There is a requirement to install four timber sleepers between steel sleepered and concrete sleepered track.
Where timber and concrete sleepered track meet at a rail joint or weld the change in sleeper type should be at least two sleepers from the joint in the rail. So if putting new concrete bearer S&C into older timber sleepered plain line you would finish the last new panel with a couple of new timber sleepers.
There may also be an underbridge with only a thin layer of ballast between the underside of the sleepers and the bridge deck. More unusually in a tight circular tunnel it may be nessesary to chamfer off the underside of the sleeper ends.
What they should not be used for is shortended sleepers at catchpits, better to have the manufacturer cut the ends short on some concretes for you so all the sleepers match. Such sleepers were standard items in BR days, but need to be arranged specially these days.
--- old post above --- --- new post below ---
That said Network Rail have been down-specifying track for a while now, and I understand that they have pretty much stopped installing the NR60 CEN60 rail S&C.
Only the smaller sizes, now done in CEN56 vertical on concrete.