Came across this article on Google Now earlier. Quite a good read and it shows, if anything, how well Southern are actually doing.: http://www.southernrailway.com/sout...dard-article-18th-september-on-cancellations/
I couldn't think of a better title so feel free to change it to something better
Southern Railway said:Response to Evening Standard article 18th September on cancellations
The above article which showed we cancelled 34,701 trains in 2012/13 failed to say that we also run over 750,000 trains per year – the second highest number in the country – and that the cancellations listed form 4.6% of that total.
Both part and full cancellations (where a train either skips stops to make service recovery quicker, or terminates short of its original destination), along with trains that are more than 30 minutes late make up the overall number of cancellations as detailed in the Network Rail report. Part cancellations make up the largest proportion of our overall cancellation figure.
When there are incidents which close lines such as fatalities and infrastructure problems, train cancellations are inevitable, but once lines open again, our top priority is to recover the service as quickly and as efficiently as possible which is what our passenger expect. Due to the congested nature of our network, this is something that generally can’t be done without short notice alterations to train services, including part cancellations or full cancellations.
There have also been major changes at London Bridge station as part of the Thameslink Programme where our platforms have been reduced from nine to six, and our lines in to the station reduced from five to three – all with only a small reduction in Southern services calling there. When disruption occurs in the area, the volume of trains timetabled to call at London Bridge means that we have to reduce the service if there are too many trains for the platforms available.
We have also seen the worst winter on record in terms of rainfall and have been subjected to flash floods, high winds and trees and other debris falling onto the tracks, closing lines and causing severe disruption. The South East was the worst hit and these storms alone accounted for 35% of our total cancellations for the year.
All of the above have contributed significantly to the cancellation figure and we are working with Network Rail to minimise future cancellations and to improve our performance.
Network Rail’s South East Route Director, Dave Ward. Has written an open letter explaining the problems they have been experiencing at London Bridge as a result of poor reliability with the infrastructure. His letter is here: http://www.networkrail.co.uk/letter-from-dave-ward/
I couldn't think of a better title so feel free to change it to something better