Aren't the containers that form the emergency breakwater sitting on the dipped section of footpath?
Yes they are and just to clear up a few questions from other posters.
The scaffold was provided for running out and temp supporting the new cables, also a additional scaffold was erected for access across the breach.
The suggestion about running trains on the 28th may have come from one of my earlier posts in reference to engineering trains, in fact these trains will run on the 29th, where emergency track renewals are taking place in the Spray Point area (where the cliff fall is) to remove/renew the track which has had a TSR on it since 2012 and also to renew the recent track damage from the controlled slip site.
In regard to signalling, I'm not a signal person but I can say that all axle counters are being renewed.
One other item that may interest is both lines across Marine Parade has been ballast bonded with an additional site from mid point Dawlish Station to Coastguards bridge