12,774
Veryy smart thinking, will have taken a lot of effort to bring work forward like that
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Zoidberg

Established Member
Joined
27 Aug 2010
Messages
1,270
Location
West Midlands

An extract for link challenged members:

MAJOR construction work on Kingskerswell bypass has closed two sections of rail line in South Devon.

The work is being carried out on the culvert near Sainsbury's at the Newton Abbot section of the South Devon Link Road.

The tracks are being lifted to install a replacement drainage culvert under the main Paddington to Plymouth and Paignton railway line at Aller junction which is required for the South Devon link road.

The work has been brought forward to coincide with the main line closure at Dawlish and is scheduled for nine days.

The main line is expected to reopen on April 4, so the bypass contractor Galliford Try wants the culvert work done while the repair work at Dawlish is still under way, to avoid another closure later in the year.
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,666
Last edited:

Cletus

Established Member
Joined
11 Dec 2010
Messages
2,398
Location
Dover
There's a comment on the Dawlish webcam saying that the line will re-open a week earlier than planned on 28th March. Anyone heard this?
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,666
There's a comment on the Dawlish webcam saying that the line will re-open a week earlier than planned on 28th March. Anyone heard this?

Just seen that myself... Honest opinion is that it does not look that far fetched. Look at the work no and we are very very close to the stage of putting ballast into the breach... Trains running and work ending are two very different things too. Ballast train arrived today and they are tamping the rest of the line so again, the route being reopened is not beyond the realm of possibility. The only snag is this controlled landslide which i cant seem to work out if it has happened or not?
--- old post above --- --- new post below ---
Still think that is unlikely mind....
--- old post above --- --- new post below ---
Apologies. This should be a public post on Facebook so those without it should just be able to click on this link and see the images. I cannot extract the images from Facebook unfortunately.

https://www.facebook.com/vivsparkles/posts/10151917093796529

Shows Colas Rail class 70s on the sea wall very close to the breach delivering ballast to the site.

Also
https://www.facebook.com/photo.php?fbid=10152065749867842&set=o.107778222580678&type=1&theater

This should be a public post too, this shows the operation to remove landslip material from the hill. Sources say it is just a steady stream of slurry that is being cleared away so as to not damage the formation. Good move to do it now rather than wait for a collapse and close it again.

Apologies that i can not extract the photos....
 

Zoidberg

Established Member
Joined
27 Aug 2010
Messages
1,270
Location
West Midlands

An extract for those who cannot access links ...

The Army has been called in to help reinstate the main rail line to the south west of England after it was destroyed by storms.

Up to 30,000 tonnes of unstable rock and soil has to be removed near Dawlish in a controlled landslip.

Network Rail hopes the Royal Engineers will be able to use specialist equipment to remove part of the rock face so the line can be reinstated.

It added it hoped the line would still be reopened on 4 April.
 

MarkyT

Established Member
Joined
20 May 2012
Messages
7,567
Location
Torbay
There's to be a feature on the controlled landslip on BBC Spotlight local news at 13:30 today on BBC1 south west, and I expect it'll be on the evening edition too. The trailer for this during national news showed a helicopter video view of the site.
 

Graiser

Member
Joined
14 Feb 2014
Messages
50
There's a comment on the Dawlish webcam saying that the line will re-open a week earlier than planned on 28th March. Anyone heard this?

I can say that the track installation will be completed by the 28th, however passenger trains will not run on that date but engineering trains might, if the current thinking of reballasting and relaying at the. Teignmouth slip site goes ahead.
 

Ploughman

Established Member
Joined
15 Jan 2010
Messages
3,101
Location
Near where the 3 ridings meet
Quote - Network Rail hopes the Royal Engineers will be able to use specialist equipment to remove part of the rock face so the line can be reinstated.

Can anyone say what specialist equipment?
As I would have thought that whatever the REs have available is also available commercially
 

oversteer

Member
Joined
26 Jan 2011
Messages
742
An extract for those who cannot access links ...

"... Network Rail hopes the Royal Engineers will be able to use specialist equipment to remove part of the rock face so the line can be reinstated..."

Rock%20blasting%20detonics%20feature.jpg


:)
 

LateThanNever

Member
Joined
18 Jul 2013
Messages
1,029
Ballast bonding on Marine Parade (sorry about the quality)
Very good quality! But never mind the quality - feel the width... So is the bonding everywhere or just at the point where the waves are most likely to overtop? Or throughout the affected area I wonder?
 

D1009

Established Member
Joined
22 Feb 2012
Messages
3,166
Location
Stoke Gifford
I've heard rumours of FGW organising celebrations in Dawlish on reopening, possibly involving 60163 Tornado working the sleepers, anyone else heard this?
 

455driver

Veteran Member
Joined
10 May 2010
Messages
11,329
I've heard rumours of FGW organising celebrations in Dawlish on reopening, possibly involving 60163 Tornado working the sleepers, anyone else heard this?

Yeah but they wont let the likes of you and me on it, we are not 'special' enough!<D

They will have all the pompous 'oh look at me' brigade on it while the people who should be on it (thats the people who actually fixed it by the way) can only look on from the sidelines.

Just open the fullipin line so the railstaff can get on with the day job and the repairers can sit down for a well earned pint or 3.
 

Temple Meads

Established Member
Joined
2 Sep 2010
Messages
2,283
Location
Devon
Last edited:

ModernRailways

Established Member
Joined
21 Apr 2011
Messages
2,180

crewmeal

Member
Joined
1 Dec 2007
Messages
462
Location
Birmingham
I would imagine The Dawlish Air Show will attract more visitors this year than ever, many to see the wall itself.

Regarding a celebration I should think the engineers who are working tirelessly should receive a 'bonus' in their salary.

Regarding a train then lets get a 'King' down with some vintage GWR coaches to run some shuttles between Exeter and Newton Abbot over some summer weekends.
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,666
You do have to wonder if Scarborough Spa Express sort of arrangement int he summer could make money....
 

D1009

Established Member
Joined
22 Feb 2012
Messages
3,166
Location
Stoke Gifford
good to see FGW quashing this (rather absurd) rumour.
Sounded crazy to me as well, but presumably there must have originally been some substance to it to cause FGW to put an end to it in that way.
--- old post above --- --- new post below ---
You do have to wonder if Scarborough Spa Express sort of arrangement int he summer could make money....
That's been done before, called the Dawlish Donkey, but it didn't make enough money, which is why we now have the Torbay Express from Bristol to Kingswear on summer Sundays.
 

infobleep

On Moderation
Joined
27 Feb 2011
Messages
13,451
Not going to happen ;)

See here - http://http://www.firstgreatwestern...tornado-steam-engine-on-night-riviera-sleeper - good to see FGW quashing this (rather absurd) rumour.

From a purely selfish point of view, I'd love to travel on a sleeper train hauled by a steam engine but it's never going to happen. Wouldn't be economical or to make it economical I probably wouldn't want to spent the reasonable but costly asking price.

Sent from my Nexus 5 using Tapatalk
 

Xenophon PCDGS

Veteran Member
Joined
17 Apr 2011
Messages
35,424
Location
A typical commuter-belt part of north-west England
From a purely selfish point of view, I'd love to travel on a sleeper train hauled by a steam engine but it's never going to happen. Wouldn't be economical or to make it economical I probably wouldn't want to spent the reasonable but costly asking price.

Sent from my Nexus 5 using Tapatalk

If I was to travel on a sleeper train in 2014 for a long restful sleep, a steam locomotive would be the last method of haulage that I would choose.
 

cambsy

On Moderation
Joined
6 Oct 2011
Messages
1,111
If doing steam on the Riviera sleeper, i would use double headed Castles or if one available, a King, not an LNER engine like an A1.
 