Dawlish sea wall collapse

Status
Not open for further replies.

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,666
Looks from the camera pictures available that the concrete has finished being poured and is now being protected with little work being undertaken. It is hard to tell but it looks like the top layer is just sheets of timber (formwork). I wouldn't expect any major work till at least tomorrow lunch now.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Graiser

Member
Joined
14 Feb 2014
Messages
50
This is getting confusing, I asked about this on a signalling forum and was told (by someone who checked with Exeter panel) that there is no emergency panel at Newton Abbot and control has continued to be from Exeter.

I'm not a signalling person but I'm fairly sure there is no mini panel in Newton Abbot or Totnes, however lthere is normal signalling from Newton Abbot westwards
--- old post above --- --- new post below ---
Due to more voids found in the sea wall requiring more investigations and subsequent repair works, you can buy yourselves a rail ticket to Dawlish from March 31st ( subject to anymore adverse weather of course )
 

ironstone11

Member
Joined
3 Jan 2013
Messages
217
Re-posted in correct thread.

https://www.google.co.uk/search?q=da...faLYzH7Aai44EQ

Network Rail could complete Dawlish repair early

27 February, 2014 | By Alexandra Wynne

Network Rail is to review whether it can bring forward the date for reopening the storm-damaged line at Dawlish next week.

Speaking to MPs on the transport select committee this week, Network Rail chief executive Mark Carne said there was a chance the repairs would be complete before the mid-April date given last week.

“I’m very hopeful we will be able to bring that date [mid-April] forward,” said Carne, adding that he remained cautious because high spring tides were expected next week.

“We could suffer some setbacks,” he told the committee. “We’re not out of the woods yet.”

The rail operator and owner also said it would be kicking off a study in the next fortnight to look at ways of increasing resilience in the medium term including the potential installation of a breakwater to diminish wave energy. This would either lie adjacent to the sea wall or further out to sea.

Alongside this work Carne said Network Rail would continue to collect all suggestions proposed for rerouting the vulnerable line with the aim of making “pretty firm” recommendations about routes that should be studied in more detail in June. This further work would be completed by September or October, said Carne.

Network Rail and its principal contractor Bam Nuttall are working to reinstate the line that was washed away earlier this month (see box).

Select committee chairman Louise Ellman said that Network Rail had got its assessment “very wrong” when in 2010 it said that the Dawlish flood defences were suitable.

“In 2010 Network Rail got it very wrong when it told the under-secretary of state for transport that the flood defences at Dawlish would be sustainable for the foreseeable future – it didn’t happen,” she said.

Carne replied that the approach to using historical weather data to assess the future resilience of railway infrastructure would need to be revised.

“There’ve been quite a few studies done on the Dawlish wall over the years using the wave and weather data from the Met Office and those have consistently shown that the wall was quite resilient,” he said. “Indeed, over 120 years the wall has never been breached.

“However, we recognise that with climate change and rising sea levels and increasing storm forces that [the wall] was not likely to exist forever, so the study had shown that within the next five to 10 years we would need to do some extra works to Dawlish and that was in the plan. It’s fair to say the weather conditions we saw in February were really the worst that have been experienced in living memory and beyond.

“We used historical data… to do the analysis and I think what we all have to recognise that historical analysis is not an accurate predictor of future weather patterns. Given that, we need to reconsider the flood defences and coastal defences we have across the country.”
Flood and storm damage repairs at Dawlish

Network Rail has now fully assessed the damage the winter storms in February caused to the South Coast Mainline south of Exeter. A 6km stretch of track is affected from Dawlish Warren to Teignmouth. A total of 256m of sea wall is extensively damaged, including the main 105m long breach north of Dawlish. Plus, 525m of granite parapets have failed, causing track ballast to collapse behind them, and Network Rail has 32 separate landslips and cliff failures to deal with.

The storm on 5 February washed away 80m of sea wall and ground, leaving track suspended over a gaping hole up to the houses of Riviera Terrace. After removing the track, contractor Bam Nuttall shored up the hole with sprayed concrete and formed a temporary breakwater of sea containers filled with rock, which were placed on the lower walkway at the foot of the breach.

This line of defence held firm during the second storm on 14 February, which has been described as the most severe in living memory by local residents. A further 20m of sea wall was breached extending the length of the hole. Many more individual wall, parapet and cliff failures also occurred.

The repair work has now been split into sections north and south of Kennaway Tunnel. Contractors Bam Nuttall, Amco, Sisk and Dyer & Butler are working 24 hours in two shifts to get the work finished.

At the main breach, Amco has now backfilled the hole with 5,000m3 of mass concrete to a depth of 3m against a shutter of concrete vehicle barriers. These have been tied together vertically and horizontally into the concrete with steel bars.

This week Amco was pouring a reinforced concrete strip footing and taking delivery of 120 bespoke precast concrete L units.

These will be placed on the strip footing and mass concrete to form a track bed channel with a 2m high wall to the front and a 3m high retaining wall on the landward side. Ballast will be placed in the channel to take sections of track which are being prefabricated at a nearby site inland.

Jon Masters
 

aylesbury

Member
Joined
3 Feb 2012
Messages
622
Thank you Jon that is a most instructive piece lets hope that the wall is protected properly and the current disaster will not happen again.
 

BHXDMT

Member
Joined
18 Feb 2011
Messages
278
Location
England
What has the Kaiser Chiefs got to do with Network Rail....or has my computer made an amazing interpretation of the link in your posting ?

How queer. I definitely opened the Network Rail video when I went to CTRL+C! Guess it didn't work. Added correct URL, although po8crg has posted it.
 

Cletus

Established Member
Joined
11 Dec 2010
Messages
2,398
Location
Dover
http://www.bbc.co.uk/news/uk-england-26433185

The storm-damaged railway line that connects the South West to the rest of the UK will reopen earlier than planned on 4 April, Network Rail has announced.

The line at Dawlish was wrecked on 4 February, when massive waves left the tracks suspended in mid air.

Ten days later, when new storms caused further damage, Network Rail said the route would remain closed until the middle of April.

The news has been welcomed by business leaders throughout the South West.

Chris Pomfret, chair of Cornwall and Isles of Scilly Local Enterprise Partnership, said it was "very, very good news".

"Dawlish is critical for the rail link to Cornwall and it was critical it opened before Easter," he told BBC News.

"This is now three weeks before Easter - so that's great.

"The managing director of Network Rail said they were working 24 hours a day when we were at the select committee and he hoped to bring it forward. I'm delighted that he has."

However, Mr Pomfret said there remained the ongoing concerns about "proper" transport links to Cornwall, which could include an alternative rail route which would avoid Dawlish and/or a breakwater to protect the coastal route.

Network Rail said it had always been conscious of the importance of the railway to the South West's economy and teams had been working around the clock.

"Over the last 10 days in particular, we've made fantastic progress and we're happy to say that we can bring forward the opening of Dawlish to Friday 4 April," MD Patrick Hallgate said.

The work at Dawlish had been the most challenging Network Rail had experienced "in years", because of access difficulties and weather conditions, he added.

The announcement means all First Great Western tickets will now be available from 4 April.

Transport Secretary Patrick McLoughlin said the early reopening would be a "real boost" for local communities and businesses.

Having seen the scale of the damage at Dawlish for himself, the minister added, he also wanted to thank Network Rail's staff for their tireless work.
 
Joined
30 Jun 2009
Messages
1,133
Location
Nottinghamshire
From 18:00 this evening you will be able to watch the rebuilding process live 24/7 from Dawlish at http://www.railcam.org.uk and http://www.dawlishbeach.com

Having seen the test feeds I can state the owner of the dawlishbeach.com has thrown some money at this project and the HD streams are superb. We at Railcam are thankful he has very kindly given us a feed to replace the Dawlish Cam we lost back in January.

Certainly looking forward to watching the rebuild and return of trains to Dawlish.
 

Graiser

Member
Joined
14 Feb 2014
Messages
50
With all this decent weather we're expecting over the next week, will it help speed things up I wonder?

Track planned to commence being installed on March 23rd, critical path for April 4th opening is not the main breach but this:

image.jpg
 

Johnuk123

Established Member
Joined
19 Mar 2012
Messages
2,800
http://www.exeterexpressandecho.co....plan-induced/story-20815189-detail/story.html

Specialist fire crews are in Dawlish preparing to set off a landslide where workmen are repairing the rail network.
Devon and Somerset Fire and Rescue Service are currently working with Network Rail contractors to initiate the controlled landslip of approximately 350,000 tonnes of soil and rock above the main line railway between Teignmouth and Dawlish.

Whatever NR say this massive amount of soil and rock being deposited on the line has surely put paid to the April the 4th reopening.
 

Zoidberg

Established Member
Joined
27 Aug 2010
Messages
1,270
Location
West Midlands
Last edited:

Johnuk123

Established Member
Joined
19 Mar 2012
Messages
2,800
It might well be that a hell of a lot more rock and dirt falls on the track than is anticipated. The figure of 350,000 tons is an estimate but who knows.
 

Zoidberg

Established Member
Joined
27 Aug 2010
Messages
1,270
Location
West Midlands
But if it is just a case of shifting the result of the instigated landslip, they may have in mind simply throwing more resource at shifting it to meet the 4th April date.

EDIT. I've not yet learned how to post links using my phone, but this exercise is mentioned on the BBC webiste. There NR is quoted as saying '... unlikely to impact ...' on 4th April.
 
Last edited:

Graiser

Member
Joined
14 Feb 2014
Messages
50
It might well be that a hell of a lot more rock and dirt falls on the track than is anticipated. The figure of 350,000 tons is an estimate but who knows.

Estimate is between 25000-40000 tons
--- old post above --- --- new post below ---
But if it is just a case of shifting the result of the instigated landslip, they may have in mind simply throwing more resource at shifting it to meet the 4th April date.

EDIT. I've not yet learned how to post links using my phone, but this exercise is mentioned on the BBC webiste. There NR is quoted as saying '... unlikely to impact ...' on 4th April.

Trying to facilitate a "controlled slip" where the worse damage to the track is spoil contamination rather than an uncontrolled slip which has the potential to damage the track (boulders etc) and destroy the parapet wall on the seaside which would indeed put the April 4th scenario at risk
 

Xenophon PCDGS

Veteran Member
Joined
17 Apr 2011
Messages
35,425
Location
A typical commuter-belt part of north-west England
Trying to facilitate a "controlled slip" where the worse damage to the track is spoil contamination rather than an uncontrolled slip which has the potential to damage the track (boulders etc) and destroy the parapet wall on the seaside which would indeed put the April 4th scenario at risk

Until we see the actual results of the controlled landslip, any discussions are just theoretical supposition and I would prefer to hold my judgement until I see what actually occurs and the tonnage actually dislodged.
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,666
Not likely to cause major damage to the track it is a superficial slip not a rotational one.
 

Rapidash

Member
Joined
3 Sep 2013
Messages
686
Location
Torbaydos, Devon
For some reason, a 10 meter long section of track has been lifted near to the Sainsburies in Newton Abbot. And all the embankment under it.

There is also a honking great crane on the line to help with the building of the Kingskerswell Bypass right next to it. I'm going to guess there wont be any shuttles running there today!

The joy of travelling on the X46 continues! ;)
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,666
The controlled landslip is yet to happen i believe they are still trying to initiate it. The parapet wall repairs are really progressing, the Dawlish Cam has is showing the last stage directly in front of the camera. It appears from the other cameras that the breach is now up to track level.
 

Sir Felix Pole

Established Member
Joined
21 Oct 2012
Messages
2,172
Location
Wilmslow
For some reason, a 10 meter long section of track has been lifted near to the Sainsburies in Newton Abbot. And all the embankment under it.

There is also a honking great crane on the line to help with the building of the Kingskerswell Bypass right next to it. I'm going to guess there wont be any shuttles running there today!

The joy of travelling on the X46 continues! ;)

From the 'Herald Express'