It's either publicly available, in which case could either of you just confirm what's happening, or it shouldn't be public knowledge, in which case people who clearly work with the Timetable should be not saying anything, rather than vaguely hinting at things.
But it is not a binary situation.
WMT through London Northwestern Railway have made public statements about wanting to serve Manchester Airport from December 2026 through a proposed extension of Stafford to Crewe via Stoke to become Birmingham to Manchester Airport via Wolverhampton and Stoke.
In the NR Calendar of Milestone dates for Dec26 & May27 Timetables - can be found at the bottom of the NR Operational Rules webpage - Priority Date for December 2026 was 6th March 2026. This is the deadline for operator access proposals (bids) submission. D-40 is from the Network Code as this deadline is 40 weeks before the Timetable is due to run.
In referring to by mid-July (from the same document) I was referencing D-21 CIF Electronic Data available. Following this point the data should be visible on places like Realtimetrains. With consideration that public statements may be made before that time.
All this is publicly available, but does not include any confirmation of whether such an extension was included in a bid, nor that in a situation where they did bid for the extensions whether there are paths in the final WTT.
Therefore it is entirely correct for me to point out that some people may not be on a position to share information which they have knowledge of.
You are welcome for the breakdown, and please do not make implied accusations when I have not “vaguely hinted” at anything.