Given all the work that went into adding 9 3/4 and 0, it seems odd to leave a gap between 9 and 10
To understand this, it helps to go back to before electrification in 1977.
The suburban trainshed had 3 platforms, 9-11 after the early 1970s renumbering. But platforms 10 and 11 were very short, long enough for 8*57' vehicles. There were double slip crossovers at the platform ends, with 8mph speed restrictions.
"Clearing the throat" was the 1977 pre-electrification remodelling. Platform 11 was removed so that platform 10 could be lengthened to take 8*64' trains. There were still double slip crossovers, though at 15nph not 8mph.
I can't recall exactly when platform 11 was reinstated, probably around the time of the Hitchin-Peterborough and Royston-Cambridge electrifications.
There were also safety concerns over how wide (then) platforms 10 and 11 were at the north end, as it carried an increased risk of someone falling under a train in crowded conditions/during rush hour.
This is right, I know from years of commuting experience! The country end of platforms 10/11 was very narrow.
It was removed in 2021 during the Kings Cross remodelling following a drop in the number of GN services going into the suburban platforms at Kings Cross post-Thameslink programme.
The "Kings uncrossed" 2021 remodelling has removed all of the double slip crossovers and further increased the speed limits. The short distance between the platform ends and Gasworks tunnel meant this couldn't be done without taking out one of platforms 10/11.
Was there an operational reason why the shorter platforms couldn’t have been used for shorter 5 car Hull Trains/Grand Central trains with some more suburban trains moving to the main train sheds?
Yes. 2*5 car trains can go in one platform in the main trainshed, but 2*8 car trains need 2 platforms in the main trainshed.