When I went past yesterday, there seemed to be a lot of leveling and laying of gravel/ballast at the former sidings site at Moreton cutting (between Didcot and Cholsey) and what looked like a load of pipes. Does anybody know what this is being done for? Looks like a storage area being created for some project.

Ok - an update for today. Those pipes look like the bases for OHE masts, so I guess it must be something to do with the electricifcation of the Paddington line
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,276
What you are calling 'pipes' are tubular steel piles.

As pictured in the 'NW electrification update' posted earlier...
 

mr_moo

Member
Joined
7 Sep 2009
Messages
649
Location
Cambridgeshire
The site is part of the OLE project. What it's for exactly I don't know as I'm not on that project, but that's who are doing it.

Interestingly, you can see the first part (excepting the stuff installed by the Reading station project) of the new GW OLE at Pangbourne. They have installed some trial piles in the Down Main cess.
 

mr_moo

Member
Joined
7 Sep 2009
Messages
649
Location
Cambridgeshire
FYI they are around the 41m 60ch mark to be precise. There's 10 of them. One of them even has a nice plaque on it commemorating it as the first pile for GW Electrification.

It's quite small and not much above ground level but it's there. :)
 