Multiple times across the last few days the District line has been suspended / severe delays to Wimbledon due to a signal failure at Wimbledon Park.

Is this going to be another repeat of the signal issues at Southfields last year where it takes forever to get resolved?

Given all of these issues, do you think that it’s now more than ever justified to bring back the planned CBTC signalling? Would they ever consider rolling it out without the ability for national rail trains to use the track up to East Putney?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Mojo

Forum Staff
Staff Member
Administrator
Joined
7 Aug 2005
Messages
21,168
Location
0035
The fault you’re talking about was resolved by NR early afternoon yesterday.

In an ideal world the entire line would be handed over to LU properly, with LU also operating the signalling and traction current and with trains operated in line with LU rules and procedures. NR trains could still operate over the line subject to their drivers receiving the appropriate training (such as on Chiltern which run down the Met). I don’t see this happening though.
 
Last edited:

Dstock7080

Established Member
Joined
17 Feb 2010
Messages
3,511
Location
West London
This particular fault, a defective block joint, would still exist if CBTC underlay was undertaken down to Wimbledon as track circuiting would be required (not as on the MET Harrow-Amersham main, Rayners Lane-Uxbridge).

(not - added)
 
Last edited:

GFE

Member
Joined
6 Jun 2024
Messages
131
Location
HA4
Note the solution used on the Met branches (to handle non CBTC equipped trains) will use Axle counters instead of track circuits.
The same seems to be the case with NR policy of conversion to "digital signalling"
Axle counters don't need Insulated block joints, electrical connections to rails or continuity bonds around rail joints (which are common failure points)
 

bluegoblin7

Established Member
Joined
10 May 2011
Messages
2,111
Location
JB
In this case though the fault absolutely would have still occurred under CBTC - the solutions planned for the Met top end and Wimbledon branches were not the same.

The Met is using a CBTC underlay - that is, the core signalling logic and interlocking is driven by the CBTC system, with colour lights and train stops added as additional features. LUL’s Seltrac implementation uses axle counters as a fallback for train detection through points and crossings anyway, there are simply more of them added to create rudimentary block sections for the detection and operation of ‘alien’ trains.

The Wimbledon (and Richmond) branches were planned to use a CBTC overlay - the existing interlocking would be retained as the primary signalling circuitry, with the CBTC system taking its data from this and communicating with the trains in the usual manner. This would therefore retain the existing track circuits and block joints, and never offered any major benefits over just retaining the existing colour lights - even CBTC trains would be restricted to the existing signalling fixed block sections.

Very much agreed with @Mojo that the best solution all round would be for the branch to properly transfer to LUL control, which would allow for the same solution as on the Met to be implemented.
 

eastrail

Member
Joined
25 Mar 2025
Messages
20
Location
London
I think I heard that the 1938 stock can still run on the Met after CBTC goes live. I assume it will use the same underlay as Chiltern trains and be limited to the Harrow-Amersham main line?
 

bluegoblin7

Established Member
Joined
10 May 2011
Messages
2,111
Location
JB
Yes, any train with fitted with a tripcock can operate on the Main Lines only, plus some selected crossovers and sidings, between Harrow and Amersham and Rayners Lane and Uxbridge following CBTC commissioning.

There are, however, logistical challenges in getting such trains on and off this part of the line, as well as overnight stabling. Not impossible, but not as simple as it is today.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,229
Multiple times across the last few days the District line has been suspended / severe delays to Wimbledon due to a signal failure at Wimbledon Park.

Is this going to be another repeat of the signal issues at Southfields last year where it takes forever to get resolved?

Given all of these issues, do you think that it’s now more than ever justified to bring back the planned CBTC signalling? Would they ever consider rolling it out without the ability for national rail trains to use the track up to East Putney?
No. Use of the track for ECS movements is regular and is essential to SWR‘s operations to and from the depot. It’s not just the relatively few passenger services that are there for route learning.
 

xtmw

Member
Joined
22 Aug 2022
Messages
189
Location
England
The west end of the District Line was descoped from the 4LM programme, on cost grounds, I assume as well as the technicalities of using a CBTC overlay
 

GFE

Member
Joined
6 Jun 2024
Messages
131
Location
HA4
So the originally proposed CBTC overlay would add more kit to existing signalling so inherently less reliable?
I think they were looking at improvement initiatives to help maintainers, but if NR are the maintainers, the motivation/priorities/response time need work.
 
Last edited:

Recessio

Established Member
Joined
4 Aug 2019
Messages
1,491
Location
London
When Wimbledon Park, Southfields and East Putney were transferred from Network Southeast to LU (for the nominal sum of £1) during privatisation in 1994, was any thought given to transferring ownership of the track itself?

And why was the implementation of CBTC planned to be an overlay rather than an underlay like on the Metropolitan? Is it just because it's still an NR line with NR signalling?
 

Mojo

Forum Staff
Staff Member
Administrator
Joined
7 Aug 2005
Messages
21,168
Location
0035
When Wimbledon Park, Southfields and East Putney were transferred from Network Southeast to LU (for the nominal sum of £1) during privatisation in 1994, was any thought given to transferring ownership of the track itself?
The track itself *was* transferred to LU. It is an LU asset and maintained by LU’s track teams, similarly for the physical infrastructure surrounding it (fencing, bridges, etc) which are all looked after by LU.
 

Dstock7080

Established Member
Joined
17 Feb 2010
Messages
3,511
Location
West London
When Wimbledon Park, Southfields and East Putney were transferred from Network Southeast to LU (for the nominal sum of £1) during privatisation in 1994, was any thought given to transferring ownership of the track itself?

And why was the implementation of CBTC planned to be an overlay rather than an underlay like on the Metropolitan? Is it just because it's still an NR line with NR signalling?
I don’t think NR wanted to give it up at that time as they had just modernised the signalling with the WARS scheme.
Yes, NR didn’t want to alter their signalling so it would have to be overlay.
 

Recessio

Established Member
Joined
4 Aug 2019
Messages
1,491
Location
London
The track itself *was* transferred to LU. It is an LU asset and maintained by LU’s track teams, similarly for the physical infrastructure surrounding it (fencing, bridges, etc) which are all looked after by LU.
Oh I see - so is it an LU track with NR signalling? Or LU signalling but that is compatible with NR? I'm trying to understand why it is different from the Metropolitan situation

== Doublepost prevention - post automatically merged: ==

I don’t think NR wanted to give it up at that time as they had just modernised the signalling with the WARS scheme.
Yes, NR didn’t want to alter their signalling so it would have to be overlay.
Ah that makes sense, thank you.
 

bluegoblin7

Established Member
Joined
10 May 2011
Messages
2,111
Location
JB
The Met uses NR-style four-aspect signalling - the actual underlying signalling principles are still to London Underground standards, which differ quite a bit from NR… although I appreciate this is splitting hairs somewhat. It is also somewhat irrelevant for CBTC given that it will be a brand new system and interlocking at the top end of the Met.

In summary:

Richmond (and north of Bakerloo): NR owned, NR signalled
Wimbledon: LUL owned, NR signalled
Met: LUL owned, LUL signalled
 

Top