It's always been my understanding that if the railway need a structure for operational purposes they didn't need planning permission.
The Grade 1 or 2 listing trumps the permitted development rights I think.
As you are probably aware, the original Act allowing the particular railway will usually include clauses allowing alterations and additions in perpetuity for operational purposes.
Also, going back to the original question, NR have just clarified that the work includes removal of the two bridges that the reliefs currently use, and the insertion of the new Caversham Rd bridge, which as the pic in the press release shows is pretty massive - as it will allow for the expanded layout into the new relief line platforms 12-15 as well.
Plenty of civils and PW work there to help justify a longer than average closure, I think...
http://www.networkrailmediacentre.co.uk/Press-Releases/READING-BRIDGE-NEARS-COMPLETION-AHEAD-OF-XMAS-RAIL-IMPROVEMENT-WORK-15f2/SearchCategoryID-8.aspx