018) does at least suggest that the NW contractor (still to be appointed) can finish that job and then carry on eastwards with TP.
Under the Northern Hub 6tph were to be provided and that was before electrification was announced. So what has been said is not an improvement on what they were supposed to being doing under the Hub anyway. However because ORR were querying the CP5 budget I believe an essential element of the Hub was dropped to save money because NR said that as TP is to be electrified we don't need to open the old bores at Standedge. We subsequently know that turned out to be untrue and NR now admit to provide the capacity and increase speed they need to do more - what as yet we don't know.
They will at least be 4 car which is an improvement on the current 185's, assuming of course we get a networker/electrostar derivative and not 317/321 stock, or anything else 20m in length!