Wigan-Bolton electrification. Construction updates only please

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

themiller

Established Member
Joined
4 Dec 2011
Messages
1,382
Location
Cumbria, UK
Construction, energisation, commissioning, training then into service. Each of these stages have hold points to ensure that nothing’s been missed so in part you need to clarify which part of the electrification process you mean. I don’t know the programme but it’s the same process across industries.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,505
Location
Preston Lancs
Construction, energisation, commissioning, training then into service. Each of these stages have hold points to ensure that nothing’s been missed so in part you need to clarify which part of the electrification process you mean. I don’t know the programme but it’s the same process across industries.
I assume that it must mean the construction phase and even then there might be some minor snagging such as bridge parapets etc.
 

themiller

Established Member
Joined
4 Dec 2011
Messages
1,382
Location
Cumbria, UK
The likes of bridge parapets may be put on a reservations list but I feel that, because they’re a safety item, they may have to be complete before energisation.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,556
So if they electrify it at the end of the year, when will the electric service start?
As demonstrated by Stalybridge OLE, day 1 of entry into service will be dependent on signage installed for manual 769 power changeover. Presumably at Hindley or Ince.
As for when the timetable will be recast for EMU operation, that is a different matter.
 

Dspatula

Member
Joined
19 Dec 2019
Messages
182
Location
Manchester
As demonstrated by Stalybridge OLE, day 1 of entry into service will be dependent on signage installed for manual 769 power changeover. Presumably at Hindley or Ince.
As for when the timetable will be recast for EMU operation, that is a different matter.
I'd be surprised if anyone was willing to risk moving the power change over away from Bolton.
Making a guess based off Stalybridge I wouldn't have thought they'd be used before May 2025 timetable change.
There is a small chance it might end up being a 2051 or 2151 Wigan North Western terminator if testing is done before May. (Won't be the last service of the day as that's always a 158 when it runs.)
The Monday to Thursday night time closures still seem to be in place till the end of February on RTT at the moment.
 

GhostManDN91

Member
Joined
2 Oct 2022
Messages
146
Location
Wigan
Any idea if anything is happening to the road bridge at Westhoughton station (church street)? Last time I seen it looks like the bridge needs raising for the overhead wires but haven't heard anything on it.
 

desiro350

Member
Joined
10 Jan 2014
Messages
21
Location
Where the Southport and Ormskirk lines cross
Any idea if anything is happening to the road bridge at Westhoughton station (church street)? Last time I seen it looks like the bridge needs raising for the overhead wires but haven't heard anything on it.
There's enough clearance already as it's quite a high bridge so nothing needs doing to it. They've already put a post in the centre of the arch to carry the wires
 

GhostManDN91

Member
Joined
2 Oct 2022
Messages
146
Location
Wigan
There's enough clearance already as it's quite a high bridge so nothing needs doing to it. They've already put a post in the centre of the arch to carry the wires
Ah ok. When I went through on the train it looked like it needed raising but good to know it doesn't need modifying.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Post #352 from last year refers to work on Church Street bridge, to repair and raise the parapets. They wouldn't have done that if they were going to raise the bridge itself.
 

stan claire

Member
Joined
26 Feb 2022
Messages
119
Location
BuckshawParkwa
How long is this line closure for again (is it the 9 or 3 day closure) and how will they get the rest of the wires up after the closures? Assuming it'll be overnight and during weekend closures?
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,505
Location
Preston Lancs
How long is this line closure for again (is it the 9 or 3 day closure) and how will they get the rest of the wires up after the closures? Assuming it'll be overnight and during weekend closures?
Tie ins at both ends will mean work on the WCML and of course at Lostock Junction will result in power switched off.
 

EastMidlander

Member
Joined
13 Mar 2015
Messages
23
Location
Wigan
The line is closed until next Sunday. Post #709 contains a link to a newsletter with the planned date of works.
 

stan claire

Member
Joined
26 Feb 2022
Messages
119
Location
BuckshawParkwa
Tie ins at both ends will mean work on the WCML and of course at Lostock Junction will result in power switched off.
Is that also the reason for the Bolton - Preston closures on Sundays recently and the odd late-night Manchester - Blackpool service replaced by a bus? I don't understand why they couldn't run services between Windermere/Barrow or Blackpool, Preston and Blackrod (as there's a crossover north of the station I believe) or even run them to Buckshaw and then using the crossover to the south of the station shunt to go back northbound but it seems like Northern don't try hard enough to run trains where they can anymore and would rather bus replace throughout and divert others. Similarly, Atherton line services could've ran Manchester to Walkden as there is a crossover there and previously there were a couple weekends in 2022 where they ran Kirkby to Walkden because of (I believe) track replacement works at Salford Crescent
 

CAF397

Member
Joined
15 Sep 2010
Messages
1,095
Location
Lancashire
Tie ins at both ends will mean work on the WCML and of course at Lostock Junction will result in power switched off.
By the looks of the OLE at Lostock Jn, there's fresh copper on the Westhoughton lines just after a new isolating section just after the junction That must've been installed in the past week or so. Previously the OLE just continued until it terminated several stanchions away.

It's also not live, with one of those flashing blue light things.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,505
Location
Preston Lancs
The Tie-In area near Wigan NW has been installed and section-proved.
So basically, marrying 1973 vintage WCML north of Weaver Junction electrification to the Wigan-Bolton section even though that is not complete just yet.
So bumping to the top to remind silly me what has and has not been done!
 

AMD

Member
Joined
6 Dec 2017
Messages
773
A few photos of the work that has been done over the past week - the bridge at Ince is in, wires have been run out from Lostock junction to the approach of Crow Nest junction and the ramp up to the iron bridge at Hindley has been removed ahead of its lifting.
 

Attachments

  • 20240909_165426[1].jpg
    20240909_165426[1].jpg
    4.6 MB · Views: 202
  • 20240909_165425[1].jpg
    20240909_165425[1].jpg
    4.4 MB · Views: 202
  • 20240909_165023[1].jpg
    20240909_165023[1].jpg
    4.2 MB · Views: 198
  • 20240909_141108[1].jpg
    20240909_141108[1].jpg
    3.7 MB · Views: 196

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,505
Location
Preston Lancs
A few photos of the work that has been done over the past week - the bridge at Ince is in, wires have been run out from Lostock junction to the approach of Crow Nest junction and the ramp up to the iron bridge at Hindley has been removed ahead of its lifting.
Really good progress. Great to see. Thanks for posting.
 

Trainbike46

Established Member
Joined
18 Sep 2021
Messages
4,374
Location
belfast
A few photos of the work that has been done over the past week - the bridge at Ince is in, wires have been run out from Lostock junction to the approach of Crow Nest junction and the ramp up to the iron bridge at Hindley has been removed ahead of its lifting.
any idea why there are two bridges that close together?
 

CAF397

Member
Joined
15 Sep 2010
Messages
1,095
Location
Lancashire
The furthest one away carries the road across the railway, the nearer one is the access to the island station platform.

You can see why in the first photo.
 

Meerkat

Established Member
Joined
14 Jul 2018
Messages
9,276
The furthest one away carries the road across the railway, the nearer one is the access to the island station platform.

You can see why in the first photo.
Bit surprised they weren’t forced to make the station accessible if they were replacing the bridge.
 