Apparently the track is due to be lifted on the stub of the disused Tidenham branch, the southern end of the Wye Valley line. The latest update by A-B Connecting Communities, who are campaigning to create a cycle and walking path along the line, includes this:
To summarise Darren Bryce from the NDAC at Chepstow has been liaising with John Grimshaw from Greenways and Sustrans to complete a planning application for the section of the railway path from the A48 Bridge to Tintern including Tidenham Tunnel. This will be submitted at the end of January to FoDDC.
The railway track will be lifted from now to the end of July and the path works will be constructed with the aid of a voluntary work camp in September. (14th -22nd)
Sustrans is happy in principle to allow NDAC and other partners to use the land, but they are not allowed to sub-let the tunnel and will continue to lead on discussions with the Historic Railway Estate. Sustrans would like John Grimshaw to take on the development of the route for the next six months, after which time they will review progress.
The Forest of Dean Railway has now been given permission by Network Rail to remove the track from Dayhouse Quarry back to the main line junction. We think that this may take them two or three years to complete. At the end of that time Greenways hope to be able to work up a second phase to continue over the A48 to Wye Dean College, and thence to connect with the proposed new Wye Link Bridge to the National Shipyard Development where it will continue along a riverside walk to connect with the Wales Coastal Path.
The railway track will be lifted from now to the end of July and the path works will be constructed with the aid of a voluntary work camp in September. (14th -22nd)
Sustrans is happy in principle to allow NDAC and other partners to use the land, but they are not allowed to sub-let the tunnel and will continue to lead on discussions with the Historic Railway Estate. Sustrans would like John Grimshaw to take on the development of the route for the next six months, after which time they will review progress.
The Forest of Dean Railway has now been given permission by Network Rail to remove the track from Dayhouse Quarry back to the main line junction. We think that this may take them two or three years to complete. At the end of that time Greenways hope to be able to work up a second phase to continue over the A48 to Wye Dean College, and thence to connect with the proposed new Wye Link Bridge to the National Shipyard Development where it will continue along a riverside walk to connect with the Wales Coastal Path.